This document package includes a summary of work specification and related federal contract opportunity notice. The specification outlines renovation work at Laguna Campground in San Diego County, including demolishing and replacing picnic tables at designated sites. The 120-calendar day project will be conducted in a single phase, with work hours restricted to weekdays from 8am to 4:30pm and shut down on weekends and holidays. The related opportunity notice is a solicitation to renovate the Laguna Campground picnic tables with an estimated price range of $100,000 to $250,000. As a 100% set-aside, only service-disabled veteran-owned small businesses may submit quotes in response to the solicitation, which are due as directed to the specified Department of Agriculture Forest Service contacts by the stated deadline.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF WORK Section 01 11 00-1
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Project consists of renovation type improvements at the following location.
1. Project Locations: Laguna Campground, San Diego County
(Option #1) Corral Canyon Campground and Bobcat Meadows Campground, San Diego County
From San Diego travel on I-8 East for approximately 40 miles, exit Sunrise Highway. Turn left onto Sunrise Highway (San Diego County S-1) travel for approximately 12 miles. Laguna Campground will be on the left.
Option #1 travel on I-8 East for approximately 45 miles, exit on Buckman Springs Road. Turn right on to Buckman Springs Road approximately 3.5 miles. Turn right on Corral Canyon Road. 5.9 miles to the intersection of Los Pinos road. Go straight 1.4 miles to Corral Canyon Campground or turn left 1.1 miles on Los Pinos Road to Bobcat Meadows Campground.
2. Owner: Cleveland National Forest, 10845 Rancho Bernardo Road, Suite 200, San Diego, CA 92127.
B. This project will include, but is not limited to the following:
Laguna Campground Picnic Table Bid:
Includes but is not limited to the following items of work:
Demo existing picnic tables at sites shown on site map. Remove existing wood bollards, Order, purchase and install new picnic tables for sites on site map. Re-install the existing wood bollards back in the same locations.
Some or all of the additives may or may not be awarded at anything throughout the contract.
1.2 WORK SEQUENCE
A. The work shall be conducted in one phase.
1. All work shall be substantially complete and ready for occupancy within 120 calendar days of the Notice To Proceed.
1.3 USE OF PREMISES
A. See Section 01 14 00, Work Restrictions.
1.4 CONTRACTOR’S SCHEDULE
A. The contractor shall provide the Government with a complete work schedule at the project prework conference describing the different work activities and when they will be initiated and completed. The Contractor will be expected to follow this schedule during the course of the contract or shall submit a revised schedule within 48 hours of any unforeseen delays or changes. Such schedule shall be in the form of a
SUMMARY OF WORK Section 01 11 00-2
Critical Path Schedule and shall include the timing for each major phase of the work. The schedule shall include the sequencing of the various phases of the work and work specialties, and shall constitute a basis for the evaluation of time extensions in the negotiations for changes.
1.5 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Division and Sections using the 48-division format and Construction Specification Institute (CSI) “Master Format” numbering system.
B. Specifications Content: The Specifications use certain convention for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. The conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred, as the same required. Singular words shall be interpreted as plural and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words “shall,” “shall be,” or “shall comply with,” depending on the context, are implied where used within a sentence or phrase.
1.6 DAYS/HOURS OF OPERATION
A. The Contractor’s hours of operation shall be restricted to 8:00 am to 4:30 pm, Monday through Friday. In addition, the work shall be shut down during the following periods.
1. Work shall be shut down on Saturdays, Sundays, and all federally listed Holidays.
2. Contract time has been adjusted to reflect these periods of shutdown.
1.7 MEASUREMENT AND PAYMENT
A. Cost Breakdown: The Contractor shall provide to the Government at the prework conference a breakdown of each Lump Sum Unit Price for the project for the purpose of computing progress payments and for use in determining costs for proposed changes to the Contract. Such breakdown shall include each separate phase of the work by Construction Specification Institute (CSI) Specifications but need not separate labor from material costs. The approved cost breakdown will constitute the basis under which monthly progress payments will be made.
B. The work shall be measured for each item as listed below and as shown on the Schedule of Items.
1. Lump Sum Quantity (LSQ) shall be measured as one job and shall include all mobilization, preparation work, new construction, site work, clean up and the like.
2. Actual Quantity (AQ) shall be measured as the actual work completed as described in Contract
Specifications herein.
SUMMARY OF WORK Section 01 11 00-3
3. Design Quantity (DQ) shall be based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings and the presentation in the contract.
C. Payment: Payment for the quantity or unit, as measured above, will be at the contract unit price as shown on the Schedule of Items. Payment will constitute full compensation for all labor, equipment, materials and incidentals necessary to complete the work described herein.
PART 2 – PRODUCTS (Not Used)
PART 3 – EXECUTION
3.1 REQUIREMENTS OF REGULATORY AGENCIES:
A. All work performed shall comply with Health, Safety and Fire Codes, OSHA regulations and/or applicable regulations established by Local, County and State codes and ordinances.
END OF SECTION 01 11 00