01 55 00 Site Access Staging and Phasing
This is a project specification document for the Colorado roof and ceiling repair project at an indoor arena and stalls facility (LCC 27-1). The document outlines site access, staging, and phasing requirements for the construction project. The specification establishes procedures for contractor access to the work site, including requirements for maintaining site security, controlling traffic flow, and coordinating with facility operations. Phasing requirements detail how work must be sequenced to minimize disruption to ongoing facility activities, with specific attention to maintaining access for personnel and equipment while repairs to the roof and ceiling systems are underway. The document establishes protocols for material staging areas, temporary facility setup, and coordination of multiple trades working within the constrained indoor arena environment.
The specification emphasizes operational continuity throughout the construction period, requiring contractors to develop and implement detailed site management plans that address logistics, safety, and access control. The document mandates coordination with facility management to schedule work phases in a manner that permits continued use of portions of the facility. Contractors must comply with all temporary facilities requirements, including erosion control, dust suppression, and waste management protocols specific to an indoor agricultural facility. The document serves as a binding requirement for bid proposals and subsequent contract performance, with all contractors required to acknowledge understanding of and compliance with these site access and phasing parameters as a condition of project award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lamar Community College Repair Roof and Ceiling, Indoor Arena, and Stalls Project Number: 2024-077M23
SITE ACCESS, STAGING AND PHASING (Bid & Const. Set) 01 55 00-1
SECTION 01 55 00- SITE ACCESS, STAGING AND PHASING
PART 1 GENERAL
1.1 DESCRIPTION
A. Work Included: This specification section covers the allowable access locations and setup procedures. Also covered are the phasing requirements for the maintenance of required egress routes during the demolition and reconstruction of the facility.
B. This project site will not be available for storage of materials nor on-site mobilization until May 3, 2027. As such, should the contractor find it advantageous to purchase materials prior to this date, they must be stored OFF-SITE in a secure and appropriately weather-protected location. Cost of all OFF-SITE storage and subsequent delivery of stored materials, must be included as part of the Contractor’s bid proposal.
1.2 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the crafts and who are completely familiar with the specified requirements and the methods needed for the proper performance of the work of this Section.
B. Only qualified personnel may use equipment or give signals to equipment operators.
C. Operate all equipment within equipment design standards.
D. Photograph all surfaces that are to be used for storage. Photographs need to be of sufficient clarity to indicate the condition of the storage surface and any adjacent walls, streets or sidewalks. Provide one set of the photographs to the Owner prior to the start of work.
Contractor shall restore all affected surfaces to the same condition at job's end.
1.3 SUBMITTALS
A. Submit the phasing and egress plan described below to the Architect and Owner for acceptance. Once accepted it will be submitted to the State’s Code Consultant for approval.
B. The contractor shall submit engineering documentation to the Owner indicating that any scaffolding or hoist equipment used on this job can operate within the project lifting and load parameters for the equipment design.
1.4 EQUIPMENT HANDLING
A. Schedule equipment arrival and significant material deliveries with Building Staff so as not to interfere with normal facility operations.
B. Do not block any roads or entrances without 72 hours of notification and Building Staff approval.
C. Secure all delivered equipment and setup material against theft or vandalism.
PART 2 PRODUCTS (NOT APPLICABLE)
SITE ACCESS, STAGING AND PHASING (Bid & Const. Set) 01 55 00-2
PART 3 EXECUTION
3.1 PLANNING, SCHEDULING AND PERFORMANCE OF WORK
A. Planning, Scheduling and Performance of Work: See other Division 1 specifications for more specific requirements. This project involves the complete removal and replacement of the roofing panels and insulation. This will leave the building open and vulnerable to exterior environmental and weather conditions. As such, contractor shall only schedule and perform demolition of roofing to the extent that it can be reconstructed within the same day.
3.2 PHASING REQUIREMENTS
A. The contractor shall develop a phasing plan. Demonstrate the extent and perimeter of demolition/construction activities to allow public access around the affected project areas and to maintain all required egress from the buildings during the construction project. The plan shall also indicate how and where temporary guards or barriers will be located. The plan shall take into consideration all demolition activities and the material and equipment movement to and away from the project area. Include information regarding temporary facilities placement as indicated in Section 01 50 00.
3.3 SITE ACCESS
A. Site contains a Geo-Thermal Well Field approximately Southwest of the Building. No vehicular traffic is allowed in this area. Contractor to review this area with Owner prior to construction mobilization.
B Site access locations are to be reviewed and approved by the Owner. The Contractor must stay within these boundaries.
C. Access to the site may be restricted by Building Events. Coordinate access requirements with the Building Staff.
D. Limited amounts of water and electricity shall be provided by the Owner.
E. Do not block or lock building exits or entrances without permission from the Building Staff.
F. Setup areas must be kept clean or screened off.
G. If access openings must be cut to install new materials, coordinate with Building Staff. Obtain utility locate prior to cutting into any concealed spaces.
3.4 INTERIOR STORAGE AND ACCESS
A. Any interior access for storage must be coordinated and approved by the Owner, and only during times when building is vacated by Owner.
3.5 COMPLIANCE
A. Do not permit materials not complying with provisions of these Specifications to be brought onto or stored at the job site.
B. Promptly remove non-complying materials and replace with materials meeting the requirements of this Project.
SITE ACCESS, STAGING AND PHASING (Bid & Const. Set) 01 55 00-3
3.6 DISPOSAL CHUTE
A. Where damage to the existing facility is a possibility, or where there is danger to persons below, a disposal chute must be used or a tarp that completely covers the side of the building.
END OF SECTION 01 55 00