01 31 00 Project Management and Coordination.pdf
PDF 134 KB Posted
- Solicitation number
- IFB1 GJFA 2027000028 3
- Issued by
- Pueblo County, Colorado
About this file
This is a Project Management and Coordination specification section for Lamar Community College's Repair Roof and Ceiling, Indoor Arena, and Stalls Project (Project Number: 2024-077M23). The specification outlines administrative and coordination procedures that the contractor must implement throughout the construction project. Key requirements include coordinating construction operations across different sections of work to ensure efficient and orderly installation, preparing coordination memoranda for all parties involved, and managing administrative procedures including schedule preparation, submittal processing, and project closeout activities. The contractor is required to conduct a preconstruction conference within ten days of receiving the Notice to Proceed, with attendance from authorized representatives of the owner, architect, contractor, major subcontractors, and suppliers. The agenda for this conference must address tentative construction schedules, critical work sequencing, key personnel designations, change order procedures, RFI processes, and other operational matters. Additionally, preinstallation conferences must be held before each construction activity requiring coordination with other work, with minutes distributed to all parties present.
The specification requires formal progress meetings at biweekly intervals, with attendance from the owner, architect, all contractors, subcontractors, and relevant suppliers. These meetings must review the contractor's construction schedule, assess whether activities are on time or behind schedule, and discuss interface requirements, submittal status, deliveries, and quality standards. The architect is responsible for recording and distributing minutes from all meetings within three days of progress meetings where schedule revisions occur. The specification emphasizes coordination of construction activities to conserve energy, water, and materials, with salvage of non-incorporated materials designated as owner property. No pricing terms, set-asides, funding sources, or contract award information are contained in this specification document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lamar Community College Repair Roof and Ceiling, Indoor Arena, and Stalls Project Number: 2024-077M23
PROJECT MANAGEMENT AND COORDINATION (Bid & Const. Set) 01 31 00 - 1
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General Project coordination procedures.
2. Coordination Drawings.
3. Project meetings.
B. See Division 1 Section "Execution Requirements" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
C. See Division 1 Section 01 32 13 “Schedule and Reports” for specific scheduling milestones that must be incorporated into the contractor’s schedule and project management activities.
1.2 COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
PROJECT MANAGEMENT AND COORDINATION (Bid & Const. Set) 01 31 00 - 2
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Startup and adjustment of systems.
8. Project closeout activities.
D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
1. Salvage materials and equipment involved in performance of, but not actually incorporated in, the Work. Refer to other specification sections and Drawings for disposition of salvaged materials that are designated as Owner's property.
1.3 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than ten (10) days after Notice to Proceed. Hold the conference at Project site or another convenient location.
Conduct the meeting to review responsibilities and personnel assignments.
1. Attendees: Authorized representatives of Owner, Architect; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Procedures for processing field decisions and Change Orders.
f. Procedures for Requests for Interpretations (RFIs).
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. Preparation of Record Documents.
l. Use of the premises and existing building.
m. Work restrictions.
n. Owner's occupancy requirements.
o. Responsibility for temporary facilities and controls.
p. Construction waste management and recycling.
q. Parking availability.
r. Office, work, and storage areas.
s. Equipment deliveries and priorities.
t. First aid.
u. Security.
v. Progress cleaning.
w. Working hours.
PROJECT MANAGEMENT AND COORDINATION (Bid & Const. Set) 01 31 00 - 3
3. Minutes: Architect will record and distribute the meeting minutes of this Preconstruction Conference.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction. At a minimum, this requires a Preinstallation Conference with Owner and Architect prior to and within 10 days of on-site mobilization.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. The Contract Documents.
b. Options.
c. Related Requests for Information (RFIs).
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
j. Compatibility problems.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's written recommendations.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of authorities having jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Conduct formal progress meetings at biweekly intervals. At the Architect’s or Owner’s discretion, more frequent meetings may occasionally be required.
1. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these
PROJECT MANAGEMENT AND COORDINATION (Bid & Const. Set) 01 31 00 - 4 meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
13) Status of correction of deficient items.
14) Field observations.
15) Requests for Information (RFIs).
16) Status of proposal requests.
17) Pending changes.
18) Status of Change Orders.
19) Pending claims and disputes.
20) Documentation of information for payment requests.
3. Minutes: Architect will record and distribute the meeting minutes to the Owner, General Contractor, appropriate Design Consultants, and all other attendees or parties who should have been present and all other necessary entities.
a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized.
Issue revised schedule within three (3) days after each meeting.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00