00017965 - Exhibit 7-2_Acceptable Quality Levels.pdf

PDF 99 KB Posted

Attached to
ESB - Interstate 5 MP 48. 3 to 50: Clear Zone Tree Removal
Solicitation number
S-73000-00017965
Issued by
Jackson County, Oregon

About this file

This is an Acceptable Quality Levels exhibit document for the State of Oregon's Interstate 5 MP 48.3 to 50 Clear Zone Tree Removal project. The document establishes quality standards and performance requirements for tree removal and clearing work intended to improve sight distance along the specified highway corridor. The work encompasses clearing trees and limbs, trimming marked trees, establishing clear zones for signage, and removing and disposing of trees and limbs within designated areas as directed by the contracting agency.

The exhibit defines specific quality standards organized by defect category, distinguishing between major and minor defects with corresponding allowable tolerances per mile. Major defect categories include tree damage exceeding 30 percent of the tree bole, horizontal clearance failures affecting more than 20 percent of the work area, vertical clearance deficiencies, height clearance issues, and drainage impedance. Minor defects allow up to ten occurrences per mile for tree damage, five per mile for clearance issues, and two per mile for drainage concerns. Oversized material remaining on road surfaces or in drainage structures is subject to zero tolerance regardless of classification. All defects require rework, with work suspension mandated for non-compliance with approved safety plans, traffic control measures, and signage requirements. The contractor must maintain work area management practices that do not impede sight distance.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Acceptable Quality Levels

Description Major Minor Allowable Defects Required Action

Defect Defect Major Minor Major Minor Tree damage Damage to more than

30% of the tree bole Damage to 30% or less of the tree bole

0 per mile 10 per mile Remove or Treat Remove or Treat

Horizontal Clearance More than 20% not cleared to limits

20% or less not cleared to limits

0 5 per mile Rework Rework if greater than 5 minor defects *

Vertical Clearance More than 20% not cleared to limits

20% or less not cleared to limits

0 5 per mile Rework Rework if greater than 5 minor defects *

Height above ground surface

More than 20% not cleared to limits

20% or less not cleared to limits

0 5 per mile Rework Rework if greater than 5 minor defects *

Drainage Impeded flow or water diverted out of drainage structures.

20% or less impeded, but water will stay in the channel.

0 2 per mile Rework Rework if greater than 2 minor defects *

Oversized Material Material greater than 3" diameter remaining on the road surface

Material 1” – 3” in diameter remaining on the road surface

0 0 Rework Rework

Material greater than 3" diameter and 36" in length remaining on the roadway drainages or has the potential to move into drainages.

Material 1” - 3" in diameter and greater 36" in length remaining on the roadway slopes and drainages or has the potential to move into drainages.

0 0 Rework Rework if greater than 0 minor defects *

Description Major Minor Allowable Defects Required Action Defect Defect Major Minor Major Minor

Concentrations

Work Area Management

Any concentrations that affect sight distance

N/A 0 0 Rework N/A

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

0 0 Suspend work until in compliance

Suspend work until in compliance