012 Attach A Revised Schedule.docx
DOCX document 18 KB Posted
- Solicitation number
- 1282A723R0015
- Issued by
-
Department of Agriculture Forest Service
About this file
This attachment revises the project schedule for life safety and building repairs at multiple North Carolina Job Corps Centers. The schedule supersedes individual package specifications and outlines key due dates including a pre-construction conference within 10 days of award, a notice to proceed issued after the conference, bonds due 10 days thereafter, initial submittals 30 days from the notice to proceed, and closeout submittals and final payment paperwork due prior to project completion acceptance and within 10 days thereafter respectively. The period of performance is 294 days from the notice to proceed start date. An extended submittal period has been provided due to the complexities of multiple locations and specification packages included in the contract.
The related federal contract opportunity is solicitation number 1282A723R0015 for life safety repairs at multiple North Carolina Job Corps Centers through the Department of Agriculture Forest Service.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT A: Revised Project Schedule for: North Carolina Job Corps - Multi-Center Life Safety and Building Repairs
This schedule supercedes the project schedules in section included individual package specifications.
project schedule
| ITEM* |
| REQUIRED DUE DATE (calendar days) |
| Pre-Construction Conference |
| Within 10 days of Award (Virtually) |
| Notice To Proceed (NTP) |
| Issued first weekday after Pre-Construction Conference |
| Bonds |
| 10 days after NTP |
| Action and Informational Submittals |
| 30 calendar days after NTP (CORs have 14 calendar days to return) |
| Closeout Submittals |
| prior to CO acceptance of project |
| Contract Release form and final pay request |
| 10 days after CO acceptance of project |
Period of Performance (POP): 294 days, the period of performance commences upon issuance of the NTP. An extended submittal period has been provided due to the complexities of multiple specification packages and locations included in this contract.