This document is a conceptual construction phasing plan for the Michigan School for the Deaf (MSD) Residence Hall project, prepared by the State of Michigan. The project involves the construction of a new residence hall and apartments on the existing MSD campus, with a phased approach designed to minimize disruption to ongoing operations. The phasing strategy spans from July 2025 through September 2027 and includes relocation of play areas and hazardous material abatement (July 2025), demolition of Gilbert Hall and relocation of utilities with initial sitework (December 2025), construction of the residence hall and apartments (December 2025 through February 2027), furniture installation and occupant move-in (March 2027 through July 2027), partial demolition of Stevens Hall (June 2027 through August 2027), and Stevens Hall exterior repairs with site landscaping and plantings (August 2027 through September 2027). The document includes conceptual site plans, building massing diagrams, and architectural renderings illustrating the new building entry and residence wings.
The document does not contain information regarding pricing terms, set-asides, incumbent contractors, funding sources, or contract award details. It functions as a planning and scheduling document to guide the sequence of construction activities and site modifications throughout the project timeline, establishing the framework for managing phased demolition, relocation, and new construction work on the MSD campus.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 5, 2023
State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall
SITE
BUILDING
tray Text Box Conceptual Construction Phasing Approach
MSD – Residence Hall | Existing Site Plan tray
Conceptual Building Massing and Site Location tray
Conceptual Building Massing and Site Location
MSD – Residence Hall | Project Phasing Strategy
Buildings to be affected
Conceptual Residence
Hall Overlay
MSD – Residence Hall | Project Schedule
July 2025
Relocate Play
Areas
Hazardous
Material
Abatement
December 2025
Raze Gilbert Hall
Relocate Utilities
Initial grading and sitework
December 2025 Thru
February 2027
Construct
Residence Hall and Apartments
March 2027 thru July 2027
Furniture and
Move-in
June 2027 thru
August 2027
Raze portion of
Stevens Hall
August 2027 thru
September 2027
Stevens Hall
Exterior Repairs
Site Landscaping and Plantings
MSD – Residence Hall | New Buildings tray
Conceptual Building Entry and Residence Wings