01 14 00 WorkRestrictions.pdf

PDF 104 KB Posted

Attached to
Renovate Laguna Campground Picnic Tables
Solicitation number
127EAW22Q0018
Issued by

About this file

This document outlines requirements for a federal contract opportunity to renovate picnic tables at Laguna Campground in Cleveland National Forest. The solicitation seeks quotations for a project estimated to cost between $100,000 and $250,000, which is set aside 100% for Service-Disabled Veteran Owned Small Businesses. Interested parties must submit quotes directly to Wendy Whiteman and Paula Sales of the US Department of Agriculture Forest Service by the date specified in Block 8 of the solicitation. A bid guarantee is required for any quotes over $150,000. The work restrictions section indicates the contractor will have full use of the designated worksite but may not use government utilities or interfere with emergency vehicle access. The contractor must also restore and clean the site after project completion.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK RESTRICTIONS Section 01 14 00-1

SECTION 01 14 00 - WORK RESTRICTIONS

PART 1 – GENERAL

1.1 SCOPE

A. This work consists of the use by the Contractor of areas and facilities owned by the Government during the construction of this project.

1.2 MEASUREMENT AND PAYMENT

A. No separate payment will be made for work specified in this section.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 No water will be available for the Contractors use. Contractor’s imported water source shall be free of all deleterious materials. All water is considered incidental to individual work items. No telephone or electrical will be available for the Contractor’s use.

3.2 The Contractor will have full use of the site within the project area as determined by the COR for construction operations. The Contractor may store equipment and materials in this area. The Contractor shall be responsible for providing for the security of the equipment and materials delivered and stored at the jobsite.

Contractor’s use of the delineated portion of the premises is limited by the Government’s right to perform work or to retain other Contractors on portions of the project.

3.3 The Contractor shall take all reasonable precautions to ensure a safe construction area.

3.4 The Contractor's operations shall at no time interfere with emergency vehicle traffic.

3.5 The Contractor shall return the area designated for equipment and materials storage to the original state at the completion of the project.

3.6 Contractor shall cleanup work areas on a daily basis in accordance with Section 01 74 00, Construction Waste

Management and Disposal.

END OF SECTION 01 14 00