This document is an Addendum 1 issued by the Oregon Department of Transportation (ODOT) for Invitation to Bid (ITB) No. S-73000-00014905, pertaining to the US 95 Idaho State Line - Rome Chip Seal Project. The addendum extends the bid closing date from October 23, 2025, to October 30, 2025, at 10:00 AM, and modifies key project dates. The project involves a pavement preservation chip seal along US 95 from the Idaho State Line to Rome, spanning approximately 36.47 miles in Malheur County. The updated project timeline now specifies a start date no earlier than April 1, 2026, with substantial completion moved to August 31, 2026, and final completion to September 15, 2026.
The addendum also updates Section 00220 regarding lane closure provisions, allowing single and two-lane closures during specific periods from April 1 to August 31, with restrictions on daily and weekly work hours. The project requires accommodating permitted annual and over-dimension loads with minimal delays. While specific budget details are not provided in the addendum, the original contract opportunity summary indicates comprehensive requirements including workforce development mandates, with contractors required to employ apprentices for 12 percent of work hours. The project is subject to state prevailing wage rates, Buy America provisions, and includes liquidated damages provisions for delays and unauthorized lane closures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00014905 Preliminary Results.xlsx | XLSX spreadsheet | |
| 00014905 Attachment A Special Provisions.pdf | ||
| 00014905 Invitation.To.Bid.docx | DOCX document | |
| 00014905 Attachment E Apprenticeship Requirements.docx | DOCX document | |
| 00014905 Attachment C Bid Pricing Form.xlsx | XLSX spreadsheet | |
| 00014905 Attachment D Material Source Narrative.pdf | ||
| 00014905 Attachment B Plans..pdf | ||
| 00014906 Specifications V2.doc | DOC document | |
| 00014905 Intent To Award.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| DATE: |
| 10/22/2025 |
| OREGON DEPARTMENT OF TRANSPORTATION |
INVITATION TO BID
ADDENDUM NO. 1
| ITB NO.: |
| S-73000-00014905 |
| CLOSING DATE: |
| 10/23/2025 |
| TIME: |
| 10:00 AM |
| DESCRIPTION: |
| US 95 Idaho State Line – Rome Chip Seal Project |
| BUYER: |
| Dave Dethloff |
| EMAIL: |
| William.d.dethloff@odot.oregon.gov |
| PHONE: |
| 503-569-8793 |
Requests for clarification, requests for change, and protests of this Addendum are due no later than:
Friday 10/24/2025 @ 5:00 PM.
This Addendum modifies the Invitation To Bid (ITB) document(s) only to the extent indicated herein. All other areas not changed or otherwise modified by this Addendum remain in full force and effect. This Addendum is hereby made an integral part of the ITB document. Bidder must be responsive to any requirements of this Addendum as if the requirements were set forth in the ITB. Acknowledge receipt of this Addendum by indicating its number in the spaces provided ITB Section H – Addenda Acknowledgement. Failure to do so may result in Bid rejection. See the ITB regarding pre-opening modifications of Bids, where to send Bid modifications, requests for clarification or change and protests of this Addendum, and the deadlines for the foregoing.
THE PURPOSE OF THIS ADDENDUM IS TO: Extend the bid closing date, extend the substantial and final completion dates, and update Section 00220 in Attachment A Special Provisions.
Bid closing date and time as listed in OregonBuys is changed from 10/23/2025 @ 10:00 AM to 10/30/2025 @ 10:00 AM.
Document labelled “00014905 Invitation.To.Bid.docx” Section A.1 INTRODUCTION, Sub Section A.1.2.1 REQUIRED PROJECT DATES., is amended as follows. New language is Bold and Underlined; deleted language is struck through.
· A.1.2.1 REQUIRED PROJECT DATES.
| START DATE: NOT PRIOR TO 04/01/2026 |
| SUBSTANTIAL COMPLETION: 08/15/2026 08/31/2026 |
| FINAL COMPLETION: 08/31/2026 09/15/2026 |
Document labelled “00014905 Invitation.To.Bid.docx” Exhibit 5 (Sample) STATE OF OREGON PUBLIC IMPROVEMENT AGREEMENT FORM, Section 3. Required Contract Dates., is amended as follows. New language is Bold and Underlined; deleted language is struck through.
· 3. Required Contract Dates.
START DATE: NOT PRIOR TO 04/01/2026
SUBSTANTIAL COMPLETION: 08/15/2026 08/31/2026
FINAL COMPLETION: 08/31/2026 09/15/2026
Document labelled “00014905 Attachment A Special Provisions” Section 00220 – ACCOMMODATIONS FOR PUBLIC TRAFFIC, Sub Section 00220.4(e)(1) Closed Lanes, is amended as follows. New language is Bold and Underlined; deleted language is struck through
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
Traffic Lanes may be closed on the I.O.N. Highway (US95) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
Single Lane Closures – One Traffic Lane on the I.O.N. Highway (US95) may be closed during the following times:
• April 1 to October August 31, weekly, Sunday at 9 p.m. through Friday at 3 p.m.
Accommodate all permitted annual and over-dimension loads by providing clear passage through the lane closure with a maximum delay of 20 minutes at each lane closure. Suspend operations and move construction equipment and traffic control devices as required to provide safe passage of all permitted annual and over-dimension loads.
Two-lane Closures – Two Traffic Lanes on the I.O.N. Highway (US95) between mile point
19.10 and mile point 20.40 may be closed during the following times:
• April 1 to October August 31, weekly, Sunday at 9 p.m. through Friday at 3 p.m.
One Traffic Lane may be closed on all other adjacent Roadways within the Project Site not listed above, when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
• Daily, Monday through Thursday, between 7:00 a.m. and 7:00 p.m.
• Friday, between 7:00 a.m. and 3:00 p.m.
ITB_ADDENDUM, S006-G031521