013200 Construction Documentation.docx
DOCX document 20 KB Posted
- Solicitation number
- 36C24226B0044
About this file
This is a Construction Documentation specification section (01 32 00) outlining mandatory requirements for contractors and A/E design firms awarded work at VISN 2 VA facilities. All selected contractors must utilize the Autodesk Build Construction Cloud (ACC) platform as the official project management and collaboration system at no cost to the contractor, with access and training provided by VISN 2 through the project Contracting Officer Representative (COR).
Contractors must request platform access within 14 days of contract award and submit a written access request listing all staff requiring authorization, including full name, company name, email address, and role/position. Upon access grant, all designated staff must complete required ACC training through the ProductivityNOW eLearning portal within 12 calendar days and submit certificates of completion to the COR within 2 business days thereafter. The platform access request window expires after 12 calendar days, and additional staff or subcontractors may be added at any time through subsequent requests to the COR. All official project correspondence and documentation—including RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys—must be submitted exclusively through the ACC platform. Contractors must notify the COR of any personnel changes within 2 business days. Failure to comply with ACC platform requirements and training will prevent work commencement, and no contract time extensions or cost increases will be granted for non-compliance. Any correspondence conducted outside the platform will not serve as governing authority and will be at the contractor's expense.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
09-01-23
SECTION 01 32 00
CONSTRUCTION DOCUMENTATION
PART 1- GENERAL
1.1 DESCRIPTION:
A. Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2 Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative (COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.
1.2 REQUIREMENTS:
| A. | Contractor shall accomplish and complete the following tasks upon award of contract: |
| 1. | Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award. |
| 2. | Only staff that shall utilize the platform to be granted access. Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc. |
3. The access request shall be in writing and include a list of staff. The list shall include the following information:
| • | Full Name |
| • | Company Name |
| • | Email Address |
| • | Role/Position on the project (i.e., Project manager, site super) |
| 4. | Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days. |
| 5. | Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 Business days. |
| B. | Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period. |
| C. | Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above. |
| D. | The contractor shall only use the ACC platform for all contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration includes but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys. |
| E. | Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertains to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor ability to maintain required utilization of the platform. |
| F. | Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training. |
‑ ‑ ‑ E N D ‑ ‑ ‑ 01 32 00 - 1