This document is a conceptual construction phasing plan for the Michigan School for the Deaf (MSD) Residence Hall project, prepared by the State of Michigan. The project involves the construction of a new residence hall and apartments on the existing MSD campus, with a phased approach designed to minimize disruption to ongoing operations. The phasing strategy spans from July 2025 through September 2027 and includes relocation of play areas and hazardous material abatement (July 2025), demolition of Gilbert Hall and relocation of utilities with initial sitework (December 2025), construction of the residence hall and apartments (December 2025 through February 2027), furniture installation and occupant move-in (March 2027 through July 2027), partial demolition of Stevens Hall (June 2027 through August 2027), and Stevens Hall exterior repairs with site landscaping and plantings (August 2027 through September 2027). The document includes conceptual site plans, building massing diagrams, and architectural renderings illustrating the new building entry and residence wings.

The document does not contain information regarding pricing terms, set-asides, incumbent contractors, funding sources, or contract award details. It functions as a planning and scheduling document to guide the sequence of construction activities and site modifications throughout the project timeline, establishing the framework for managing phased demolition, relocation, and new construction work on the MSD campus.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 5, 2023

State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall

SITE

BUILDING

tray Text Box Conceptual Construction Phasing Approach

MSD – Residence Hall | Existing Site Plan tray

Conceptual Building Massing and Site Location tray

Conceptual Building Massing and Site Location

MSD – Residence Hall | Project Phasing Strategy

Buildings to be affected

Conceptual Residence

Hall Overlay

MSD – Residence Hall | Project Schedule

July 2025

Relocate Play

Areas

Hazardous

Material

Abatement

December 2025

Raze Gilbert Hall

Relocate Utilities

Initial grading and sitework

December 2025 Thru

February 2027

Construct

Residence Hall and Apartments

March 2027 thru July 2027

Furniture and

Move-in

June 2027 thru

August 2027

Raze portion of

Stevens Hall

August 2027 thru

September 2027

Stevens Hall

Exterior Repairs

Site Landscaping and Plantings

MSD – Residence Hall | New Buildings tray

Conceptual Building Entry and Residence Wings

File details come from the government source that posted it. Updated .