This document is a Notice of Intent to Award from the Oregon Department of Transportation (ODOT) Procurement Office for RFP S-73000-00013855 for Audiometric Services. Listen Audiology Services, Inc. has been selected as the top-ranked firm for contract negotiations to provide Personal Services, with the award process detailed in a comprehensive timeline. The notice outlines a structured negotiation process involving establishing a statement of work (SOW), completing a Breakdown of Costs (BOC), and securing necessary approvals, with specific timelines for each stage ranging from 3-20 business days depending on project complexity.

The document emphasizes that no work is authorized until the contract is fully executed and a written Notice to Proceed (NTP) is issued by the ODOT Project Manager. The procurement includes requirements for submitting various documents such as Billing Rate Information, Certificates of Insurance, Responsibility Inquiry form, Business Registry Number, and W-9 Form. Additionally, ODOT encourages the use of direct deposit via Automated Clearing House (ACH) for consultant payments and suggests that consultants make reasonable efforts to offer ACH direct deposit payments to their subcontractors. The notice also notes that if negotiations cannot be completed within the specified timeframe, ODOT may terminate discussions and begin negotiations with the next highest-ranked firm.

View the file

Other files

File Type Posted
00013855_AttB.doc DOC document
00013855_AttC~1.doc DOC document
00013855_Evaluation Score Summary.pdf PDF
00013855_AttE_Final.xls XLS spreadsheet
00013855_Mobile Audiometrics_RFP_Final.doc DOC document
Notice to Award_Broadmoor and Schmeer Design RFP.pdf PDF
00013855_AttF_Sample Test Schedule.xlsx XLSX spreadsheet
00013855_AttA_Sample Contractv_Final~1.docx DOCX document
S-73000-000013855 _QA 1_Final.docx DOCX document
S-73000-00013855 _Addendum 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Transportation Procurement Office

355 Capitol St NE, MS#3-3 Salem, OR, 97301

Phone: (503) 986-2710 Fax: (503) 986-5790

OREGON DEPARTMENT OF TRANSPORTATION

Notice of Intent to Award

DATE: June 18, 2025 TO: All Proposers for RFP S-73000-00013855 (Audiometric Services) SUBJECT: Notice of Intent to Award

Listen Audiology Services, Inc. is the top-ranked firm selected for negotiations of a contract to provide Personal Services as specified in the above referenced RFP. The scores and rankings of all Proposers are shown in the score matrix accompanying this notice. The award submittal requirements stated in the RFP are summarized in Attachment 1 of this notice.

Robert Snyder will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work (SOW), schedule of performance and costs under the contract. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC-NBR as applicable) and submitted to ODOT’s PM. A BOC must demonstrate subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal set forth in the RFP. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:

Activity Responsible Party Business Days

N eg ot ia tio ns

Establish work session to discuss the SOW with Consultant

ODOT PM Within 5-10 days of this notice (days depend on size and complexity of the project) Respond to work session with comments/edits to SOW Consultant Within 5 days of work session Respond to SOW comments/edits ODOT PM Within 3 days of receipt of Consultant comments/edits

Submission of BOC / Billing Rates Consultant Within 5-10 days of final ODOT scope (days depend on size and complexity of the project)

Activity Responsible Party Business Days Respond to BOC, billing rates, negotiate, and

Submit for legal sufficiency

ODOT PM / OPO

OPO

Within 5-10 days of Consultant submission of the BOC (days depend on the size and complexity of the project) Legal Sufficiency OPO, ODOT PM, and DOJ Within 15 (Mini- Solicitation) & 20 (Formal) days of submission by ODOT PM Signature routing and execution OPO, Consultant, and ODOT Expenditure Authority (if required)

Within 6-8 days from initial routing

Issue Notice to Proceed (NTP) ODOT PM 1 day after execution

Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice.

If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon.

If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).

Note that no work is authorized until the contract is executed and Consultant has received a written NTP from the ODOT PM.

ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.

Sincerely, Sarika Herigstad

Procurement & Contract Specialist | ODOT Procurement Office

Attachment 1 – Award Submittal Requirements

Please email to me, the Contract Coordinator, the following items if marked as “REQUIRED” in the RFP (see detailed requirements and due date for each item in Section 4.2 of the RFP).

• Billing Rate Information

• Breakdown of Costs

• Certificates of Insurance

• Responsibility Inquiry form

• Business Registry Number

• W-9 Form

Direct Deposit via Automated Clearing House (ACH). For Consultants that receive ongoing monthly payments from Agency on one or more contracts or work orders, Agency prefers making Consultant payments via ACH direct deposit. While not required, if Consultant has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, Consultant must complete a Vendor ACH Authorization form and submit to Agency per the instructions on the form. To expedite Consultant’s payments to its subcontractors, if applicable, Consultant should make reasonable efforts to offer ACH direct deposit payments.