This document outlines the process for tracking comments in DrChecks for a federal construction project. The project involves demolishing fueling equipment and associated infrastructure at two Army National Guard sites at Fort Pickett, including underground storage tanks, fuel dispensers, canopies, and a truck fillstand. Bids for the project must be submitted by 20 September 2021 and is restricted to Women Owned Small Businesses. The selected contractor must begin work within 10 days of notice to proceed and complete demolition within 330 calendar days. Performance and payment bonds are required, and the estimated construction cost is between $500,000 and $1,000,000. The document details the procedures for government and contractor reviewers to enter, track, and resolve comments using the DrChecks system throughout the design process.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT F TRACKING COMMENTS IN DRCHECKS
1.0 General
The Government and Contractor shall set up the project in Dr Checks. Throughout the design process, the parties shall enter, track, and back-check comments using the DrChecks system. Government reviewers enter design review comments into DrChecks. Designers of Record shall annotate comments timely and specifically to indicate exactly what action will be taken or why the action is not required. Comments considered critical by the conference participants shall be flagged as such.
2.0 DrChecks Review Comments
The 6aetractor and the Government shall monitor DrChecks to assure all comments are annotated and agreed to by the designers and reviewers prior to the next submittal. The DrChecks comments and responses shall be printed and included in the design analysis for record.
2.1. Conference participants (reviewers) will expect coordination between Design Analysis calculations and the submitted design. Reviewers will also focus on the design submittal’s satisfaction of the contract requirements.
2.2. The Designers of Record shall answer each comment in DrChecks with a formal response prior to the next submittal, clearly indicating what action will be taken and what drawing/spec will change. Designers of Record are encouraged to directly contact reviewers to discuss and agree to the formal comment responses rather than relying only on DrChecks and review meetings to discuss comments. With the next design conference, reviewers will back-check answers to the comments against the submittal, in addition to reviewing additional design work.
2.3. Comments that, in the Contractor’s opinion, require effort outside the scope of the contract shall be clearly indicated as such in DrChecks. The Contractor shall not proceed with work outside the contract until a modification to the contract is properly executed, if one is necessary.
3.0 DrChecks Initial Account Set-Up
To initialize an office’s use of DrChecks, choose a contact person within the office to call the DrChecks Help Desk at 800-428-HELP, M-F, 8AM-5PM, Central time. This POC will be given an office password to distribute to others in the office. Individuals can then go to the hyperlink at https://www.projnet.org/projnet/binKornHome/index.cfm and register as a first time user. Upon registration, each user will be given a personal password to the DrChecks system.
3.1. Once the office and individuals are registered, the COE’s project manager or lead reviewer will assign the individuals and/or offices to the specific project for review. At this point, persons assigned can make comments, annotate comments, and close comments, depending on their particular assignment.
4.0 DrChecks Reviewer Role
The Contractor is the technical reviewer and the Government is the compliance reviewer of the DB designers design documents. Each reviewer enters their own comments into the Dr Checks system. To enter comments:
4.1. Log into DrChecks.
4.2. Click on the appropriate project.
4.3. Click on the appropriate review conference. An Add comment screen will appear.
4.4. Select or fill out the appropriate sections (particularly comment discipline and type of document for sorting) of the comment form and enter the comment in the space provided.
Attachment
F
Tracking
Comments in
DrChecks
4.5. Click the Add Comment button. The comment will be added to the database and a fresh screen will appear for the next comment you have.
4.6. Once comments are all entered, exit DrChecks by choosing “My Account” and then Logout.
5.0 DrChecks Comment Evaluation
The role of the designers of record is to evaluate and respond to the comments entered by the Government reviewers and by the Contractor. To respond to comments:
5.1. Log into DrChecks.
5.2. Click on the appropriate project.
5.3. Under “Evaluate" click on the number under “Pending".
5.4. Locate the comments that require your evaluation. (Note: If you know the comment number you can use the Quick Pick window on your home page in DrChecks; enter the number and click on go.)
5.5. Select the appropriate evaluation (concur, non-concur, for information only, or check and resolve) and add the response.
5.6. Click on the Add button. The evaluation will be added to the database and a fresh screen will appear with the next comment.
5.7. Once evaluations are all entered, exit DrChecks by choosing “My Account” and then Logout.
6.0 DrChecks Back-check
At the following design conference, participants will back-check comment annotations against newly presented documents to verify that the designers’ responses are acceptable and completed. The Contractor and Government reviewers shall either enter additional back-check comments, as necessary or close those that are resolved as a result of the design conferences:
6.1. Log into DrChecks.
6.2. Click on the appropriate project.
6.3. Under “My Backcheck” click on the number under “Pending”.
6.4. If you agree with the designer’s response select “Close Comment” and add a closing response if desired.
6.5. If you do not agree with the designer’s response or the submittal does not reflect the response given, select “Issue Open”, enter additional information.
6.6. Click on the Add button. The back-check will be added to the database and a fresh screen will appear with the next comment.
6.7. Once back-checks are all entered, exit DrChecks by choosing “My Account” and then Logout. The design is completed and final when there are no pending comments to be evaluated and there are no pending or open comments under back-check.