02 - Surplus Canal-IFB-Project Manual Book 2.pdf

PDF 10 MB Posted

Attached to
Salt Lake City Airport Surplus Canal Relocation
Solicitation number
SLCDA-DCM-542715
Issued by
Salt Lake County, Salt Lake City, Utah

About this file

This is a Project Manual Book 2 containing technical specifications for the Surplus Canal Relocation project at Salt Lake City International Airport, a heavy civil construction project located landside south and west of the center runway adjacent to the newly constructed South Employee Parking Lot. The project involves relocating the Surplus and North Point canals to the south of the new parking area, parallel to the existing TRAX line, and includes earthwork in compliance with U.S. Army Corps standards, water management, a storm water pump station and detention basin, and utility relocations. The specifications are organized into multiple sections covering sustainability measures, temporary pollution and erosion control, mobilization, preparation and removal of existing pavements, safety and security, contractor staging areas, dewatering, shoring, survey work, and construction signage. The contract is issued for bid as Project No. 542715 (Contract No. CA-009069) with an effective bid date of November 6, 2026, and encompasses comprehensive technical requirements across divisions for concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, equipment, plumbing, HVAC, electrical, communications, safety systems, earthwork, exterior improvements, site utilities, waterway and marine construction, and process interconnections.

The technical specifications establish extensive performance requirements including sustainability measures aligned with Envision v3 certification targeting a Silver level award, with specific requirements for 15 percent recycled/reused/renewable materials, 50 percent construction waste diversion, implementation of at least two energy conservation strategies, and three water conservation strategies. The project requires a Contractor Sustainability Representative and submission of multiple plans including a Sustainability Action Plan, Construction Management Plan, Construction Waste Management Plan, Health, Safety & Security Plan, Sustainable Procurement Policy, and Soil Protection Plan. Mobilization payments are structured on a lump sum basis with phased disbursements tied to percentage of contract completion, with up to 8 percent of the total bid reserved for mobilization costs and payment upon final project acceptance. The contract mandates strict safety and security compliance including appointment of a Contractor Safety and Security Officer, implementation of detailed work sequence schedules, provision of gate guards with TSA security training, flagging operations for active taxiway crossings, and coordination with Airport Operations. Payment is structured as lump sum items for most work categories with measurement by linear feet, square yards, each, or tons as applicable to specific removal and construction tasks.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SALT LAKE CITY INTERNATIONAL AIRPORT

PROJECT MANUAL FOR

SURPLUS CANAL RELOCATION

PROJECT NO. 542715

CONTRACT NO. CA-009069

Book 2 of 3

DESIGN & CONSTRUCTION MANAGEMENT

DIVISION

PAGE LEFT INTENTIONALLY BLANK

TECHNICAL SPECIFICATIONS

542715

TS-1

SURPLUS CANAL RELOCATION

ISSUED FOR BID

PROJECT NO. 542715

TABLE OF CONTENTS

Section Description No. of

Pages

C-101 SUSTAINABILITY MEASURES (ISI ENVISION) 10

C-102

TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND

SILTATION CONTROL

C-105 MOBILIZATION 4

P-101

PREPARATION/REMOVAL OF EXISTING PAVEMENTS AND

MISCELLANEOUS ITEMS

P-102 SAFETY AND SECURITY 8

P-110 CONTRACTOR'S STAGING AREA 2

P-115 DEWATERING 4

P-116 SHORING 4

P-130 SURVEY 6

P-148

CONSTRUCTION SIGNS, BARRICADES, WARNING LIGHTS, GATE

GUARDS, AND FLAGGING OPERATIONS

P-149 STREET AND PAVEMENT CLEANING 2

P-151 CLEARING AND GRUBBING 2

P-153 CONTROLLED LOW-STRENGTH MATERIAL (CLSM) 4

P-157 GROUND STABILIZATION FABRIC 2

P-306 LEAN CONCRETE BASE COURSE 10

P-605 JOINT SEALANTS FOR CONCRETE PAVEMENTS 6

P-610 CONCRETE FOR MISCELLANEOUS STRUCTURES 8

D-701 PIPE FOR STORM DRAINS AND CULVERTS 8

D-751

MANHOLES, CATCH BASINS, INLETS, AND OTHER UTILITY

STRUCTURES

D-754 CONCRETE GUTTERS, DITCHES, AND FLUMES 4

F-162 CHAIN-LINK FENCE 4

T-905 TOPSOIL 4

DIVISION 01 GENERAL REQUIREMENTS

01 20 00

SOUTH PUMP STATION NO. 8 MEASUREMENT AND PAYMENT

PROCEDURES

01 45 00 QUALITY CONTROL 14

01 53 00 TEMPORARY FLOOD PROTECTION 4

DIVISION 03 CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE 26

DIVISION 04 MASONRY

04 22 00 CONCRETE UNIT MASONRY 18

DIVISION 05 METALS

05 05 10 METAL GALVANIZING 2

05 05 19 POST-INSTALLED CONCRETE ANCHORS 6

542715

TS-2

05 05 23 WELDING 10

05 12 00 STRUCTURAL STEEL FRAMING 12

05 31 00 STEEL DECKING 6

05 50 10 METAL FABRICATIONS 12

05 51 00 METAL STAIRS 4

05 52 13 PIPE AND TUBE RAILINGS 10

05 53 13 BAR GRATINGS 8

DIVISION 06 WOOD

06 10 53 MISCELLANEOUS ROUGH CARPENTRY 6

06 20 23 INTERIOR FINISH CARPENTRY 6

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 13 26 SHEET WATERPROOFING 10

07 14 16 COLD FLUID-APPLIED WATERPROOFING 8

07 19 00 WATER REPELLENTS 8

07 21 00 THERMAL INSULATION 4

07 21 19 FOAM IN PLACE THERMAL INSULATION 6

07 22 00 ROOF AND DECK BOARD INSULATION 4

07 26 00 VAPOR RETARDERS 4

07 50 00 SINGLE PLY ROOFING 12

07 60 00 FLASHING AND SHEET METAL 6

07 72 00 ROOF ACCESSORIES 6

07 92 15 JOINT SEALANTS 12

DIVISION 08 OPENINGS

08 11 19 STAINLESS STEEL DOORS AND FRAMES 10

08 34 83 FLOOR DOORS 4

08 37 23 OVERHEAD COILING DOORS 10

08 71 00 HARDWARE 8

08 91 00 STATIONARY BLADE WALL LOUVERS 8

DIVISION 09 FINISHES

09 96 05 HIGH-PERFORMANCE COATINGS 8

DIVISION 10 SPECIALTIES

10 14 23 PANEL SIGNAGE 6

10 26 00 WALL AND DOOR PROTECTION 6

10 44 16 FIRE EXTINGUISHERS 4

DIVISION 11 EQUIPMENT

11 81 29 HORIZONTAL FALL PROTECTION 6

DIVISION 14 CONVEYING EQUIPMENT

14 60 00 HOISTS AND CRANES 4

DIVISION 22 PLUMBING

22 14 29 SUMP PUMPS 4

DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 13 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 4

23 05 29 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 8

23 05 48 VIBRATION AND SEISMIC CONTROLS FOR HVAC 8

23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 4

542715

TS-3

23 34 23 HVAC POWER VENTILATORS 6

23 82 39.16 PROPELLER UNIT HEATERS 6

DIVISION 25 INTEGRATED AUTOMATION

25 01 25 BUILDING AUTOMATION SYSTEM 10

25 01 30 BAS INTERFACE REQUIREMENTS 4

25 02 05 FIELD DEVICES FOR BUILDING AUTOMATION SYSTEM 16

25 08 00 COMMISSIONING OF BUILDING AUTOMATION SYSTEM (BAS) 8

DIVISION 26 ELECTRICAL

26 05 00 BASIC ELECTRICAL MATERIALS AND METHODS 2

26 05 19 WIRES AND CABLES 6

26 05 26 GROUNDING AND BONDING 6

26 05 33 RACEWAYS 8

26 05 48 SEISMIC RESTRAINT FOR ELECTRICAL WORK 6

26 09 13 ELECTRICAL POWER MONITORING 20

26 22 00 TRANSFORMERS 6

26 24 16 PANELBOARDS 8

26 27 26 WIRING DEVICES 4

26 29 00 MOTOR CONTROLLERS 8

26 29 23 VARIABLE-FREQUENCY DRIVES 10

26 32 14 ENGINE GENERATORS 20

26 36 01 TRANSFER SWITCHES 10

26 43 00 SURGE PROTECTIVE DEVICES 4

26 51 00 LIGHTING 6

DIVISION 27 COMMUNICATIONS

27 05 10 COMMON WORK RESULTS FOR COMMUNICATIONS SYSTEMS 28

27 05 27 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS 12

27 05 34 PATHWAYS FOR COMMUNICATIONS SYSTEMS 12

27 05 54 IDENTIFICATION FOR COMMUNICATIONS SYSTEMS 22

27 08 10 TESTING OF COMMUNICATIONS SYSTEMS 10

27 11 10 COMMUNICATIONS EQUIPMENT ROOM FITTINGS 6

27 13 10 COMMUNICATIONS BACKBONE CABLING 24

27 15 10 COMMUNICATIONS HORIZONTAL CABLING 12

27 21 00 DATA COMMUNICATIONS NETWORK EQUIPMENT 14

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

28 05 10 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 16

28 13 10 CARD ACCESS SECURITY SYSTEM (CASS) 24

28 23 10 VIDEO SURVEILLANCE SYSTEM (VSS) 20

DIVISION 31 EARTHWORK

31 05 19.13 GEOTEXTILES FOR EARTHWORK 6

DIVISION 32 EXTERIOR IMPROVEMENTS

32 15 00 AGGREGATE BASE COURSE AND SURFACING 10

32 92 19 SEEDING 8

32 93 10 BIOSWALE AND LANDSCAPE 14

542715

TS-4

DIVISION 33 SITE UTILTIES

33 05 01 HIGH DENSITY POLYETHYLENE PIPE (AWWA C906, MODIFIED) 16

33 05 07 POLYVINYL CHLORIDE PIPE 4

33 08 00 COMMISSIONING OF WATER UTILITIES 6

33 11 00 WATER DISTRIBUTION AND TRANSMISSION 10

33 12 16 WATER VALVES 6

33 13 00 DISINFECTION 4

33 31 00 SANITARY SEWERAGE SYSTEMS 8

33 47 13 POND AND RESERVOIR LINERS 6

33 51 00 GAS LINE EXCAVATION AND BACKFILL 4

33 51 42

UNDERGROUND DUCT BANKS AND CONDUITS FOR COMMUNICATIONS

SYSTEMS

33 51 43 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS 18

DIVISION 35 WATERWAY AND MARINE CONSTRUCTION

35 31 19.40 STONE REVETMENTS 18

35 41 00

EXCAVATION AND EMBANKMENT FOR LEVEE, CANAL, DETENTION

BASIN, AND APPURTENANT STRUCTURE CONSTRUCTION

DIVISION 40 PROCESS INTERCONNECTIONS

40 05 07 HANGERS AND SUPPORTS FOR PROCESS PIPING 8

40 05 19 DUCTILE IRON PROCESS PIPE 6

40 05 31 THERMOPLASTIC PROCESS PIPE 8

40 05 51 COMMON REQUIREMENTS FOR PROCESS VALVES 6

40 05 52 SLIDE AND FLUME GATES 6

40 05 57 ACTUATORS FOR PROCESS VALVES AND GATES 6

40 05 59.33 CAST IRON SLIDE GATES 8

40 05 61 GATE VALVES 4

40 05 65.23 SWING CHECK VALVES 4

40 05 78.29 COMBINATION AIR VALVES FOR WASTEWATER SERVICE 4

40 70 00 AUTOMATIC SAMPLER 8

40 71 00 FLOW MEASUREMENT 8

40 72 00 LEVEL MEASUREMENT 6

40 73 13 PRESSURE AND DIFFERENTIAL PRESSURE GAUGES 6

40 73 36 PRESSURE AND DIFFERENTIAL PRESSURE SWITCHES 4

DIVISION 43

PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND

STORAGE EQUIPMENT

43 05 20 COMMON WORK RESULTS FOR LIQUID HANDLING EQUIPMENT 8

43 23 31 VERTICAL CENTRIFUGAL PUMPS 6

43 25 13 SUBMERSIBLE CENTRIFUGAL PUMPS 8

TECHNICAL SPECIFICATIONS SECTION C-101

Salt Lake City International Airport C-101-1 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

SECTION C-101

SUSTAINABILITY MEASURES (ISI ENVISION)

101-1 GENERAL

101-1.1 Description. Salt Lake City (Owner) is committed to the integration of sustainability into the

Surplus Canal Relocation project. This Specification is a Contract Document and is intended to supplement the Construction Contract between the Owner and its Contractor. References herein to the

“Project Team” refers to representatives of Salt Lake City, the Consultant, and the Contractor.

In October 2024, the Salt Lake City published Section 56-3-6: Sustainable Infrastructure: “City staff shall evaluate, implement, and seek certification from at least one approved third-party certification program, to the extent practicable, to ensure environmental justice and sustainable infrastructure best practices are incorporated into all capital infrastructure projects that meet the thresholds defined in sub-section (F), including new infrastructure and major renovations proposed by the City and its agencies on City owned properties.”1

101-1.2 Related Bid Documents. Comply with the Contract, Drawings, Technical Specifications, and

SLC requirements. Where conflicts arise, the more stringent sustainability requirement shall govern unless directed otherwise by SLC.

101-1.3 Definitions.

a. Diverted Waste. Materials sent to reuse, recycling, or salvage rather than landfill.

b. Recycled Content. Post-consumer and/or pre-consumer (post‑industrial) content as declared by the manufacturer.

c. Renewable Materials. Materials derived from resources that can naturally regenerate within a short timeframe; provide minimal long-term depletion of natural resources.

d. Potable Water. Water that is safe for human consumption, meaning it meets all applicable drinking water quality standards set by public health authorities (e.g., drinking, cooking, bathing).

e. Non‑Potable Water. Water that is not safe for human consumption because it does not meet drinking water quality standards, however may be safely used for other activities (e.g., dust suppression, irrigation, toilet flushing).

f. Commingled Recycling. Mixed construction debris sent to a facility that performs material recovery and provides recovery rates.

101-1.4 Envision Verification. The City is pursuing Envision Verification for this Project. Envision, put forth by the Institute for Sustainable Infrastructure (ISI), is a rating system and framework that enables a holistic examination of the sustainability and resiliency of infrastructure projects. Envision includes 64 sustainability and resilience indicators (credits) organized into five categories: Quality of Life, Leadership, Resource Allocation, Natural World, and Climate and Resilience. Credits are assessed using a predetermined point system, and then are added together to receive a total Envision score. Each credit has multiple levels of achievement, which are assessed to determine how well the project addresses sustainability and resiliency. The Envision score is presented as a percentage of the achieved points

1 Salt Lake City, 56-3-6: Sustainable Infrastructure, effective Date: Beginning January 1, 2024, https://codelibrary.amlegal.com/codes/saltlakecityut/latest/saltlakecity_manual_ut/0-0-0-11544 (accessed 2/5/2025).

Salt Lake City International Airport C-101-2 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026 compared to the applicable points. To receive verification, projects must achieve a minimum percentage of the total applicable Envision points. Project recognition has four award levels:

1. Verified: 20%

2. Silver: 30%

3. Gold: 40%

4. Platinum: 50%

This Project shall be designed and constructed to seek an Envision v3 Silver level award. The City intends that the Project Team, to the maximum extent possible, utilize sustainability principles and

Envision guidelines to facilitate design and construction of the Project. Specific sustainability requirements and guidance are identified in this Exhibit.

101-1.5 Sustainability Representative. The Contractor shall provide personnel with knowledge and experience of the Sustainability Tools selected for inclusion in the Project. The Contractor shall designate a person as its Sustainability representative for purposes of implementing and tracking Envision requirements.

Sustainability Commitment. The Contractor shall review and sign the Project Sustainability

Commitment (Attachment 1 - Contractor Project Sustainability Commitment). The commitment should be signed by a supervisor of the Contractor team as well as by the Sustainability representative.

101-2 SUBMITTALS

101-2.1 Preconstruction. The following documents are due before first Payment Application and no later than 14 days after NTP. The requirements of each of these submittals is provided in PLANNING

REQUIREMENTS section:

• Sustainability Action Plan (SAP)

• Construction Management Plan (CMP)

• Construction Waste Management Plan (CWMP)

• Health, Safety & Security Plan (HSSP)

• Sustainable Procurement Policy (SPP)

• Soil Protection Plan

• Spill Prevention and Response Plan.

• Attachment A signed: Contractor Project Sustainability Commitment (by SR and a Contractor supervisor).

101-2.2 Monthly. The following documents are due to the SLC Project Manager or his/her designee monthly:

a. Monthly Sustainability Tracking Form (Attachment B, Monthly Sustainability Tracking Form) covering all measures in this Section, with supporting evidence (tickets, invoices, certifications, utility data, fuel logs, photos), specifically:

b. Water Use Tracking Form (Attachment C, Water Use Tracking Form), where applicable. This form is intended for completion in Microsoft Excel (request active files if not provided at receipt of award).

Salt Lake City International Airport C-101-3 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

c. Total tonnage of Construction and Demolition waste disposed of and total tons recycled every month using the Construction Waste Diversion Form (Attachment D) or Recycled Materials tracking within Attachment B (Monthly Sustainability Tracking Form) (request active files if not provided at receipt of award).

d. Fuel log to track fuel use on a monthly basis to include fuel type, off-road vehicles or equipment, vehicle or equipment EPA tier rating, gallons used, and strategies conducted to reduce fuel use

(Attachment B – Monthly Sustainability Tracking Form) (request active files if not provided at receipt of award).

101-2.3 Closeout or Prior. Consolidated sustainability report summarizing: recycled/reused/renewable content; waste diversion (Attachment D and Attachment B); energy strategies with calculations; water strategies with calculations (Attachment C); copies of key certifications and chain‑of‑custody documents;

and supporting documentation consistent with Attachment E (Example Calculation Worksheets).

101-3 PLAN REQUIREMENTS

101-3.1 Sustainability Action Plan (SAP). The Contractor shall submit a SAP indicating how each of the Contract details in this specification will be met. The Project SAP should be a compilation of the

PERFORMANCE REQUIREMENTS in this Section. The Project SAP should, at a minimum, include how each requirement will be met, including deliverables, responsible parties, and start/finish milestones.

Identify the declared calculation basis (cost, weight, or volume) to be used consistently for all relevant metrics.

101-3.2 Construction Management Plan (CMP). The Contractor shall create and submit a Construction

Management Plan. The management plan shall address the following:

• Management plan to mitigate noise

• Safety, wayfinding

• Access/mobility for pedestrians and vehicles during construction

• Distracting or intrusive lighting

• Methods to monitor performance and mechanisms for reporting construction impacts

• Methods to avoid accidental introduction of invasive species.

101-3.3 Construction Waste Management Plan (CWMP). The Contractor shall create and submit a plan to achieve ≥50% of construction waste materials must be diverted through recycling, reuse, and/ or salvage. The plan should identify the materials to be diverted from disposal and whether the materials will be sorted on site or commingled. Tracking and reporting shall be consistent with Attachment D –

Construction Waste Diversion Form and summarized monthly in Attachment B – Monthly Sustainability

Tracking Form.

101-3.4 Health, Safety & Security Plan (HSSP). The Contractor shall create an HSSP that addresses the following:

• Safety or security training requirements for personnel

• Comprehensive security plan to protect workers, the public, and sensitive information

• Health and/or well-being programs

• Safety Rewards Program to reward outstanding safety performance.

Salt Lake City International Airport C-101-4 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

Documentation may include providing a list of training requirements, examples of training (e.g., videos, PowerPoint presentations, etc.), and an attendance log for all employees participating in the trainings;

incident reporting workflows and templates/forms; worker/public/security protections; health and wellbeing programs (e.g., free health screenings, health workshops); safety recognition and/or incentive programs (e.g., events during Construction Safety Week).

101-3.5 Sustainable Procurement Policy (SPP). The Contractor shall create a Sustainable Procurement

Policy that includes commitments where practical, and without impacting the overall schedule of the project, to identify and select manufacturers that implement sustainable practices, including a well-defined process for selecting suppliers and/or manufacturers of materials, supplies, and equipment based on environmental practices and social responsibility. Procurement practices should meet or exceed the standards below:

• Environmental management systems consistent with ISO (International Organization for

Standardization) 14001.

• Project-Specific type III Environmental Product Declaration conforming to ISO 14025, 14044 for

Final Product(s) of P-401 Asphalt Mix Pavement.

• Project-Specific type III Environmental Product Declaration conforming to ISO 14025, 14044 for

Final Product of P-501 Cement Concrete Pavement.

• Third-party verified sustainability program (e.g., Forest Stewardship Council (FSC), Green Seal, EcoLogo, Underwriters Laboratory, National Biosolids Partnership (NBP), Concrete

Sustainability Council (CSC), etc.)

• Third-party verified corporate sustainability report consistent with the Global Reporting Initiative

(GRI) Sustainability Report or equivalent.

In addition, the Contractor, to the greatest extent possible, should include in material purchasing agreements, a waste reduction provision requesting that materials and equipment be delivered in packaging made of recyclable material, that they reduce the amount of packaging, and that packaging be taken back for reuse or recycling.

The Contractor shall incorporate sustainability practices into the on-site field office. Such practices should include but not be limited to: collecting and sorting waste materials for recycling, maximizing electronic records while minimizing use of paper, providing sustainability training to office occupants, eliminating the use of single-use plastics to the extent practicable, instituting a “no-idling” policy on the job site.

101-3.6 Soil Protection Plan. The Contractor shall preserve the composition, structure, and function of site soils by minimizing disruption of soil and restoring soil health where possible. At least 95% of post-construction vegetated areas on site, including areas disturbed by development, will be restored to a condition that can support healthy plant and tree growth. Soils must be reused for functions comparable to their original function. The Plan must identify special landscape features and include best management practices to prevent soil disruption within their protective zones.

101-3.7 Spill Prevention and Response Plan. The Contractor shall adhere to a spill and leak prevention and response plan during construction of the Project to reduce the risk of surface water and/or

Salt Lake City International Airport C-101-5 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026 groundwater quality degradation. Refer to the Special Conditions and the Construction Safety and

Security Compliance Manual for the Salt Lake City International Airport.

101-3.8 Ecological Value Sites. The Contractor shall ensure that areas of high ecological value on site are protected during construction. The sites will be identified by the project team and communicated to the Contractor.

101-4 PERFORMANCE REQUIREMENTS

101-4.1 Reused/Recycled/Renewable Materials (≥15%). Use at least 15% (by declared basis: weight, volume, or cost) of total permanent materials as recycled, reused, and/or renewable. Include any onsite reuse of existing structures or materials. Track each product with: manufacturer, product name, quantity

(consistent with declared basis), and recycled content (%) split by post‑consumer and pre‑consumer where available. Declare and maintain one calculation basis across the project. Include the proposed strategy to meet this requirement as part of 101-3.1 Sustainability Action Plan (SAP) submittal. Tracking shall be documented and reported monthly using Attachment B – Monthly Sustainability Tracking Form and supported by calculations consistent with Attachment E.

101-4.2 Construction Waste Diversion (≥50%). Divert at least 50% of Construction, Demolition &

Land‑Clearing (CD&L) waste from landfill. Track by category and report totals generated and totals diverted, with diversion % = (Diverted ÷ Generated) × 100 using the C&D Waste Diversion Form

(Attachment D, Construction Waste Diversion Form) to report actual material streams and diversion quantities/rates. Provide scale tickets or volumetric conversions; for commingled waste, provide facility recovery certifications and monthly summaries. CD&L waste materials that can be salvaged, reused or recycled include, but are not limited to, the following:

• Soil

• Asphalt

• Concrete

• Electrical Equipment including conduit, conductors and lights

• Metals

• Shipping and packaging materials, e.g., cardboard and wood pallets, field office waste, including office paper, aluminum cans, glass, plastic, and office cardboard

Include the proposed strategy to meet this requirement as part of 101-3.1 SAP submittal.

101-4.3 Construction Energy Consumption (≥2 strategies). The Contractor shall conduct one or more planning reviews to identify and analyze the potential for reducing energy consumption during construction. The Contractor shall document the number of energy conservation strategies implemented during construction, at least two are required. Strategies include:

• Tier IV construction equipment or Tier III with Best Available Technology (BAT) for at least

75% of non-road equipment fleet greater than 50 horsepower;

• Alternative fuels in heavy equipment such as biodiesel for at least 5% of total fuel consumption;

• Hybrid or fully electric project vehicles for at least 50% of fleet;

• Electrified equipment for at least 20% of equipment (vs. gas or diesel engines);

• Employee commuting programs with incentives (shuttles to transit, ride- share programs, biking facilities, etc.);

Salt Lake City International Airport C-101-6 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

• Reduce purchased energy for workstations (construction trailer/ office energy) by 30% for two of the following: (1) lighting; (2) HVAC; (3) plug loads;

• Purchase green power (RECs) for 30% of workstation energy consumption;

• Offset electrical consumption by generating 5% renewable energy on site (e.g., solar panels on trailer complex, solar-powered temporary light plant, solar powered cameras and variable message sign boards); and

• Reduce overall fuel consumption by 10% through improved planning and logistics.

Include the proposed strategy to meet this requirement as part of 101-3.1 SAP submittal. Tracking shall be documented in Attachment B – Monthly Sustainability Tracking Form with supporting calculations consistent with Attachment E.

101-4.4 Construction Water Consumption (≥3 strategies). The Contractor shall conduct one or more planning reviews to identify and analyze options for reducing water consumption during construction.

The Contractor shall document the number of water conservation strategies implemented during construction, at least three are required. Include a calculation of potable water saved for each strategy as compared to not implementing the strategy during the construction period. Strategies include:

• High‑efficiency fixtures in trailers/offices (≥40% usage reduction).

• Active monitoring/management using the Water Use Tracking Form to detect leaks and inefficiencies.

• Reduce embodied water by reducing waste material (≥10% reduction in new material quantities entering the site).

• Dust suppression alternatives, such as dry agents (≥50% water reduction in water usage due to alternative controls).

• Concrete curing alternatives (≥50% reduction in water usage due to alternative controls).

• Truck tire wash station alternatives (≥50% reduction in water usage due to alternative controls).

• Product selection that reduces potable water use by >25% for permanent/temporary materials.

• Stormwater harvesting (≥40% savings by using harvested stormwater instead of potable water).

• Greywater/wastewater reuse (≥40% reuse).

• Dewatering water reuse (≥40% reuse/recycling).

Include the proposed strategy to meet this requirement as part of 101-3.1 SAP submittal.

101-5 MEETING COORDINATION

101-5.1 Construction Sustainability Kick-Off Meeting. A Sustainability Kick-Off meeting will be held within fourteen (14) days after execution of the Construction Contract. The meeting will review appropriate Envision requirements and action plans for meeting requirements. The Contractor’s designated Sustainability representative shall attend this charette.

101-5.2 Coordination Meetings. Coordination meetings shall be held on a regular basis from the start of construction and continue throughout construction. The meeting agenda should include, at a minimum (1)

Salt Lake City International Airport C-101-7 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026 a review of the sustainability measures and tracking progress, and (2) a health and safety discussion with any updates or incident reporting.

101-6 TRACKING, CALCULATIONS & DOCUMENTATION

101-6.1 Calculations. The Contractor may rely on the following calculation methods, or others, as approved by SLC:

a. Declared Basis. Contractor shall select cost, weight, or volume as the basis for percentage calculations where allowed and use it consistently.

b. Formulas (examples). Recycled/Reusable/Renewable % = (Qualifying Quantity ÷ Total Quantity)

× 100; Waste Diversion % = (Total Diverted ÷ Total Generated) × 100; Energy/Water Savings % =

((Baseline − Actual) ÷ Baseline) × 100.

c. Baselines. Provide reasonable, transparent baselines (e.g., standard fixtures, conventional curing, typical dust suppression practices) and cite data sources/assumptions.

101-6.2 Documentation. The Contractor shall be responsible for documentation and maintaining the organization of the documentation. Documentation may include, but is not limited to, the following examples:

a. Materials. Invoices, cut sheets, EPDs, recycled content letters, FSC/other certifications, chain‑of‑custody.

b. Waste. Scale tickets, volume-to-weight conversion methodology, recycler receipts, commingled facility recovery rates.

c. Energy. Equipment lists, engine tier documentation, fuel logs/invoices, office utility bills or temporary meter readings, REC purchase documentation, renewable generation logs.

d. Water. Meter logs, delivery tickets, equipment settings/operational logs, photographic evidence, calculations and assumptions.

101-6.3 Forms. Use Attachment B – Monthly Sustainability Tracking Form (including materials, waste, and fuel tracking) for monthly reporting, Attachment C – Water Use Tracking Form for construction water monitoring, Attachment D – Construction Waste Diversion Form for waste tracking, and

Attachment E – Example Calculation Worksheets (materials, waste, energy, water) for calculation methodologies.

101-7 METHOD OF MEASUREMENT

101-7.1 Sustainability Measures will be measured based on percent of original contract amount earned.

101-8 BASIS OF PAYMENT

101-8.1 Payment for Sustainability Measures shall include all management, submittals, declarations, tracking, plans, programs, reviews, tools and all labor, equipment and materials to complete the item.

Sustainability Measures will be paid for as a lump sum (LS) through partial payments as defined below:

Percent of Original Contract Amount Earned Percent of Amount Bid for Sustainability to be paid

25% 25%

50% an additional 25%

75% an additional 25%

Salt Lake City International Airport C-101-8 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

101-8.2 Payment will be made under:

Item C-101 Sustainability Measures ................................................................ Per Lump Sum (LS)

101-9 ATTACHMENTS

• Attachment A: Contractor Project Sustainability Commitment (signature page)

• Attachment B: Water Use Tracking Form

90% an additional 15%

100% Project Closeout

Salt Lake City International Airport C-101-9 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

ATTACHMENT A - CONTRACTOR PROJECT SUSTAINABILITY COMMITMENT

Salt Lake City International Airport is committed to advancing sustainability through innovative design and construction practices. We, as Contractor to Salt Lake City, are committed to implementing the specifications and associated actions to support integration of sustainable principles into the construction of the Surplus Canal Relocation, and to support Salt Lake City Department of Aviation in its pursuit of

ISI Envision® verification and Salt Lake City’s broader sustainability goals. We commit to incorporating sustainable design and construction principles to minimize environmental impact and promote resilience.

Our sustainable procurement policy will prioritize eco-friendly and recycled materials. We will reduce waste and energy use and implement water conservation measures when feasible. Regular coordination with the Design Team and Sustainability Coordinator will ensure alignment with sustainability objectives and prioritize health and safety.

X

Contractor Team

Sustainability Representative

X

Contractor Team

Project Manager

Salt Lake City International Airport C-101-10 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

Attachment B - Water Usage Tracker

Contractor must track and report on water use on a weekly basis. This includes both potable and non-potable water use.

(Intended for completion in Excel - Please request if needed) Contractor Water Usage

Week Of:

Potable Gallons Used This week

Potable Gallons Used to Date

Non-potable Gallons Used

This Week

Non-potable gallons Used to

Date

Total Water Used on

Project This Week (Gallons)

Total Water

Used on Project to

Date (Gallons)

% Change in Potable Water Use to Date

Notes

0.00

0.00 0.00 0.00 0

0.00 0.00 0.00 #DIV/0!

END OF SECTION C-101

TECHNICAL SPECIFICATIONS SECTION C-102

Salt Lake City International Airport C-102-1 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

SECTION C-102

TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND SILTATION

CONTROL

102-1 DESCRIPTION

102-1.1 This item shall consist of temporary control measures as shown on the plans or as ordered by the

Resident Project Representative (RPR) during the life of a contract to control pollution of air and water, soil erosion, and siltation through the use of silt fences, berms, dikes, dams, sediment basins, fiber mats, gravel, mulches, grasses, slope drains, and other erosion control devices or methods.

Temporary erosion control shall be in accordance with the approved erosion control plan; the approved

Construction Safety and Phasing Plan (CSPP) and AC 150/5370-2, Operational Safety on Airports

During Construction. The temporary erosion control measures contained herein shall be coordinated with the permanent erosion control measures specified as part of this contract to the extent practical to assure economical, effective, and continuous erosion control throughout the construction period.

Temporary control may include work outside the construction limits such as borrow pit operations, equipment and material storage sites, waste areas, and temporary plant sites.

Temporary control measures shall be designed, installed and maintained to minimize the creation of wildlife attractants that have the potential to attract hazardous wildlife on or near public-use airports.

102-2 MATERIALS

102-2.1 Grass. Grass that will not compete with the grasses sown later for permanent cover per Item T-

901 shall be a quick-growing species (such as ryegrass, Italian ryegrass, or cereal grasses) suitable to the area providing a temporary cover. Selected grass species shall not create a wildlife attractant.

102-2.2 Mulches. Mulches may be hay, straw, fiber mats, netting, bark, wood chips, or other suitable material reasonably clean and free of noxious weeds and deleterious materials per Item 32 92 19. Mulches shall not create a wildlife attractant.

102-2.3 Fertilizer. Fertilizer shall be a standard commercial grade and shall conform to all federal and state regulations and to the standards of the Association of Official Agricultural Chemists.

102-2.4 Slope drains. Slope drains may be constructed of pipe, fiber mats, rubble, concrete, asphalt, or other materials that will adequately control erosion.

102-2.5 Silt fence. Silt fence shall consist of polymeric filaments which are formed into a stable network such that filaments retain their relative positions. Synthetic filter fabric shall contain ultraviolet ray inhibitors and stabilizers to provide a minimum of six months of expected usable construction life. Silt fence shall meet the requirements of ASTM D6461.

102-2.6 Drop Inlet Barrier/Filter. Drop inlet barriers or filters consisting of filter fabric, fiber rolls, straw bales, stone, silt fence, or other devices to prevent silt from entering existing or new storm drain inlets shall be installed as shown in the drawings.

102-2.7 Stabilized Construction Entrance. Stabilized construction entrance shall be installed as shown on the drawings.

Salt Lake City International Airport C-102-2 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

102-2.8 Other. All other materials shall meet commercial grade standards and shall be approved by the

RPR before being incorporated into the project.

102-3 CONSTRUCTION REQUIREMENTS

102-3.1 General. In the event of conflict between these requirements and pollution control laws, rules, or regulations of other federal, state, or local agencies, the more restrictive laws, rules, or regulations shall apply.

The RPR shall be responsible for assuring compliance to the extent that construction practices, construction operations, and construction work are involved.

102-3.2 Schedule. Prior to the start of construction, the Contractor shall submit schedules in accordance with the plans for accomplishment of temporary and permanent erosion control work for clearing and grubbing; grading; construction; paving; and structures at watercourses. The Contractor shall also submit a proposed method of erosion and dust control on haul roads and borrow pits and a plan for disposal of waste materials. Work shall not be started until the erosion control schedules and methods of operation for the applicable construction have been accepted by the RPR.

102-3.3 Construction details. The Contractor will be required to incorporate all permanent erosion control features into the project at the earliest practicable time as outlined in the plans and approved

CSPP. Except where future construction operations will damage slopes, the Contractor shall perform the permanent seeding and mulching and other specified slope protection work in stages, as soon as substantial areas of exposed slopes can be made available. Temporary erosion and pollution control measures will be used to correct conditions that develop during construction that were not foreseen during the design stage; that are needed prior to installation of permanent control features; or that are needed temporarily to control erosion that develops during normal construction practices, but are not associated with permanent control features on the project.

Where erosion may be a problem, schedule and perform clearing and grubbing operations so that grading operations and permanent erosion control features can follow immediately if project conditions permit.

Temporary erosion control measures are required if permanent measures cannot immediately follow grading operations. The RPR shall limit the area of clearing and grubbing, excavation, borrow, and embankment operations in progress, commensurate with the Contractor’s capability and progress in keeping the finish grading, mulching, seeding, and other such permanent control measures current with the accepted schedule. If seasonal limitations make such coordination unrealistic, temporary erosion control measures shall be taken immediately to the extent feasible and justified as directed by the RPR.

The Contractor shall provide immediate permanent or temporary pollution control measures to minimize contamination of adjacent streams or other watercourses, lakes, ponds, or other areas of water impoundment as directed by the RPR. If temporary erosion and pollution control measures are required due to the Contractor’s negligence, carelessness, or failure to install permanent controls as a part of the work as scheduled or directed by the RPR, the work shall be performed by the Contractor and the cost shall be incidental to this item.

The RPR may increase or decrease the area of erodible earth material that can be exposed at any time based on an analysis of project conditions.

The erosion control features installed by the Contractor shall be maintained by the Contractor during the construction period.

Provide temporary structures whenever construction equipment must cross watercourses at frequent intervals. Pollutants such as fuels, lubricants, bitumen, raw sewage, wash water from concrete mixing

Salt Lake City International Airport C-102-3 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026 operations, and other harmful materials shall not be discharged into any waterways, impoundments or into natural or manmade channels.

Sequence work, where practicable, from downstream to upstream to minimize unprotected conveyance.

Where demolition activities expose open storm drain lines or create a direct pathway for sediment to downstream structures, the Contractor shall implement temporary blocking measures to be approved by the RPR prior to installation, including inflatable pipe plugs (balloons) installed at downstream structures, internal structure barriers such as filter fabric or gravel bags, and temporary caps or covers on open pipe ends.

102-3.4 Installation, maintenance and removal of silt fence. Silt fences shall extend a minimum of 16 inches (41 cm) and a maximum of 34 inches (86 cm) above the ground surface. Posts shall be set no more than 6 feet (1.8 m) on center. Filter fabric shall be cut from a continuous roll to the length required minimizing joints where possible. When joints are necessary, the fabric shall be spliced at a support post with a minimum 6-inch (150-mm) overlap and securely sealed. A trench shall be excavated approximately 6 inches (150 mm) deep by 4 inches (100 mm) wide on the upslope side of the silt fence.

The trench shall be backfilled and the soil compacted over the silt fence fabric. The Contractor shall remove and dispose of silt that accumulates during construction and prior to establishment of permanent erosion control. The fence shall be maintained in good working condition until permanent erosion control is established. Silt fence shall be removed upon approval of the RPR.

102-3.5 Drop Inlet Barrier or Filters. Install drop inlet barriers and filters as shown on the drawings and as directed by the RPR to prevent silt-laden runoff from entering new or existing storm drainage collection systems.

102-3.6 Stabilized Construction Entrance. Stabilized construction entrance shall be installed as shown on the drawings at the location agreed to with the RPR where haul vehicles will enter and exit the construction area and travel onto aircraft operational areas. Remove when no longer needed or as directed by the RPR.

102-3.7 Dust Control. Contractor shall control dust emissions to prevent blowing dust from the construction area from migrating over active runways, taxiways, and roadways by sprinkling exposed soils with water, placement of and Owner-approved dust palliative, covering exposed soils, or other means acceptable to the RPR. Dust control measures shall be implemented throughout the construction period, including non-working periods. If dust emissions become a problem during non-working times, the Contractor shall provide a maximum one-hour response time after notification by the RPR to bring dust emissions under control.

102-3.8 Authority of RPR. The RPR has the authority to limit the surface area of erodible earth material exposed by stripping, to limit the surface area of erodible earth material exposed by excavation, borrow and fill operations, and to direct the Contractor to provide immediate permanent or temporary pollution and/or dust control measures to minimize dust emissions and prevent contamination of the storm water collection system, adjacent streams or other watercourses, lakes, ponds, or other areas of water impoundment.

102-4 MEASUREMENT AND PAYMENT

102-4.1 Method of Measurement. Temporary erosion and pollution control work will not be measured but shall be paid for on the basis of lump sum (LS). Control work performed for protection of construction areas outside the construction limits, such as borrow and waste areas, haul roads, equipment

Salt Lake City International Airport C-102-4 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026 and material storage sites, and temporary plant sites, will not be measured but shall be considered a subsidiary obligation of the Contractor.

102-5 BASIS OF PAYMENT

102-5.1 Temporary air and water pollution, soil erosion, and siltation control, as shown on the drawings and specified herein or as ordered by the RPR will be paid by the lump sum (LS) and shall include all labor, equipment, and materials necessary to complete all required work. The percentage of the lump sum payment paid in each application for payment shall be proportionate to the percentage of work completed during the pay application period.

Payment will be made under:

Item C-102 Temporary Air & Water Pollution, Soil Erosion, & Siltation Control

........................................................................................................................ Per Lump Sum (LS)

REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

Advisory Circulars (AC)

AC 150/5200-33 Hazardous Wildlife Attractants on or Near Airports

AC 150/5370-2 Operational Safety on Airports During Construction

ASTM International (ASTM)

ASTM D6461 Standard Specification for Silt Fence Materials

United States Department of Agriculture (USDA)

FAA/USDA Wildlife Hazard Management at Airports, A Manual for Airport Personnel

END OF SECTION C-102

TECHNICAL SPECIFICATIONS SECTION C-105

Salt Lake City International Airport C-105-1 100% Design

SURPLUS CANAL RELOCATION September 21, 2026

SECTION C-105

MOBILIZATION

105-1 DESCRIPTION

This item of work shall consist of, but is not limited to, the work and operations necessary to move in personnel, equipment and materials, security fencing and gates, set up all temporary offices, buildings, facilities, temporary lighting, pavement sweeping and cleaning, construction signs and utilities, safety flagging and barricades, obtain all required permits, pay all fees, transport all employees and materials to and from the work site, remove all equipment, personnel, and materials at the completion of the project, and all other expenses as required for the Project. This item shall include all traffic control (flaggers) and gate guards as required.

105-2 RELATED ITEMS

See:

Item C-102 Temporary Air and Water Pollution, Soil Erosion and Siltation Control

Item P-110 Contractor’s Staging Area

Item P-148 Construction Signs, Barricades, Warning Lights, Gate Guards, and

Flagging Operations

Item P-149 Street and Pavement Cleaning

105-3 POSTED NOTICES

Prior to commencement of construction activities, the Contractor must post the following documents in a prominent and accessible place where they may be easily viewed by all employees of the prime

Contractor and by all employees of subcontractors engaged by the prime Contractor: Equal Employment

Opportunity (EEO) Poster “Equal Employment Opportunity is the Law” in accordance with the Office of

Federal Contract Compliance Programs Executive Order 11246, as amended; Davis Bacon Wage Poster

(WH 1321) - DOL “Notice to All Employees” Poster; and Applicable Davis-Bacon Wage Rate

Determination. These notices must remain posted until final acceptance of the work by the Owner.

105-4 ENGINEER/RPR FIELD OFFICE

The Contractor shall provide dedicated space for the use of the field RPR and inspectors, as a field office for the duration of the project. This space shall be located conveniently near the construction and shall be separate from any space used by the Contractor. The Contractor shall furnish water, sanitary facilities, heat, air conditioning, and electricity in accordance with local building codes.

105-5 CONSTRUCTION METHODS

105-5.1 Work Areas. The approximate work area limits are shown on the drawings.

Provide and maintain all signing, safety flagging, barricades, fencing, flagging, drainage, flaggers, gate guards, and other items as required to protect public and private property from damage caused by mobilization, demobilization, and construction operations in accordance with Section P-148, Construction

Signs, Barricades, Warning Lights, Gate Guards, and Flagging Operations.

Salt Lake City International Airport C-105-2 100% Design

SURPLUS CANAL RELOCATION September 21, 2026

105-5.2 Access. Construction access to work areas shall be as shown on the Drawings. If construction access is required in addition to the construction entrances shown on the drawings, secure RPR's approval of all additional project construction entrances prior to construction. All haul routes, staging areas and equipment storage shall be at the location shown on the Drawings, unless otherwise approved by the

RPR.

All Contractor access routes leading from the project site to a public road shall be paved with asphalt concrete pavement or constructed of asphalt millings per the Drawings. Construction access locations shall also include stabilized construction entrance pads per Section C-102, Temporary Air and Water

Pollution, Soil Erosion, and Siltation Control. The Contractor shall design, construct, and maintain all temporary access roads during the life of the construction. All temporary paved roads shall be removed at the end of construction and returned to their pre-construction condition unless permission is granted in writing by the RPR for it to remain.

105-5.3 Temporary Facilities. Provide and maintain suitable areas on site for materials storage. Location of storage areas shall be approved by the RPR but remain the responsibility of the Contractor. Location shall not interfere with drainage, traffic, airport operations or NAVAIDS, or private property.

Set up and maintain in a neat and orderly manner all temporary construction facilities within the designated area or at a location approved by the RPR.

Provide and maintain temporary road detours and construction signing where indicated on the drawings.

105-6 METHOD OF MEASUREMENT

105-6.1 Mobilization will be measured based on percent of original contract amount earned.

105-7 BASIS OF PAYMENT

105-7.1 Mobilization will be paid for as a lump sum (LS) through partial payments as defined below:

Percent of Original Contract Amount Earned Percent of Amount Bid for Mobilization to be paid

5% 25%, but not exceeding 2 percent of the total bid

10% An additional 25%, but not exceeding 4 percent of the total bid

25% An additional 25%, but not exceeding 6 percent of the total bid

80% An additional 15%, but not exceeding 8 percent of the total bid

Upon final project acceptance, which includes delivery of all deliverables, O&M manuals, and contractors’ as-built drawings, any unpaid amount of the contract amount for the item of mobilization will be paid. Should the bid amount for this item exceed 8 percent of the total bid, the amount over 8 percent will not be paid until final project acceptance. Nothing herein shall be construed to limit or preclude partial payments provided for by the Agreement.

105-7.2 Payment will be made under:

Item C-105 Mobilization .................................................................................. Per Lump Sum (LS)

REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

Salt Lake City International Airport C-105-3 100% Design

SURPLUS CANAL RELOCATION September 21, 2026

Office of Federal Contract Compliance Programs (OFCCP) Executive Order 11246, as amended

EEOC-P/E-1 – Equal Employment Opportunity is the Law Poster

United States Department of Labor, Wage and Hour Division (WHD)

WH 1321 – Employee Rights under the Davis-Bacon Act Poster

END OF SECTION C-105

Salt Lake City International Airport C-105-4 100% Design

SURPLUS CANAL RELOCATION September 21, 2026

PAGE LEFT INTENTIONALLY BLANK

TECHNICAL SPECIFICATIONS SECTION P-101

Salt Lake City International Airport P-101-1 Issued for Bid

SURPLUS CANAL RELOCATION November 6, 2026

SECTION P-101

PREPARATION/REMOVAL OF EXISTING PAVEMENTS AND MISCELLANEOUS ITEMS

101-1 DESCRIPTION

101-1.1 This item shall consist of preparation of existing pavement surfaces for overlay, surface treatments, removal of existing pavement, and other miscellaneous items. The work shall be accomplished in accordance with these specifications and the applicable plans.

101-2 EQUIPMENT AND MATERIALS

101-2.1 All equipment and materials shall be specified here and in the following paragraphs or approved by the Resident Project Representative (RPR). The equipment shall not cause damage to the pavement to remain in place.

101-3 CONSTRUCTION

101-3.1 Removal of existing pavement. The Contractor’s removal operation shall be controlled to not damage adjacent pavement structure, and base material, cables, utility ducts, pipelines, or drainage structures which are to remain under the pavement.

1. Concrete pavement removal. Full depth saw cuts shall be made perpendicular to the slab surface. The Contractor shall saw through the full depth of the slab including any dowels at the joint, removing the pavement and installing new dowels as shown on the plans and per the specifications. Where the perimeter of the removal limits is not located on the joint and there are no dowels present, the perimeter shall be saw cut the full depth of the pavement. The pavement inside the saw cut shall be removed by methods which will not cause distress in the pavement which is to remain in place. If the material is to be wasted on the airport site, it shall be reduced to a maximum size of 16 inches. Concrete slabs that are damaged by under breaking shall be repaired or removed and replaced as directed by the RPR.

The edge of existing concrete pavement…