The file's text, extracted by GovTribe without its formatting.
ExA
| ATTACHMENT J-0200000-05 |
| N40080-22-D-XXXX HVAC Water Testing and Treatment Services |
| RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| BY - EXHIBIT A |
| ELIN | SUB ELIN | Description | Quantity | Unit of Issue | Unit Price | Total |
| PWD South Potomac Dahlgren NSF, VA | | | | | | |
| A001 | PWD South Potomac Dahlgren NSWC | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 180 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 221 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1470 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1490 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1500 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1510 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1530 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 150 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 194 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 202 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 371 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 456 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren NSWC Subtotal | | | | $0.00 | $0.00 |
| A002 | PWD South Potomac Dahlgren ATRC | | | | | |
| AA | SKID Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| PWD South Potomac Dahlgren ATRC Subtotal | | | | $0.00 | $0.00 |
| A003 | PWD South Potomac Dahlgren NDW | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, BMD 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 220 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 963 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 206 | 12 | Month | | |
| | HVAC Chilled and Boiler Water Treatment and Testing Building 1610 | 12 | Month | | |
| PWD South Potomac Dahlgren NDW Subtotal | | | | $0.00 | $0.00 |
| PWD South Potomac Dahlgren NAVFAC | | | | | |
| AB | HVAC Boiler Water Treatment and Testing Building 481 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 962A | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1281 | 12 | Month | | |
| PWD South Potomac Dahlgren NAVFAC Subtotal | | | | $0.00 | $0.00 |
| PWD South Potomac Dahlgren CNIC Total | | | | $0.00 | $0.00 |
| A004 | PWD South Potomac Dahlgren BMD | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1705A | 12 | Month | | |
| PWD South Potomac Dahlgren BMD Subtotal | | | | $0.00 | $0.00 |
| A005 | PWD South Potomac Dahlgren Air Force | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren Air Force Subtotal | | | | $0.00 | $0.00 |
PWD South Potomac Dahlgren NSF (A001-A005) Total $0.00 $0.00
ExB
| ATTACHMENT J-0200000-06 |
| N40080-17-D-2502 HVAC Water Testing and Treatment Services |
| NON-RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| BASE PERIOD - EXHIBIT B |
| ELIN | Supplies/Services | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| PWD South Potomac Dahlgren NSF,VA | | | | | |
| B001 | The Contractor shall conduct replacement of chemical feed pump(s) and associated tubing/plumbing for non operational chemical feed pump systems. Contractor shall provide all labor, material, and tools/equipment for replacement, render replacement operational, and maintain replacement as existing designated inventory. Replacement shall of new condition and like composition, quality, and funtion. | 8 | Each | |
| B002 | The Contractor shall conduct installation of new (non existing) chemical feed pump(s) and associated tubing/plumbing. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Contractor installation responsibility shall be from Chemical containment to point of chemical injection. | 8 | Each | |
| B003 | The Contractor shall conduct replacement chemical feed pump controllers for non operational chemical feed pump conttrollers. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Replacement shall of new condition and like composition, quality, and funtion. | 6 | Each | |
| TOTAL NON-RECURRING WORK PRICE (B001 through B003)- Not to Exceed | | | | $0.00 |
ExC
| ATTACHMENT J-0200000-05 |
| N40080-22-D-XXXX HVAC Water Testing and Treatment Services |
| RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY1 - EXHIBIT C |
| ELIN | SUB ELIN | Description | Quantity | Unit of Issue | Unit Price | Total |
| PWD South Potomac Dahlgren NSF, VA | | | | | | |
| A001 | PWD South Potomac Dahlgren NSWC | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 180 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 221 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1470 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1490 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1500 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1510 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1530 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 150 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 194 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 202 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 371 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 456 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren NSWC Subtotal | | | | $0.00 | $0.00 |
| A002 | PWD South Potomac Dahlgren ATRC | | | | | |
| AA | SKID Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| PWD South Potomac Dahlgren ATRC Subtotal | | | | $0.00 | $0.00 |
| A003 | PWD South Potomac Dahlgren NDW | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, BMD 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 220 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 963 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 206 | 12 | Month | | |
| | HVAC Chilled and Boiler Water Treatment and Testing Building 1610 | 12 | Month | | |
| PWD South Potomac Dahlgren NDW Subtotal | | | | $0.00 | $0.00 |
| PWD South Potomac Dahlgren NAVFAC | | | | | |
| AB | HVAC Boiler Water Treatment and Testing Building 481 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 962A | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1281 | 12 | Month | | |
| PWD South Potomac Dahlgren NAVFAC Subtotal | | | | | |
| PWD South Potomac Dahlgren CNIC Total | | | | $0.00 | $0.00 |
| A004 | PWD South Potomac Dahlgren BMD | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1705A | 12 | Month | | |
| PWD South Potomac Dahlgren BMD Subtotal | | | | $0.00 | $0.00 |
| A005 | PWD South Potomac Dahlgren Air Force | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren Air Force Subtotal | | | | $0.00 | $0.00 |
PWD South Potomac Dahlgren NSF (A001-A005) Total $0.00 $0.00
ExD
| ATTACHMENT J-0200000-06 |
| N40080-17-D-2502 HVAC Water Testing and Treatment Services |
| NON-RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY 1 - EXHIBIT D |
| ELIN | Supplies/Services | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| PWD South Potomac Dahlgren NSF,VA | | | | | |
| D001 | The Contractor shall conduct replacement of chemical feed pump(s) and associated tubing/plumbing for non operational chemical feed pump systems. Contractor shall provide all labor, material, and tools/equipment for replacement, render replacement operational, and maintain replacement as existing designated inventory. Replacement shall of new condition and like composition, quality, and funtion. | 8 | Each | |
| D002 | The Contractor shall conduct installation of new (non existing) chemical feed pump(s) and associated tubing/plumbing. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Contractor installation responsibility shall be from Chemical containment to point of chemical injection. | 8 | Each | |
| D003 | The Contractor shall conduct replacement chemical feed pump controllers for non operational chemical feed pump conttrollers. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Replacement shall of new condition and like composition, quality, and funtion. | 6 | Each | |
| TOTAL NON-RECURRING WORK PRICE (D001 through D003)- Not to Exceed | | | | $0.00 |
ExE
| ATTACHMENT J-0200000-05 |
| N40080-22-D-XXXX HVAC Water Testing and Treatment Services |
| RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY2 - EXHIBIT E |
| ELIN | SUB ELIN | Description | Quantity | Unit of Issue | Unit Price | Total |
| PWD South Potomac Dahlgren NSF, VA | | | | | | |
| A001 | PWD South Potomac Dahlgren NSWC | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 180 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 221 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1470 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1490 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1500 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1510 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1530 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 150 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 194 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 202 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 371 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 456 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren NSWC Subtotal | | | | $0.00 | $0.00 |
| A002 | PWD South Potomac Dahlgren ATRC | | | | | |
| AA | SKID Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| PWD South Potomac Dahlgren ATRC Subtotal | | | | $0.00 | $0.00 |
| A003 | PWD South Potomac Dahlgren NDW | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, BMD 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 220 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 963 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 206 | 12 | Month | | |
| | HVAC Chilled and Boiler Water Treatment and Testing Building 1610 | 12 | Month | | |
| PWD South Potomac Dahlgren NDW Subtotal | | | | $0.00 | $0.00 |
| PWD South Potomac Dahlgren NAVFAC | | | | | |
| AB | HVAC Boiler Water Treatment and Testing Building 481 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 962A | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1281 | 12 | Month | | |
| PWD South Potomac Dahlgren NAVFAC Subtotal | | | | | |
| PWD South Potomac Dahlgren CNIC Total | | | | $0.00 | $0.00 |
| A004 | PWD South Potomac Dahlgren BMD | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1705A | 12 | Month | | |
| PWD South Potomac Dahlgren BMD Subtotal | | | | $0.00 | $0.00 |
| A005 | PWD South Potomac Dahlgren Air Force | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren Air Force Subtotal | | | | $0.00 | $0.00 |
PWD South Potomac Dahlgren NSF (A001-A005) Total $0.00 $0.00
ExF
| ATTACHMENT J-0200000-06 |
| N40080-17-D-2502 HVAC Water Testing and Treatment Services |
| NON-RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY 2 - EXHIBIT F |
| ELIN | Supplies/Services | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| PWD South Potomac Dahlgren NSF,VA | | | | | |
| F001 | The Contractor shall conduct replacement of chemical feed pump(s) and associated tubing/plumbing for non operational chemical feed pump systems. Contractor shall provide all labor, material, and tools/equipment for replacement, render replacement operational, and maintain replacement as existing designated inventory. Replacement shall of new condition and like composition, quality, and funtion. | 8 | Each | |
| F002 | The Contractor shall conduct installation of new (non existing) chemical feed pump(s) and associated tubing/plumbing. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Contractor installation responsibility shall be from Chemical containment to point of chemical injection. | 8 | Each | |
| F003 | The Contractor shall conduct replacement chemical feed pump controllers for non operational chemical feed pump conttrollers. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Replacement shall of new condition and like composition, quality, and funtion. | 6 | Each | |
| TOTAL NON-RECURRING WORK PRICE (F001 through F003)- Not to Exceed | | | | $0.00 |
ExG
| ATTACHMENT J-0200000-05 |
| N40080-22-D-XXXX HVAC Water Testing and Treatment Services |
| RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY3 - EXHIBIT G |
| ELIN | SUB ELIN | Description | Quantity | Unit of Issue | Unit Price | Total |
| PWD South Potomac Dahlgren NSF, VA | | | | | | |
| A001 | PWD South Potomac Dahlgren NSWC | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 180 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 221 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1470 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1490 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1500 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1510 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1530 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 150 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 194 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 202 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 371 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 456 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren NSWC Subtotal | | | | $0.00 | $0.00 |
| A002 | PWD South Potomac Dahlgren ATRC | | | | | |
| AA | SKID Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| PWD South Potomac Dahlgren ATRC Subtotal | | | | $0.00 | $0.00 |
| A003 | PWD South Potomac Dahlgren NDW | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, BMD 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 220 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 963 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 206 | 12 | Month | | |
| | HVAC Chilled and Boiler Water Treatment and Testing Building 1610 | 12 | Month | | |
| PWD South Potomac Dahlgren NDW Subtotal | | | | $0.00 | $0.00 |
| PWD South Potomac Dahlgren NAVFAC | | | | | |
| AB | HVAC Boiler Water Treatment and Testing Building 481 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 962A | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1281 | 12 | Month | | |
| PWD South Potomac Dahlgren NAVFAC Subtotal | | | | | |
| PWD South Potomac Dahlgren CNIC Total | | | | $0.00 | $0.00 |
| A004 | PWD South Potomac Dahlgren BMD | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1705A | 12 | Month | | |
| PWD South Potomac Dahlgren BMD Subtotal | | | | $0.00 | $0.00 |
| A005 | PWD South Potomac Dahlgren Air Force | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren Air Force Subtotal | | | | $0.00 | $0.00 |
PWD South Potomac Dahlgren NSF (A001-A005) Total $0.00 $0.00
ExH
| ATTACHMENT J-0200000-06 |
| N40080-17-D-2502 HVAC Water Testing and Treatment Services |
| NON-RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY 3 - EXHIBIT H |
| ELIN | Supplies/Services | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| PWD South Potomac Dahlgren NSF,VA | | | | | |
| H001 | The Contractor shall conduct replacement of chemical feed pump(s) and associated tubing/plumbing for non operational chemical feed pump systems. Contractor shall provide all labor, material, and tools/equipment for replacement, render replacement operational, and maintain replacement as existing designated inventory. Replacement shall of new condition and like composition, quality, and funtion. | 8 | Each | |
| H002 | The Contractor shall conduct installation of new (non existing) chemical feed pump(s) and associated tubing/plumbing. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Contractor installation responsibility shall be from Chemical containment to point of chemical injection. | 8 | Each | |
| H003 | The Contractor shall conduct replacement chemical feed pump controllers for non operational chemical feed pump conttrollers. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Replacement shall of new condition and like composition, quality, and funtion. | 6 | Each | |
| TOTAL NON-RECURRING WORK PRICE (H001 through H003)- Not to Exceed | | | | $0.00 |
ExI
| ATTACHMENT J-0200000-05 |
| N40080-22-D-XXXX HVAC Water Testing and Treatment Services |
| RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY4 - EXHIBIT I |
| ELIN | SUB ELIN | Description | Quantity | Unit of Issue | Unit Price | Total |
| PWD South Potomac Dahlgren NSF, VA | | | | | | |
| A001 | PWD South Potomac Dahlgren NSWC | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 180 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 221 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1470 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1490 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1500 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1510 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1530 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 150 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 183 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 194 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 202 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 371 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 456 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1560 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren NSWC Subtotal | | | | $0.00 | $0.00 |
| A002 | PWD South Potomac Dahlgren ATRC | | | | | |
| AA | SKID Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| PWD South Potomac Dahlgren ATRC Subtotal | | | | $0.00 | $0.00 |
| A003 | PWD South Potomac Dahlgren NDW | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, BMD 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 220 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 963 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Chilled Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1520 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 206 | 12 | Month | | |
| | HVAC Chilled and Boiler Water Treatment and Testing Building 1610 | 12 | Month | | |
| PWD South Potomac Dahlgren NDW Subtotal | | | | $0.00 | $0.00 |
| PWD South Potomac Dahlgren NAVFAC | | | | | |
| AB | HVAC Boiler Water Treatment and Testing Building 481 | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 962A | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1281 | 12 | Month | | |
| PWD South Potomac Dahlgren NAVFAC Subtotal | | | | | |
| PWD South Potomac Dahlgren CNIC Total | | | | $0.00 | $0.00 |
| A004 | PWD South Potomac Dahlgren BMD | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1705A | 12 | Month | | |
| PWD South Potomac Dahlgren BMD Subtotal | | | | $0.00 | $0.00 |
| A005 | PWD South Potomac Dahlgren Air Force | | | | | |
| AA | HVAC Chilled Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| | HVAC Boiler Water Treatment and Testing Building 1700 (Cost Share- NDW 1/4, NSWC 1/4, and AF 1/2 each) | 12 | Month | | |
| PWD South Potomac Dahlgren Air Force Subtotal | | | | $0.00 | $0.00 |
PWD South Potomac Dahlgren NSF (A001-A005) Total $0.00 $0.00
ExJ
| ATTACHMENT J-0200000-06 |
| N40080-17-D-2502 HVAC Water Testing and Treatment Services |
| NON-RECURRING WORK EXHIBIT LINE ITEM NUMBERS |
| OY 4 - EXHIBIT J |
| ELIN | Supplies/Services | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| PWD South Potomac Dahlgren NSF,VA | | | | | |
| J001 | The Contractor shall conduct replacement of chemical feed pump(s) and associated tubing/plumbing for non operational chemical feed pump systems. Contractor shall provide all labor, material, and tools/equipment for replacement, render replacement operational, and maintain replacement as existing designated inventory. Replacement shall of new condition and like composition, quality, and funtion. | 8 | Each | |
| J002 | The Contractor shall conduct installation of new (non existing) chemical feed pump(s) and associated tubing/plumbing. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Contractor installation responsibility shall be from Chemical containment to point of chemical injection. | 8 | Each | |
| J003 | The Contractor shall conduct replacement chemical feed pump controllers for non operational chemical feed pump conttrollers. Contractor shall provide all labor, material, and tools/equipment for new installation and render newly installed equipment operational. Replacement shall of new condition and like composition, quality, and funtion. | 6 | Each | |
| TOTAL NON-RECURRING WORK PRICE (J001 through J003)- Not to Exceed | | | | $0.00 |