7-Addendum No 1 2025-08-05.pdf

PDF 3 MB Posted

Attached to
Thornton Road Low Pressure Sewer - Phase II
Solicitation number
US.196130
Issued by
Delaware County, Chicora Borough, Pennsylvania

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P:\Projects\THRN - THORNBURY\THRN 0310 - THORNTON ROAD SEWER\Phase 2 Extension\SPECIFICATIONS\Project

Specifications\Addendum No 1

THRNM 0310.02

BULLETIN ISSUING ADDENDUM NO. 1

THORNBURY TOWNSHIP

THORTON ROAD LOW PRESSURE SEWER – PHASE 2

CONTRACT NO. 2025-03

ISSUE DATE: AUGUST 5, 2025

The attention of all bidders is called to the following supplemental data amending the Contract

Documents of the above project. Each bidder shall consider this amendment in the preparation of their proposal and shall acknowledge same in the space provided thereon Page D-1.

The following modifications to the Contract Documents are hereby made:

A. CONTRACT DOCUMENTS:

Section C – Form of Bid

1. Page C-3, Added an Add Alternate and transferred Item 5 “Installation of Lateral to

Future Maintenance Building” from the Base Bid to the included Add Alternate. Bid item numbers were updated to reflect this change.

Enclosed is a revised Form of Bid

Section G – Construction Specifications

1. Section 01025 – Measurement and Payment

Page 01025-4, Revised item number 5 through 9 to reflect Alternate Bid; Added

Alternate Bid item.

Enclosed is a revised Section 01025.

B. CONTRACT DRAWINGS:

The following Contract Drawings have been updated to clarify Add Alternate Item 9.

CS1002 PROPOSED LOW PRESSURE PLAN & PROFILE

END OF ADDENDUM No. 1

C-3 P:\Projects\THRN - THORNBURY\THRN 0310 - THORNTON ROAD SEWER\Phase 2 Extension\SPECIFICATIONS\Project Specifications\Addendum No 1\00000 Contract General

Conditions_Addendum No. 1.doc

THORNTON ROAD LOW PRESSURE SEWER - PHASE 2

ITEM

NO.

ESTIMATED

QUANTITY DESCRIPTION

UNIT

PRICE

ESTIMATED

TOTAL

A. BASE BID:

1. 1 L.S. Mobilization/Demobilization. Price complete, in place for the lump sum of:

DOLLARS $

2. 1 L.S. Furnishing, Installation, Maintenance and Removal of Temporary Controls. Price complete, in place for the lump sum of:

3. 1,685 L.F. Installation of 2 &3-inch HDPE force main via

Directional Drilling. Price complete, in place per linear foot:

DOLLARS $ $

4. 340 L.F. Installation of 1-1/4-inch Laterals via Directional

Drilling. Price complete, in place per linear foot:

5. 120 L.F. Directional Drilling through Rock. Price complete, in place per linear foot:

6. 2 E.A. Installation of Air Release Valve/Air Release/Flushing Manhole. Price complete, in place per each:

ADDENDUM NO. 1

C-4 P:\Projects\THRN - THORNBURY\THRN 0310 - THORNTON ROAD SEWER\Phase 2 Extension\SPECIFICATIONS\Project Specifications\Addendum No 1\00000 Contract General

Conditions_Addendum No. 1.doc

THORNTON ROAD LOW PRESSURE SEWER - PHASE 2

ITEM

NO.

ESTIMATED

QUANTITY DESCRIPTION

UNIT

PRICE

ESTIMATED

TOTAL

7.

1 L.S. Restoration. Price complete, in place for the lump sum of:

8. 50 C.Y. Miscellaneous Excavation and Backfill with

PennDOT 2A stone. Price complete, in place per cubic yard:

TOTAL BASE BID FOR CONTRACT 2025-03

(Items 1 thru 8 Based on Estimated Quantities) $_______________

B. ADD ALTERNATE:

9. 660 L.F. Installation of Lateral to Future Maintenance

Building. Price complete, in place per linear foot:

TOTAL ALTERNATE BID FOR CONTRACT 2025-03

(Item 9 Based on Estimated Quantities) $

Job No. THRN 0310.02

MEASUREMENT AND PAYMENT 01025-4

P:\Projects\THRN - THORNBURY\THRN 0310 - THORNTON ROAD SEWER\Phase 2 Extension\SPECIFICATIONS\Project Specifications\Addendum No 1\01025

Measurement & Payment.doc the pipe to the depths/elevations indicated on the plans including excavation, shoring, protection and backfill of all entry and receiving pits; furnishing, installation and removal of all sheeting/shoring as required to comply with OSHA requirements; dewatering; stone bedding as required; backfill/compaction;

regrading, removal and legal disposal of excess excavated material; dust control;

shop drawings; testing; repair and/or replacement of any pipe that does not pass the required testing; as-built documentation, and all appurtenant labor, work, supervision, tools, equipment, materials, insurance/bonds, and all other items incidental thereto, in accordance with the manufacturer’s instructions and recommendations, all Local, State and Federal requirements and all generally accepted standards for this work.

Item 4: Payment for “Installation of 1¼-inch HDPE Laterals via Directional

Drilling” will be made at the price bid per linear foot in "Form of Bid". Payment for laterals will be for the actual number/length of laterals authorized and installed from the centerline of the force main to the right-of-way line. This item does not include the lateral to the future maintenance building. Unit price bid shall include: maintenance and protection of traffic; construction stakeout; coordination with the Township, PennDOT and all affected residents; coordination of lateral location with the individual property owners; clearing and grubbing; test pits to locate utilities to be crossed with the lateral pipe; protection of existing utilities;

backfilling and restoration; saw cutting of existing pavement (as necessary);

furnishing and installation of all pipe, connection to the 2 or 3-inch force main including shut off valves, fittings, connections, furnishing and installation of the lateral valve assembly; directional drilling including entry and receiving pits;

unclassified excavation; dewatering; stone bedding; backfilling; compaction;

installation of any required temporary paving; regrading, temporary restoration of all disturbed areas, including removal/replacement of any fences, utilities, wire, poles, lights, mailboxes, walkways, and any other item necessary to install the lateral; sheeting and shoring; removal and legal disposal of excess excavated material; dust control; and all appurtenant labor, work, supervision, tools, equipment, materials, insurance/bonds, and all other items incidental thereto, in accordance with the manufacturer’s instructions and recommendations, all Local, State and Federal requirements and all generally accepted standards for this work.

Item 5: Payment for “Directional Drilling through Rock” will be made at the price bid per linear foot in "Form of Bid". Payment will be for the actual length of the directional drilling completed through rock only. This cost shall be the additional cost associated with drilling through rock over and above the cost of Items No 3, 4 & 9. All rock encountered must be verified by the Township and/or Engineer as soon as it is encountered. Unit price bid shall include:

furnishing of the appropriate equipment/accessories required to drill through the rock encountered; furnishing of clear, thorough and complete documentation of the start and end of the rock encountered and the associated equipment, material and labor required to perform this work including a detailed log of the time rock

01025-5 MEASUREMENT AND PAYMENT

P:\Projects\THRN - THORNBURY\THRN 0310 - THORNTON ROAD SEWER\Phase 2 Extension\SPECIFICATIONS\Project Specifications\Addendum No 1\01025

Measurement & Payment.doc was encountered and the length of time spent per day drilling through the rock, and all appurtenant labor, work, supervision, tools, equipment, materials, insurance/bonds, and all other items incidental thereto, in accordance with the manufacturer’s instructions and recommendations, all Local, State and Federal requirements and all generally accepted standards for this work.

Item 6: Payment for “Installation of Air Release Valve Manhole and Air Release

Flushing Manhole” will be made at the unit price bid for each in "Form of Bid".

Payments will be for the actual number of air release manholes installed. Unit price bid shall include: maintenance and protection of traffic; construction stakeout; coordination with the Township, PennDOT and all affected residents;

clearing and grubbing; erosion and sedimentation control measures; saw cutting of existing pavement; frame and cover; furnishing and installing precast concrete manhole, including base, steps, adjustment rings, sleeves and gaskets, coatings and appurtenances; frame and cover; combination air release/vacuum valve, all piping, fittings, transition fittings; valves and supports; connections to the force main; utility location and protection of existing utilities; unclassified excavation;

sheeting and shoring; dewatering; stone foundation; backfilling; compaction;

regrading, removal and legal disposal of excess excavated material; dust control;

shop drawings; testing; as-built documentation; and all appurtenant labor, work, supervision, tools; equipment, materials, insurance/bonds, and all other items incidental thereto, in accordance with the manufacturer’s instructions and

Item 7: Payment for “Restoration” will be made at the lump sum price bid in

“Form of Bid.” The lump sum price bid shall include all work required to restore all disturbed areas to the pre-construction conditions that existed prior to the work including but not limited to lawn areas, roadway paving, driveways, pavement makings, signs, mailboxes, markers, pipes and all other items disturbed by the work; coordination with the Township, PennDOT and all affected residents;

removal and legal disposal of all excess material; regrading of affected areas to their original contours; installation of a minimum of 6-inches of topsoil; seeding, fertilizing and mulching of all disturbed areas; installation of erosion control fabric over all disturbed areas greater than 15-square feet; watering of all seed until a minimum 70% germination is achieved as determined by the Township; re-installation all signage; repair of any damaged paving including both the cartway of Thornton and Glen Mills Roads and any driveways; removal of all erosion and sedimentation controls and restoration of areas disturbed by the controls; shop drawings; and all appurtenant labor, work, supervision, tools; equipment, materials, insurance/bonds, and all other items incidental thereto, in accordance with the manufacturer’s instructions and recommendations, all Local, State and

Federal requirements and all generally accepted standards for this work.

MEASUREMENT AND PAYMENT 01025-6

P:\Projects\THRN - THORNBURY\THRN 0310 - THORNTON ROAD SEWER\Phase 2 Extension\SPECIFICATIONS\Project Specifications\Addendum No 1\01025

Measurement & Payment.doc

Item 8: Payment for “Miscellaneous Excavation and Backfill with PennDOT 2A

Stone” will be made at the unit price bid per cubic yard in "Form of Bid".

Payment will be made for each cubic yard of measured excavation and backfill as directed by the Township/Engineer. Unit price bid shall include: unclassified miscellaneous excavation as directed by the Township/Engineer, furnishing and installation of PennDOT 2A stone backfill within all road right-of ways;

compaction; protection of existing utilities; dewatering; removal and legal disposal of all excavated material; and all appurtenant labor, work, supervision, tools; equipment, materials, insurance/bonds, and all other items incidental thereto, in accordance with the manufacturer’s instructions and recommendations, all Local, State and Federal requirements and all generally accepted standards for this work..

Item 9: Payment for “Installation of Lateral to Future Maintenance Building” will be made at the price bid per linear foot in "Form of Bid". Payment will be for the actual length of lateral authorized and installed from the 2” x 1-1/4” reducer to the end of the lateral as indicated on the plan, or as revised by the Township. Unit price bid shall include: construction stakeout; coordination with the Township and

PennDOT; layout; review and coordination of the final lateral location with the

Township; test pits to locate utilities to be crossed; protection of existing utilities;

backfilling and restoration; furnishing and installation of all pipe; directional drilling of the pipe; connection to the 2” x 1-1/4”reducer; furnishing and installation of the in-line flushing manhole and lateral valve assembly at the end of the main; fittings, connections, directional drilling including entry and receiving pits; unclassified excavation; dewatering; stone bedding where required;

backfilling; compaction; regrading; temporary restoration of all disturbed areas,;

sheeting and shoring; removal and legal disposal of excess excavated material;

dust control; testing of the completed installation; and all appurtenant labor, work, supervision, tools, equipment, materials, insurance/bonds, and all other items incidental thereto, in accordance with the manufacturer’s instructions and

END OF SECTION

0+00

6.

6.

1+00

3.

3.

2+00

9.

9.

3+00

4.

4.

4+00

9.

9.

5+00

1.

1.

6+00

4.

4.

7+00

4.

4.

07 7+11.61 434.2 434.2246

6.

1.

6.

2.

6.

7.

4.

1 14" LATERAL FROM

FUTURE MAINTENANCE

BUILDING

4' COV. MIN.

(TYP)

IN LINE FLUSHING

MANHOLE W/AIR RELEASE

PROPOSED

2" X 1 14 "

REDUCER

IN LINE FLUSHING

MANHOLE

PROPOSED

2" FORCE MAIN

RETAINED AS RO

W

O F

BRO

ADM

EADO

W

S FARM

(33' W

IDE)

GLEN MILLS ROAD (SR4016)

(50' WIDE)

GLEN MILLS ROAD (SR4016)

(33' WIDE)

TBTBTBTBTBTBTBTBTBTBTBTBTB

UNDERGROUND ELECTRIC LINE (TO

BE ABANDONED)

APPROXIMATE LOCATION

FUTURE ELECTRIC LINE

V

12.25'

END OF LATERAL

PROVIDE CURB STOP

ASSEMBLY

1 14" LATERAL TO FUTURE

MAINTENANCE BUILDING

MANUFACTURED

45° BEND

1 14" SERVICE LATERAL

TO REST ROOM FACILITY

(± 140 Feet)

(SEE NOTE BELOW)

3" GATE

VALVE

MANUFACTURED

3"X3"X2" WYE

W/45° BEND

END WORK

5.0'

CURB STOP

ASSEMBLY

SEE NOTE 8 ON

DRWG CM1001

IN LINE

FLUSHING

MANHOLE

2"x1 14" REDUCER

(W/CAP)

AIR RELEASE

IN LINE FLUSHING

MANHOLE

±25' TO EOP

A

AIR

RELEASE

VALVE

5.0'

SEE NOTE 2

BELOW

A

4' COV. MIN.

(TYP)

0+00

8.

8.

8.

1+00

7.

7.

6.

1+99.26

6.

6.

MIN.

3' CLEARANCE

PROPOSED

2" FORCE MAIN

P:

\P ro jec ts\

TH

RN

TH

OR

NB

UR

Y\

TH

RN

- T

HO

RN

TO

N

RO

AD

S

EW

ER

\D

ES

IG

N\

PE

RM

IT

P

LA

NS

\C S1

- P

ER

M

IT

.d wg

PL

OT

TE

D:

4/

/2

1:

P M, B

Y:

Se da K or km az

PL

OT

ST

YL

E:

Pe nn on i N

CS

.st b

PR

OJ

EC

T

ST

AT

US

BY

N

O

D

AT

E R

EV

IS

IO

N

S

APPROVED BY

DRAWN BY

DRAWING SCALE

DATE

PROJECT

ALL DOCUMENTS PREPARED BY PENNONI ASSOCIATES

ARE INSTRUMENTS OF SERVICE IN RESPECT OF THE

PROJECT. THEY ARE NOT INTENDED OR REPRESENTED

TO BE SUITABLE FOR REUSE BY OWNER OR OTHERS ON

THE EXTENSIONS OF THE PROJECT OR ON ANY OTHER

PROJECT. ANY REUSE WITHOUT WRITTEN VERIFICATION

OR ADAPTATION BY PENNONI ASSOCIATES FOR THE

SPECIFIC PURPOSE INTENDED WILL BE AT OWNERS

SOLE RISK AND WITHOUT LIABILITY OR LEGAL

EXPOSURE TO PENNONI ASSOCIATES; AND OWNER

SHALL INDEMNIFY AND HOLD HARMLESS PENNONI

ASSOCIATES FROM ALL CLAIMS, DAMAGES, LOSSES AND

EXPENSES ARISING OUT OF OR RESULTING THEREFROM.

AL

L

D

IM

EN

SI

O N

S M

U

ST

B E

VE

R

IF

IE

D B

Y C

O N

TR

AC

TO

R

AN

D

O W

N

ER

M U

ST

B

E N

O

TI

FI

ED

O F

AN

Y

D

IS

C R

EP

AN

C

IE

S

BE

FO

R

E

PR

O C

EE

D

IN

G

W

IT

H W

O R

K

00 40' 80'

PR

O

PO

SE

D L

O W

P R

ES

SU

R E

PL

AN

PR

O

FI

LE

1"=40'

TH

O

R N

TO

N

R O

AD

L

O W

P R

ES

SU

R E

SE

W

ER

PH

AS

E

TH

O

R N

TO

N

R O

AD

TH

O R

N

BU

R Y, P A

TO

W N

SH

IP

D R

IV

E

C H

EY

N

EY

, P

A

TO

W

N

SH

IP

O

F

TH

O R

N

BU

R Y

THRN 0310.02

SK

06/22/2025

CF

CS1002

SHEET 4 6OF

PE

N

N O

N I A

SS

O

C

IA

TE

S

IN

C

H or iz on D riv e, S ui te

Ki ng o f P ru ss ia

, P A

T

0.

7.

F

0.

7.

NOTES:

1. LATERAL TO THE REST ROOM BULDING TO BE INSTALLED TO WITHIN 20 FEET

OF BUILDING.

2. CONTRACTOR TO LOCATE EXISTING UNDERGROUND CONDUIT VIA TEST PITS

AS REQUIRED A MINIMUM OF 3 WEEKS PRIOR TO COMMENCEMENT OF ANY

INSTALLATION. MAIN TO BE LOCATED AT ALL LOCATIONS WHERE CONDUIT IS

MARKED AND WITHIN 6-FEET OF THE PROPOSED FORCE MAIN/LATERAL TO

MAINTENANCE BUILDING.

3. ALIGNMENT OF 1 14"- INCH LATERAL TO MAINTENANCE BUILDING MAY BE

ADJUSTED SLIGHTLY TO AVOID SURFACE FEATURES AND MAXIMIZE

DISTANCE FROM TOP OF SLOPE.

BID PLANS

BID ALTERNATE

(ALTERNATE)

(ALTERNATE)

(ALTERNATE)

/0

5/

A D

D E

D B

ID

A

LT

E

R N

A T

E C

F

BID ALTERNATE

File details come from the government source that posted it. Updated .