00013012 Att A Revised Special Provisions V2.docx

DOCX document 56 KB Posted

Attached to
Central Oregon Highway 20 Chip Seal, MP 33 - 62. 1
Solicitation number
S-73000-00013012
Issued by
Deschutes County, Oregon

About this file

This document is a Special Provisions attachment for an Invitation to Bid (ITB) issued by the Oregon Department of Transportation (ODOT) for a highway maintenance project on Central Oregon Highway 20. The project involves chip sealing approximately 33 miles of highway from mile post 33 to 62.1, and includes comprehensive roadway maintenance services such as traffic control, installing temporary pavement markers, and permanent striping. The work is scheduled to be performed between May 15 and August 15, with bidders required to demonstrate at least two years of experience in emulsified asphalt chip seal applications. The bid documents were posted on March 21, 2025, with proposals due by April 9, 2025, and the contract will be awarded on a unit price basis.

The contract includes a one-year warranty period with payment limited to 75% until the warranty begins and potential price adjustments based on the expected life of the chip seal. The project will utilize polymer-modified emulsified asphalt and requires strict quality control measures, with specific technical requirements including a minimum pavement temperature of 70°F and humidity below 75%. The bid includes 18 distinct line items covering various aspects of roadway maintenance, and while no specific set-aside designations were mentioned, the project appears open to qualified contractors with appropriate highway maintenance experience. The technical specifications emphasize long-term performance and durability of the road surface, indicating a sophisticated approach to infrastructure maintenance.

View the file

Other files

File Type Posted
ODOT_TM782_flakiness_index~1.pdf PDF
ODOT_TM780_Sand_Circle~1.pdf PDF
00013012 Invitation to Bid.docx DOCX document
ODOT_TM781_agg_loss~1.pdf PDF
MP 67 Location that can be used..PNG PNG image
Health Benefits Actuary RFP 2025 QA Addendum.pdf PDF
00013012_Att C_Bid Pricing Form.xlsx XLSX spreadsheet
MP 87 Stock Pile.PNG PNG image
00013012 Prelim Bid Results.xlsx XLSX spreadsheet
00013012 Addendum 4.docx DOCX document
00013012 Att A Special Provisions.docx DOCX document
MP 35 Stock Pile.PNG PNG image
00013012 Att C Revised Bid Pricing Form V2~1.xlsx XLSX spreadsheet
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A – REVISED Special Provisions V2

PROJECT NAME: Central Oregon Highway 20 Chip Seal, MP 33 – 62.1

SCOPE OF WORK: Chip Seal of OR 20 and associated work. The work also includes performing all traffic control, installing temporary pavement markers, and permanent striping.

WORK LOCATION: The work is located on OR 20, MP 33 to MP 62.158, approximately 33 miles East of Bend, OR.

PROJECT MANAGER:

Tyson Snell 63055 N. Hwy 97. Bldg. K Bend, OR 97703 Phone: (541) 527-2087 Email: Tyson.a.snell@odot.oregon.gov

APPLICABLE SPECIFICATIONS: The Specifications which are applicable to the work on this project are the 2024 Oregon Standard Specifications for Construction (“Standard Specifications”), which are by this reference incorporated herein and the Special Provisions. The Standard Specifications include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Specifications. Sections of the technical specifications not identified in the Plans and Specifications remain applicable to the Contract according to their original terms.

Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in the Plans and Specifications as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

COOPERATION WITH UTILITIES: This project is located within the Oregon Utility Notification Center area, which is a utilities notification system for notifying owners of utilities about work being performed in the vicinity of their facilities. The contractor shall notify owners of Utilities prior to the performance of work in the vicinity of their Utilities. The utilities notification system telephone number is 811 (or use the old number which is 1-800-332-2344).

PAYMENT: Payment for all work under this contract is to be included in the bid items contained in the Bid Schedule. Payment constitutes full compensation to the Contractor for furnishing all Materials, Equipment, labor and incidentals necessary to complete the work as specified. There will be no separate payment for items not listed, as that work will be included in payment made for the items listed in the Bid Schedule.

PAYMENT TO CONTRACTOR: The Contractor shall be paid upon completion of contract work. A bill must be submitted to the Project Manager for payment processing. There shall be no retainage for work performed under this contract.

PRECONSTRUCTION CONFERENCE, SCHEDULE AND LIMITATIONS OF OPERATIONS: The Contractor shall meet with the Project Manager for a preconstruction conference at a mutually agreed upon time. Work shall commence within 10 working days of this meeting providing the Notice to Proceed has been received. At the preconstruction conference, submit a project schedule to plan, coordinate and control the progress of construction and traffic control installations. The project schedules will take into account the orderly, timely, and efficient prosecution of the work in sufficient detail to enable both the Contractor and the Project Manager to plan, coordinate, appraise, document, and control their respective contract responsibilities. The predicted Completion date(s) for the project schedule shall be within the specified contract time.

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

00220.02(a) General Requirements - Add the following bullet to the end of the bullet list:

· Accommodate all over-dimensional loads through the work zone with. Do not hold or delay over-dimensional loads for more than 20 minutes.

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Traffic Lanes may be closed on the Central Oregon Highway (#007) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

Single Lane Closures – One Traffic Lane on US20 may be closed at any time. Limit the length of the work area to 2 miles between flaggers. Maintain 13ft lane width.

One Traffic Lane on OR27 Crooked River Hwy (#014) may be closed at any time.

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.90(b) Temporary Protection and Direction of Traffic ‑ Delete the bullet that begins “Moving temporary barrier to and from Contractor’s stockpile areas”.

Replace the bullet that begins "When the Schedule of Items does not include …" with the following bullet:

Preparing and signing the daily “Traffic Control Inspection Report”, when a TCS is not included in the Schedule of Items or when a TCS is not onsite for a work shift.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications modified as follows:

00222.40(e) Temporary Sign Placement ‑ Add the following to the end of the bullet list:

· Install beyond each end of the Project, facing outgoing traffic, an "END ROAD WORK" (CG20‑2A‑24) sign a distance of (A ÷ 2) according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans.

· During Emulsified Asphalt surface treatment operations, protect traffic by installing signing according to the "LOOSE GRAVEL IN ROADWAY SIGNING" detail shown on the Standard Drawings. The maximum length of loose Sand or Gravel shall not exceed 5 miles.

· When the existing centerline striping on the Central Oregon highway is obliterated, do the following:

· Place a "NO CENTER LINE" (W8‑12) sign with a 24 by 18-inch "NEXT 30 MILES" (W7‑3aP) plaque, approximately 2,500 feet in advance of each end of the Project.

· Place "NO CENTER LINE" (W8‑12) signs on approximately 2 mile intervals for each direction of traffic.

· Install a 60 by 36-inch "INTERMITTENT ROAD WORK NEXT 30 MILES" (CG20‑13) sign on the OR 20, in advance of the "ROAD WORK AHEAD" (W20‑1) sign on each end of the Project according to sign spacing "A" from the "TCD Spacing Table" shown on the Standard Drawings.

· During pilot car operations, install a 12 by 12-inch "WAIT FOR PILOT CAR" (CR4‑20a) sign in private residential driveways accessing the Highway within the limits of the pilot car operation. Place the sign in the driveway facing the private residence and so the sign face is not visible to Public Traffic on the Highway. Do not use the sign for apartments, condominiums or business accesses.

· At accesses, side roads, or residential driveways where "WAIT FOR PILOT CAR" (CR4‑20) signs are installed, do not allow traffic to be stopped or held for longer than 20 minutes.

· In addition to the signs, public notification (e.g. flyers, door hangers) may be used to inform the residents that may be affected by the pilot car operations and the "WAIT FOR PILOT CAR" signs.

· For each location of the "WAIT FOR PILOT CAR" sign, closely monitor for traffic compliance, operation, and safety at least once per hour during pilot car operations. If operational issues are observed, or if notified of operational issues, at stop-controlled accesses or side roads utilizing the "WAIT FOR PILOT CAR" (CR4‑20) sign, remove the sign and replace it with a flagger.

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

Comply with Section 00223 of the Standard Specifications modified as follows:

00223.31(b) Traffic Control Inspection Without TCS ‑ Replace the bullet that begins “Prepares and signs a daily “Traffic Control Inspection Report”…” with the following bullet:

Prepares and signs a “Traffic Control Inspection Report” (Form No. 734-2474) upon the initial installation of TCM and each working day when any modification, removal, or reinstallation of TCM are made, or as directed by the Engineer. Submit completed reports to the Engineer no later than the end of the next working day.

00223.43 Automated Flagger Assistance Device ‑ Replace the bullet that begins “Install and operate the AFAD…” with the following bullet: Comment by KLEINBERG Austin: AFAD language requested by Ramon

Install and operate the AFAD according to the manufacturer’s instructions and as described in Section 3.11 of the Oregon Temporary Traffic Control Handbook (OTTCH).

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

Comply with Section 00224 of the Standard Specifications

SECTION 00225 - TEMPORARY PAVEMENT MARKINGS

Comply with Section 00225 of the Standard Specifications modified as follows:

00225.40 Temporary Pavement Markers - Replace the paragraph that begins "Unless otherwise shown..." and the three bullets with the following paragraphs and bullets:

Install temporary flexible oiling pavement markers for temporary centerline marking as follows:

· Place and maintain one temporary flexible oiling pavement marker on 40-foot spacing in tangent and curve sections except as below.

· Place and maintain one temporary flexible oiling pavement marker on 20-foot spacing in curved alignment sections identified by a speed rider displaying less than the posted speed and channelization areas.

Establish alignment for placing the temporary flexible oiling pavement markers as follows:

Control markers at:

· 200‑foot intervals on tangents

· 50‑foot intervals on curves

· 40‑foot intervals on curves with speed rider

· Use string line or other appropriate means to maintain proper alignment of the markers. Adjust placement to avoid straddling a longitudinal joint, while maintaining a suitable alignment of markers.

· Remove and replace misaligned markers at no additional cost to the Agency.

00225.40(b) Flexible Oiling Pavement Markers - Add the following paragraphs to the end of this subsection:

Remove the markers on underlying surfaces before placing the next full Lift of paving that would obliterate the marker.

Use flexible oiling pavement markers with double covers, as directed, when a surface treatment requires two oil applications for a single Pavement Lift. Remove the marker covers, as directed, before reopening the Roadway to traffic.

SECTION 00280 - EROSION AND SEDIMENT CONTROL

Comply with Section 00280 of the Standard Specifications.

SECTION 00305 - CONSTRUCTION SURVEY WORK

Comply with Section 00305 of the Standard Specifications modified as follows:

00305.00 Scope – Add the following to the end of this subsection:

In addition to the requirements of the ODOT Construction Surveying Manual for Contractors, establish Engineering Stationing at 500 foot intervals for the length of the project along the shoulder of the highway. Maintain the stationing so it is visible throughout construction of the project.

SECTION 00705 - EMULSIFIED ASPHALT PRIME COAT AND EMULSIFIED ASPHALT FOG COAT

Comply with Section 00705 of the Standard Specifications.

SECTION 00710 - SINGLE APPLICATION EMULSIFIED ASPHALT CHIP SEAL

Replace this Section, except for the Section number and title, with the following:

Description

00710.00 Scope - This Work consists of applying Emulsified Asphalt and graded Aggregates as shown.

The Emulsified Asphalt and Aggregate size will be designated in this Section.

This Work includes a Contractor Warranty and the Contractor Warranty includes the Work performed under this Section and the Work performed under Section 00705.

00710.01 Definitions:

Flushing – A pavement condition where excess asphalt binder is present at the pavement surface, in a solid or semi-solid state. Flushing occurs when the texture depth is less than 0.9 mm (.035 in.) as measured according to ODOT Provisional TM 780.

Loss of Cover Aggregate – A pavement condition where aggregate has become displaced from the Emulsified Asphalt Chip seal and occurs when the degree of Loss of Cover Aggregate is greater than 6 according to ODOT Provisional TM 781.

Macro Texture – The texture of the Emulsified Asphalt Chip seal which can easily be seen by the eye.

Segment – A segment size is 528 continuous feet in a travel lane.

Sublot – The sublot size is 1 continuous lane mile or 5280 feet.

00710.02 ODOT Provisional Test Methods – The following ODOT Provisional Test Methods are applicable to the Work in this Section and Work in Section 00705:

ODOT Provisional TM 780 – Sand Circle Test ODOT Provisional TM 781 – Loss of Cover Aggregate ODOT Provisional TM 782 – Flakiness Index of Aggregates

The version in effect at the time of Advertisement is the applicable version. These test methods are available from the Engineer.

00710.03 Submittals - Submit the following to the Engineer at least 14 days prior to the placement of the Emulsified Asphalt Chip seal:

· An Emulsified Asphalt Chip seal design according to 00710.13

· Personnel experience documentation according to 00710.32

· If requested, a 100 lb. sample of aggregate from each proposed aggregate source and two quarts of Emulsified Asphalt from each supplier.

Materials

00710.10 Aggregates – Aggregates will be furnished by the Agency

· Aggregates are located in the following locations

· M.P. 35 approximately 1331 yd3

· M.P. 86 approximately 3915 yd3

(h) Taking Aggregates from Agency Stockpiles - When it is specified that Aggregates are to be taken from Agency-controlled stockpiles, take the material in an orderly manner. Do not contaminate the materials. Salvage all material possible from the area which the material is taken. Shape unused portions of a stockpile to Neat Lines. The Contractor will be charged for materials wasted through negligence or used without authority.

00710.11 Emulsified Asphalt Furnish PMCRS-2h polymer-modified Emulsified Asphalt conforming to the requirements of ODOT's publication, "Standard Specifications for Asphalt Materials". Copies of the publication are available from the ODOT State Pavement Engineer. The applicable Specifications are those contained in the current publication on the date the Project is advertised, as modified in this subsection.

Excessive delay in the use of the Emulsified Asphalt or excessive pumping of the Emulsified Asphalt may significantly reduce the viscosity and may make the material unsuitable for chip seal use. For this reason, limit pumping between the bulk storage tank, hauling transportation, field storage tanks and distributor to an absolute minimum to maintain proper viscosity.

Obtain samples of Emulsified Asphalt according to AASHTO T 40 at the frequency indicated in the MFTP. Samples will be tested at the ODOT Materials Laboratory, or other laboratory as designated by the Agency. Polymer-modified Emulsified Asphalt will be tested within 14 Calendar Days from the date it is sampled.

00710.13 Emulsified Asphalt Chip Seal Design Requirements - Do not start placing the Emulsified Asphalt Chip seal on the Project until the Emulsified Asphalt Chip seal design is reviewed by the Engineer and written consent is provided to proceed. The Emulsified Asphalt Chip seal design will be evaluated based on the criteria identified in the latest Oregon Emulsified Asphalt Chip Seal Design Guide available from the Engineer. A new Emulsified Asphalt Chip seal design is required if the Emulsified Asphalt supplier or the source of the Aggregate change during production.

The Emulsified Asphalt Chip seal design shall include the following:

· Gradation and all quality test results, as specified in 00710.10

· Design application rate of aggregate

· Design application rate of emulsified asphalt

00710.15 Aggregate Production Quality Control - Provide quality control during production of Aggregate according to Section 00165. Sampling and Testing shall be performed by a CAgT at the minimum frequency schedule indicated in the MFTP.

(a) Quality Control Compliance - Evaluate Aggregates for compliance according to the following:

(1) Gradation - Analyze gradation statistically according to Section 00165. A stockpile contains specification Aggregate when the Pay Factor (PF) for each sieve size calculated according to 00165.40 is equal to or greater than 1.00.

When the results from Table 00165-2 yield a Pay Factor of less than 1.00 for any sieve size, the material is non-specification. The Engineer will reject any stockpile of Aggregate containing non-specification material unless the non-specification material is removed from the stockpile. Do not add additional material to such a stockpile until enough non-specification material is removed so that the PF for each sieve size is equal to or greater than 1.00.

(2) Other Tests - Stop production, make appropriate operational adjustments, and remove all failing material from the stockpile whenever a quality control test result, other than sieve analysis, does not meet Specifications. Document operational adjustments made and notify the Engineer prior to resuming production.

(3) Preproduced Aggregate - Compliance of Aggregates produced and stockpiled before the Award of this Contract will be determined by either of the following:

· Continuing production records meeting the requirements of 00710.10 and 00710.15.

· Sampling according to AASHTO T 2 and testing the entire stockpile at the minimum frequency schedule indicated in the MFTP. The material shall meet the requirements of 00710.10 and 00710.15.

(b) Quality Assurance of Aggregate - The Agency will perform Aggregate production quality assurance according to Section 00165, the MFTP and the ODOT Quality Assurance Program.

Equipment

00710.20 Equipment - Provide a pressure distributor, hauling vehicles, aggregate spreader, compactors, power brooms and other necessary Equipment to ensure efficient operation and construction to meet specified results. Provide Equipment in sufficient number and capacities that will provide coordinated and uniform progress of the Work.

Provide two-way radio communication between the asphalt distributor and aggregate spreader.

00710.21 Asphalt Distributor - Provide an asphalt distributor designed, equipped, maintained and operated so the Emulsified Asphalt material may be applied uniformly at even heat. The distributor shall be capable of applying the asphalt on variable surface widths up to 16 feet, at readily determined and controlled rates from 0.05 - 2.0 gallons per square yard, and with uniform pressure. The variation allowed from any target rate shall not exceed 0.02 gallons per square yard. Provide distributor Equipment that includes a tachometer, pressure gauges, accurate volume measuring devices and a thermometer for measuring temperature of tank contents. Provide distributors equipped with a positive power unit for the asphalt pump, and full circulation spray bars adjustable both laterally and vertically. Set the bar height for triple lap coverage.

00710.22 Aggregate Spreaders - Provide self-propelled aggregate spreaders equipped with a mechanical device that will spread the Aggregate at a uniform rate across the full width of the aggregate spreaders. Provide aggregate spreaders of adequate width to provide full coverage of the specified Panel and without placing joints in the travel lanes. Provide field verification that the aggregate spreader is calibrated to maintain an application rate within 10% of the target rate.

00710.23 Compactors - Provide self-propelled pneumatic-tired or steel-wheeled rollers in good condition and capable of operating at speeds compatible with the chip seal operation. Provide two pneumatic-tired rollers and one steel-wheeled roller as described below.

(a) Pneumatic-tired Rollers - Provide self-propelled, tandem or multiple axle, multiple wheel type pneumatic-tired rollers with smooth-tread pneumatic tires of equal size. The tires shall be staggered on the axles at such spacing and overlap that will provide uniform compacting pressure for the full compacting width of the roller. The minimum load per tire shall be 2,800 pounds, with tire inflation pressures of 45 psi to 90 psi.

(b) Steel-wheeled Rollers - Provide steel-wheeled rollers with a gross static weight of at least 6 tons. Use for final rolling as necessary.

00710.24 Power Brooms - Provide pickup or non-pickup type power brooms equipped with a positive means to control vertical pressure. Pickup power brooms are required where there is curb and gutter or adjacent paved areas. Non-pickup type power brooms may be used when the edge of pavement is immediately followed by a roadside ditch. Do not broom material into adjacent waterways according to 00710.61.

Labor

00710.30 Quality Control Personnel - Provide a technician having a CAgT technical certification.

00710.31 Technical Representative - Provide a qualified technical representative from the Emulsified Asphalt Supplier, on site, during all chip seal operations. The technical representative’s duties are to advise the Contractor on standard industry installation procedures, to assist the Contractor in establishing the asphalt binder and Aggregate application rates, and to provide input on adjustments to the application rates.

00710.32 Personnel Qualifications - Provide personnel skilled in the application of Emulsified Asphalt Chip seals. The experience shall be relevant to the anticipated conditions, materials, and construction techniques for Emulsified Asphalt Chip seals. The on-site supervisor shall have at least two years of experience in applying Emulsified Asphalt Chip seals and have successfully installed at least 20 lane miles of Emulsified Asphalt Chip seals within the previous four years.

Construction

00710.40 Season and Weather Limitations - Do not apply Emulsified Asphalt when the Pavement temperature is below 70 °F, or if the humidity is higher than 75 percent. Complete the application of the Emulsified Asphalt and the Aggregate 3 hours before sunset. Remove by milling, or other methods approved by the Engineer, and replace all chip seals damaged by weather during the first 24 hours after application at no additional cost to the Agency. The placing of single application Emulsified Asphalt chip seals will not be allowed before May 15 or after August 15.

00710.41 Rate of Progress and Scheduling - Do not apply more chip seal in any 1 Day than can be broomed the following morning, unless approved by the Engineer.

00710.42 Preparation of Underlying Surfaces - Immediately before applying the Emulsified Asphalt, clean and dry the surface to be treated.

00710.43 Sequence of Operations - Construct the single application Emulsified Asphalt chip seal with a single spread of Emulsified Asphalt followed immediately with a single spread of Aggregate and initial rolling. Chip seal is not required for guardrail flares, driveways, or other irregular areas unless directed.

00710.44 Application Rates - Refer to the latest Oregon Emulsified Asphalt Chip seal Design Guide as a guideline for determining initial application rates of the Emulsified Asphalt and the Aggregate. If the initial application rates are different from the design application rates, document and submit to the Engineer. Document and submit additional adjustments to the application rates during placement of the Emulsified Asphalt Chip seal.

00710.45 Applying Emulsified Asphalt - Apply Emulsified Asphalt at the rates according to 00710.44 and the following:

· Leave a minimum of 200 gallons of Emulsified Asphalt in the distributor tank at all times.

· Do not apply Emulsified Asphalt to more than one-half the width of the Traveled Way at one time with the remaining width remaining open to traffic. Apply the chip seal, weather permitting, to both sides of the travel way so that the end of the Work is squared up 3 hours before sunset.

· Do not apply Emulsified Asphalt a greater distance than can be immediately covered by Aggregates before the emulsion breaks.

· Place building paper over the treated surface at the beginning of each spread to ensure that the nozzles are operating properly before the uncovered surface is reached and to avoid double application. Remove and dispose of building paper in a manner satisfactory to the Engineer.

· If requested by the Engineer, demonstrate that the distribution of the Emulsified Asphalt does not vary between the individual nozzles by more than 15 percent transversely from the average, and no more than 10 percent longitudinally from the specified rate of application.

· Apply the Emulsified Asphalt at a temperature between 140 °F and 185 °F or as recommended by the manufacturer.

00710.46 Hauling and Spreading Aggregates - Spread Aggregates at the rates according to 00710.44.

Do not operate hauling and spreading Equipment on uncovered Emulsified Asphalt. Carefully operate hauling Equipment at all times, at moderate speeds that will not damage the new chip seal or create a hazard to the traveling public. Route hauling Equipment and pilot lines uniformly over the full width of the new surface in place.

Calibrate the gate opening, gear selection and engine RPM of the aggregate spreaders for the various sizes of Aggregate to be used. Following calibration, verify the rate of application by a method acceptable to the Engineer.

Immediately cover the Emulsified Asphalt surface with Aggregate unless otherwise authorized by the Engineer. Remove or repair Emulsified Asphalt that has set or "broke" before being covered with Aggregate, at no additional cost to the Agency.

Aggregates shall be surface damp at the time of application. Excess free water (water not adhering to the Aggregate surface) on the Aggregate will not be allowed.

Do not operate the aggregate spreader at speeds which cause the aggregates to roll over after striking the emulsion covered surface.

Provide coverage without gaps or overlapping adjacent coverages. Do not construct longitudinal joints within the travel lanes.

Construct neat transverse cut off of Aggregates and remove any excess Aggregates from the surface prior to resuming operations.

00710.47 Shaping and Compacting - After the Aggregates have been placed on the Emulsified Asphalt, spread or remove all piles, ridges, or uneven distribution to ensure against rough spots in the final surface.

Compact the surface with a minimum of two coverages with a pneumatic-tired roller. Continue compacting until the material is interlocked, firm and partially bound with the underlying Emulsified Asphalt.

Operate rollers at speeds such that the rollers do not pick up Aggregates from the surface. Do not exceed rolling speeds of 5 mph.

Maintenance

00710.61 Power Brooming - Following the application of the chip seal, carefully broom the entire surface to remove loose Aggregate. Discontinue the operation if brooming damages the chip seal. Use a minimum of two power brooms.

Subsequent brooming may be directed by the Engineer to ensure that the surface is free of loose Aggregate that could cause vehicle damage.

In curbed areas, use a pick-up type power broom. On Bridges, sidewalks and other areas off the roadway, remove all loose Aggregates to the satisfaction of the Engineer. Dispose of loose Aggregate at least 150 feet from the nearest waterway in areas identified for this purpose.

00710.72 Inspection and Repairs

- After the chip seal Work described in this Section is complete and the Work identified in Section 00705 has been completed the Engineer will perform an inspection within 14 Days following completion of the chip seal and Work identified in Section 00705 to accept the Work or to determine if any failures exist. Failures are defined in 00710.75(b).

If no failures are identified the Engineer will notify the Contractor in writing that the warranty period has begun and the start date for the warranty will be the date of acceptance of the Work.

If the Engineer identifies failures, provide repairs according to this Subsection and Section 00705. When the Engineer is satisfied that repairs have been made then the Engineer will notify the Contractor in writing that the warranty period has begun and the start date for the warranty will be will be the date of acceptance of the repairs.

Before making repairs, provide the Engineer recommendations for chip seal repairs, subject to approval. Repair or replace chip seal according to the following:

· One of the following, as approved by the Engineer:

· Install additional chip seal elements including those in Section 00705,

· Remove the failed chip seal and install a new chip seal according to this Section and Section 00705, or

· Remove the failed chip seal and install a new alternate chip seal acceptable to the Engineer.

· Submit a detailed repair plan for approval within 7 Calendar Days of the Agency's written notification of failure. The Engineer will respond within 7 Calendar Days of receiving the plan.

· Provide the remedy to the entire Segment that contains the failure unless otherwise approved in writing by the Engineer.

· Provide the remedy within 21 Calendar Days of the Agency's written notification of failure unless otherwise approved in writing by the Engineer.

· Use materials and procedures meeting the Specifications or approved in writing by the Engineer

· Coordinate timing of repair Work with the Engineer.

All repairs to the chip seal including but not limited to all Work in this Section, Section 00705, and all other Sections shall be at no additional cost to the Agency.

All repairs to the chip seal must be completed and accepted before the warranty period may begin.

00710.75 Contractor Warranty - The Contractor unconditionally warrants to the Agency the chip seal and installation under this Section and under Section 00705 against failure, according to this subsection and 00170.85(b)(1).

"Unconditionally warrant" means that the warranty covers all failures, regardless of the source or cause of the failure, including, without limitation, whether the source or cause is or may be related to workmanship, inspection, or choice of materials.

The Agency inspection of any portion of the Work during the Contract and during the installation, the Agency acceptance of the Work, corrections under the warranty, or expiration of the warranty shall not relieve the obligations under this warranty.

(a) Warranty Period - The warranty period shall be for 1 year.

(b) Failure - For purposes of the warranty, failure is defined as one or more of the following:

· Loss of Cover Aggregate

· The Degree of Loss of Cover Aggregate is greater than 6 as determined by ODOT Provisional TM 781.

· Flushing

· The average texture depth is less than 0.9 mm (.035 in.) as determined by ODOT Provisional TM 780.

· Visual Inspection

· Chip seal failure determined by visual inspection by the Engineer.

The Engineer will not determine that a failure exists if the failure is limited to an area that is less than 50 continuous feet long in a travel lane or for areas that total up to less than 100 feet long in a travel lane within a Segment. Each travel lane will be independently evaluated.

The Engineer may not determine that a failure exists if the failure, in the Engineer’s opinion, is caused by winter maintenance activities performed by the Agency.

(c) Remedy - Upon notification by the Engineer of a failure as defined above, provide the following remedy:

· One of the following, as approved by the Engineer:

· Install additional chip seal elements including those in Section 00705,

· Remove the failed chip seal and install a new chip seal according to this Section and Section 00705, or

· Remove the failed chip seal and install a new alternate chip seal acceptable to the Engineer.

· Submit a detailed repair plan for approval within 7 Calendar Days of the Agency's written notification of failure. The Engineer will respond within 7 Calendar Days of receiving the plan.

· Provide the remedy to the entire Segment that contains the failure(s) unless otherwise approved in writing by the Engineer.

· Provide the remedy within 21 Calendar Days of the Agency's written notification of failure unless otherwise approved in writing by the Engineer.

· Use materials and procedures meeting the Specifications or approved in writing by the Engineer

· Coordinate timing of repair Work with the Engineer.

All repairs to the chip seal including but not limited to all Work in this Section, Section 00705, and all other Sections shall be at no additional cost to the Agency.

(d) Agency's Right to Make Repairs - If, in the opinion of the Engineer, a failure causes or may cause a hazard, the failure may be temporarily corrected by Agency or other forces at no additional cost to the Agency. Replace temporary repairs with permanent repairs at no additional cost to the Agency and according to the Specifications and within the time specified in 00710.75(c).

During the warranty period and prior to the end of the warranty period the Engineer will perform inspections to determine if any failures exist. The Contractor will be notified in advance of the inspections and will be permitted to accompany the Agency Inspector.

Measurement

00710.80 Measurement - The quantities of Placement of Emulsified Asphalt Chip seal will be measured on the area basis.

The quantities of Emulsified Asphalt will be measured on the weight basis.

Payment

00710.90 Payment - The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a) Placement of Emulsified Asphalt Chip seal……Square Yard
(b) Asphalt in Emulsified Asphalt Chip seal…..Ton

The Agency will pay the Contract unit price only once for the specified quantity.

Payment is for furnishing and placing all Materials, and for furnishing all Equipment, labor, and incidentals necessary to complete the Work as specified.

No separate or additional payment will be made for preparing, maintaining, and repairing the road surface.

Payment for Work performed under this Section will be limited to 75 percent of the amount due until the warranty period has started.

00710.95 Price Adjustments – The Work in this Section and in Section 00705 is subject to a price adjustment for the calculated expected life of the Asphalt Chip seal. A price adjustment will be determined at a minimum of 5 random locations in each travel lane. The individual price adjustments will be averaged together to determine a composite pay factor. The composite pay factor will then be used to determine the price adjustment for the pay items in this Section. If a sublot or partial sublot fails and the remedy is to install an alternate chip seal such as ACP that sublot or partial sublot will not be evaluated or included in the price adjustment. The Engineer may determine that a sublot or partial sublot should be excluded from the evaluation if in the Engineer’s opinion the expected life was reduced in the sublot or partial sublot as a result of winter maintenance activities performed by the Agency.

Prior to the end of the warranty period the Engineer will evaluate each travel lane according to ODOT Provisional Test Method 780. For each sublot the average texture depth will be used to calculate the expected life for the sublot according to Appendix “A” - TM780 Life Expectancy Calculations.

If the calculated expected life (Yf) is greater than or equal to the design life (Yd) then a pay adjustment factor of 1.05 (5% increase) will apply to the pay items in this Section.

If the calculated expected life (Yf) is less than the design life (Yd) then a pay adjustment factor of 0.95 (5% decrease) will apply to the pay items in this Section.

For US20 (Highway 007) the following factors will be used in the calculations:

AADT = 2300

HCV = 20.2%

Nothing in this Subsection limits the ability of the Engineer to take additional action including but not limited to action described in Subsection 00150.25.

SECTION 00850 - COMMON PROVISIONS FOR PAVEMENT MARKINGS

Comply with Section 00850 of the Standard Specifications.

SECTION 00866 - LONGITUDINAL PAVEMENT MARKINGS - HIGH PERFORMANCE

Comply with Section 00866 of the Standard Specifications.

SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND BARS

Comply with Section 00867 of the Standard Specifications.

SECTION 00940 - SIGNS

Comply with Section 00940 of the Standard Specifications.

Rev 1/4/2019