005582A__Liquidated_Damages_(Construction).pdf

PDF 202 KB Posted

Attached to
53rd Avenue N. Force Main Replacement (PID 005582A)
Solicitation number
24-0791-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

This document is a Liquidated Damages worksheet for Pinellas County's 53rd Avenue N Force Main Replacement project (PID 005582A), prepared on 5/14/2024. The project involves replacing an aging 20" & 24" concrete force main with new PVC force main using open cut and horizontal directional drill (HDD) methods. The estimated construction cost is $2,602,892.38, with a projected duration of 365 calendar days. The document details staffing allocations across multiple personnel classifications, including roles from Pinellas County Construction Division, CEI (Construction Engineering Inspection), and various technical specialists.

The liquidated damages for the project are recommended at $1,359.00, distributed across Construction Management Division and potentially other sections. The staffing breakdown includes hourly rates ranging from $25.94 to $134.00, with total compensation calculated at $434,408.59. Key personnel include a Construction Division Director, Construction Section Manager, Construction Administrator/Supervisor, and multiple specialized roles such as Senior Inspectors, Project Engineers, and Support Specialists. The funding appears to be from a Capital Improvement Project (CIP) source, with a focus on infrastructure replacement and utility improvement in Pinellas County, Florida.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CIP/UTILITY x

365 12

DATE PREPARED

1 Pinellas County Construction Division Director 83.958 $77.01 max $115.03 $9,657.83 $9,657.83 2 Pinellas County Construction Section Manager 83.958 $70.51 max $107.66 $9,038.70 $9,038.70 3 Pinellas County Senior Administrative Manager max

4 Pinellas County Construction Administrator/Supervisor 590.417 $59.14 max $92.33 $54,512.97 $54,512.97 15 Pinellas County Contract Control Specialist 330.417 $25.94 avg $46.86 $15,484.68 $15,484.68 16 Pinellas County Public Information Specialist max 17 Pinellas County Secretary/Clerical Typist max 18 Principal max

19 Construction Manager max

20 CEI Project Manager max 21 CEI Senior Project Engineer max 22 CEI Project Administrator max 23 CEI Contract Support Specialist max 24 CEI Senior Inspector 2345.417 max $134.00 $314,285.83 $31,428.58 $345,714.42 25 CEI Senior Inspector max 26 CEI Inspector's Aid max 27 CEI Secretary/Clerk Typist max 28 CEI Public Information Specialist max 29 CEI Utility Coordinator max 30 CEI Schedule Analyst max 31 CEI Environmental Specialist max 32 Geotechnical Senior Engineer max 33 Geotechnical Project Manager max 34 Geotechnical Project Engineer max 35 Geotechnical Autocad max 36 Geotechnical Staff Professional max 37 Survey Professional Land Surveyor max 38 Survey Senior Project Surveyor max 39 Survey Autocad Technician max 40 Survey Administrative max 41 Survey 3 Member Crew max 42 Survey 4 Member Crew max 43 Resident Compliance Officer max 44 CCA Asst. Construction Manager max 45 CCA Project Controls Specialist max 46 CEI Utility Inspector max 47 Consultant Senior Engineer max 48 Consultant Project Engineer max 49 Consultant CADD Technican max 50 Consultant Environmental Scientist max

TOTAL $361.88 $134.00 $402,980.01 $31,428.58 $434,408.59

TOTAL

OTHER justification

RECOMMENDED PROJECT LIQUIDATED DAMAGES

(project MUST have data input from Construction, Engineering & Design, and OTHER) $1,359.00

RECOMMENDED LIQUIDATED DAMAGES related to

OTHER

Staff Man Hours / DAY

RECOMMENDED LIQUIDATED DAMAGES related to

CONSTRUCTION MANAGEMENT DIVISION $1,359.00

Total Hourly Rate +

Overhead

Consultant Rate based on Contract

Cost Item No.

Personnel Classifications

Hourly Rate

Hourly Basis

MAX

AVG

MIN

RECOMMENDED LIQUIDATED DAMAGES related to ENGINEERING & DESIGN SECTION(s) of

Transportation/Stormwater Division

Staffing Comments

Man Hours Hourly

Rate Item No.

Personnel Classifications

Hourly Basis

MAX

AVG

MIN

Total Hourly Rate +

Overhead

CEI Rate

(2012 CEI

Contract)

Cost Total Compensation Straight O/T

10% MHR

(Hr rate+Benefits)

5/14/2024

CONSTRUCTION COST $ 2,602,892.38

ESTIMATED DURATION (Calendar Days):

PROJECT TYPE & DESCRIPTION TRAFFIC

PROJECT NAME/From/To 53rd Aveneu N Force Main Replacement

FUNDING (CIP OR OTHER)

SUB‐PROJECT IDENTIFICATION NO. (SUB‐PID):

FINANCIAL PROJECT ID (Applies to LAP Agreements):

OFFICE PREPARING ESTIMATE PINELLAS COUNTY

PROJECT IDENTIFICATION NO. (PID): 005582A

TOTAL

$1,359.00 -$ -$

Construction Engineering/Design Other

5/14/2024 8:20 AM

Manhour Estimate (2)

File details come from the government source that posted it. Updated .