This is a proposal evaluation matrix for the Oregon state contract opportunity S-73000-00016737 for Crash Data Safety Consultant Support Services. The document presents detailed scoring results from a five-member evaluation team assessing multiple bidding firms against six weighted evaluation criteria: Understanding of Requested Services (maximum 30 points), Specific Experience of Key Staff (20 points), Availability (20 points), Project Samples (20 points), Clarity of Proposal and Conformity with Requirements (10 points), and Price (20 points), for a total possible score of 120 points. DKS Associates was the only firm with complete evaluation scores recorded, achieving individual evaluator scores of 30, 27, 15, and 28 points, with totals ranging from 88 to 119 points across the evaluation panel. The remaining 17 vendor positions in the matrix were left blank, indicating either incomplete evaluations at the time the document was prepared or the template structure allowing for additional bidders.
The scoring framework demonstrates a balanced emphasis on technical qualifications and pricing considerations, with equal weighting given to Price and Understanding of Requested Services as the most significant evaluation factors. No scoring deductions were applied to any evaluator's assessment. The matrix structure accommodates evaluation by up to five independent reviewers to ensure comprehensive and objective proposal assessment. The presence of this detailed evaluation documentation indicates the procurement process had advanced to the proposal evaluation stage, though the file does not contain information regarding contract award decisions, final contract terms, pricing details, or contract duration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00016737 ITA.docx | DOCX document | |
| 00016737 Mini Final.docx | DOCX document | |
| 00016737 Mini RFP Att D BOC.xlsx | XLSX spreadsheet | |
| 00016737 Mini RFP Att C Key Staff Resumes.docx | DOCX document | |
| 00016737 Mini RFP Att B References.doc | DOC document | |
| 00016737 Mini RFP Att A Cover Sheet.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Proposal Detail Scores
| S-73000-00016737 Crash Data Safety Consultant Support Services | ||||||||
| SOP SCORE DETAILS | ||||||||
| Proposal Evaluation Detail Scores | ||||||||
| Evaluation Team | ||||||||
| Maximum | ||||||||
| Score | evaluator 1 | evaluator 2 | evaluator 3 | evaluator 4 | evaluator 5 | |||
| 1 | DKS Associates | |||||||
| 3.2.1 | EVALUATION ITEM 1 – Understanding of Requested Services | 30 | 30 | 27 | 15 | 28 | ||
| 3.2.2 | EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | 20 | 20 | 20 | 25 | ||
| 3.2.3 | EVALUATION ITEM 3 – Availability | 20 | 20 | 18 | 20 | 25 | ||
| 3.2.4 | EVALUATION ITEM 4 – Project Samples | 20 | 20 | 20 | 20 | 10 | ||
| 3.2.5 | EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | 9 | 10 | 5 | |||
| 3.2.6 | EVALUATION ITEM 5 – Price | 20 | 20 | 20 | 20 | |||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| Total | 120 | 119 | 115 | 100 | 88 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 119 | 115 | 100 | 88 | 0 |
| 2 | Firm Name | |||||||
| 3.2.1 | EVALUATION ITEM 1 – Understanding of Requested Services | 30 | ||||||
| 3.2.2 | EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | ||||||
| 3.2.3 | EVALUATION ITEM 3 – Availability | 20 | ||||||
| 3.2.4 | EVALUATION ITEM 4 – Project Samples | 20 | ||||||
| 3.2.5 | EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | ||||||
| 3.2.6 | EVALUATION ITEM 5 – Price | 20 | ||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 3 | Firm Name | |||||||
| 3.2.1 | EVALUATION ITEM 1 – Understanding of Requested Services | 30 | ||||||
| 3.2.2 | EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | ||||||
| 3.2.3 | EVALUATION ITEM 3 – Availability | 20 | ||||||
| 3.2.4 | EVALUATION ITEM 4 – Project Samples | 20 | ||||||
| 3.2.5 | EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | ||||||
| 3.2.6 | EVALUATION ITEM 5 – Price | 20 | ||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 4 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 5 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 6 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 7 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 8 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 9 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 10 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 11 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 12 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 13 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 14 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 15 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 16 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 17 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |
| 18 | Firm Name | |||||||
| EVALUATION ITEM 1 – Understanding of Requested Services | 30 | |||||||
| EVALUATION ITEM 2 – Specific Experience of Key Staff | 20 | |||||||
| EVALUATION ITEM 3 – Availability | 20 | |||||||
| EVALUATION ITEM 4 – Project Samples | 20 | |||||||
| EVALUATION ITEM 5 – Clarity of Proposal and Conformity with Requirements | 10 | |||||||
| EVALUATION ITEM 5 – Price | 20 | |||||||
| Enter Eval Criterion 7 | 0 | |||||||
| Enter Eval Criterion 8 | 0 | |||||||
| Enter Eval Criterion 9 | 0 | Scoring Deductions | ||||||
| TOTAL | 120 | 0 | 0 | 0 | 0 | 0 | 0% | |
| Scoring Deduction Points | 0 | 0 | 0 | 0 | 0 | |||
| TOTAL (incl. Scoring Deductions) | 0 | 0 | 0 | 0 | 0 |