01 71 13 Mobilization.pdf

PDF 105 KB Posted

Attached to
Renovate Laguna Campground Picnic Tables
Solicitation number
127EAW22Q0018
Issued by

About this file

This document contains a mobilization section for a construction project and details of a related federal contract opportunity to renovate picnic tables at Laguna Campground in Cleveland National Forest. The mobilization section outlines preparatory work and operations necessary prior to work on site, including payment terms of 50% when 5% of the original contract amount is earned from other items and 100% when 10% is earned. The federal contract opportunity is a solicitation from the Department of Agriculture Forest Service to renovate picnic tables with an estimated price range of $100,000 to $250,000, which is set aside 100% for Service-Disabled Veteran Owned Small Businesses. Quotations are required to be submitted to two individuals by the specified deadline, and a bid guarantee is required for quotes over $150,000.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOBILIZATION Section 01 71 13-1

SECTION 01 71 13 - MOBILIZATION

PART 1 - GENERAL

1.1 SCOPE

A. This work consists of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.

1.2 MEASUREMENT AND PAYMENT

A. The accepted quantities will be paid for at the contract unit price for item 01 71 13, Mobilization.

B. Progress payments will be made as follows:

1. The Government will pay to the Contractor in the first progress payment the total premium paid by the Contractor to obtain bonds. This payment shall not be in addition to the contract price and will be included in Item 01 71 13, Mobilization.

2. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.

3. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.

4. Upon completion of all work on the project, any unpaid amount for item 01 71 13, Mobilization, will be paid.

C. The total of all payments will not exceed the original contract amount for item 01 71 13, Mobilization.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 71 13

END OF SECTION 01 71 13