This document is an example of a Cost Proposal RFP (Request for Proposals) Attachment E - Proposed Fully Burdened Billing Rates for a state or local government contract opportunity. The RFP requires proposers to provide the proposed fully burdened hourly rates for their key staff, as well as any subcontractor key staff, along with a breakdown of their job duties and the percentage of the typical project budget those duties would comprise. Proposers must ensure the total percentage of the project budget across all staff equals 100%.
The RFP also includes a sample cost proposal sheet for instructional purposes, which shows example key staff titles, proposed billing rates, and weighted rates. Key details around the specific RFP number, title, and proposal submission requirements are included in the file.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00010942 Att B.doc | DOC document | |
| 00010942 Att G.docx | DOCX document | |
| 00010942 Matrix for release.xlsx | XLSX spreadsheet | |
| 245052 RFP.pdf | ||
| 00010942 Att C.doc | DOC document | |
| 00010942 Q&A.docx | DOCX document | |
| 00010942 Matrix for release final~1.xlsx | XLSX spreadsheet | |
| 00010942 Att F.doc | DOC document | |
| 00010942 RFP Final.doc | DOC document | |
| 00010942 Q&A~1.docx | DOCX document | |
| 00010942 Intent to Award~1.docx | DOCX document | |
| 00010942 Att A Sample Contract Final.doc | DOC document | |
| 00010942 A1.docx | DOCX document | |
| 00010942 Notice of Competetive Range.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cost Proposal
| RFP Number: | ________ | RFP Title: | _________________________________ | |||
| RFP Attachment E - Proposed Fully Burdened Billing Rates | ||||||
| Name of Proposing Firm: | ||||||
| Name of Proposer's Key Staff | Job Classification (Individual) | Proposed Fully Burdended Hour Rate | Job Duties | % of Typical Project Budget (Total % Must Equal 100) | Weighted Rate (for purposes of evaluation scoring only) | |
| 1 | $ - 0 | |||||
| 2 | $ - 0 | |||||
| 3 | $ - 0 | |||||
| 4 | $ - 0 | |||||
| 5 | $ - 0 | |||||
| 6 | $ - 0 | |||||
| 7 | $ - 0 | |||||
| 8 | $ - 0 | |||||
| Total Hourly Rate All Classifications | ||||||
| Name of Subcontractor Key Staff | ||||||
| Name of Key Staff | Job Classification (Individual) | Proposed Fully Burdended Hour Rate | Job Duties | % of Typical Project Budget (Total % Must Equal 100) | Weighted Rate | |
| 1 | $ - 0 | |||||
| 2 | $ - 0 | |||||
| 3 | $ - 0 | |||||
| 4 | $ - 0 | |||||
| 5 | $ - 0 | |||||
| 6 | $ - 0 | |||||
| 7 | $ - 0 | |||||
| 8 | $ - 0 | |||||
| Total: | 0% | |||||
| Total Weighted Rate (for scoring purposes only): | $ - 0 |
SAMPLE ONLY
| THIS SHEET IS FOR INSTRUCTIONAL PURPOSES ONLY. PROPOSERS SHALL USE TAB MARKED "COST PROPOSAL" TO SUBMIT THEIR PROPOSALS. | |||||||
| RFP Number:___________ RFP Title: _________________________ | |||||||
| RFP Attachment E - Proposed Fully Burdened Billing Rates | |||||||
| Name of Proposing Firm: | |||||||
| Total Key Staff | Name of Proposer's Key Staff | Job Classification (Individual) | Proposed Fully Burdended Hour Rate | Job Duties | % of Typical Project Budget (Total % Must Equal 100) | Weighted Rate (for purposes of evaluation scoring only) | |
| 1 | Tech Specialist 3 | $ 120.00 | Project Manager | 10% | $ 12.00 | ||
| 2 | Programmer 2 | $ 100.00 | Lead Programmer | 80% | $ 80.00 | ||
| 3 | $ - 0 | ||||||
| 4 | $ - 0 | ||||||
| 5 | $ - 0 | ||||||
| 6 | $ - 0 | ||||||
| 7 | $ - 0 | ||||||
| 8 | $ - 0 | ||||||
| Name of Subcontractor Key Staff | |||||||
| 1 | Facilitator | $ 115.00 | Facilitate public involvement meetings | 10% | $ 11.50 | ||
| 2 | $ - 0 | ||||||
| 3 | $ - 0 | ||||||
| 4 | $ - 0 | ||||||
| 5 | $ - 0 | ||||||
| 6 | $ - 0 | ||||||
| 7 | $ - 0 | ||||||
| 8 | $ - 0 | ||||||
| Total: | 100% |
Kim Rice:
Percent for prime and subcontractors combined must equal 100%.
Total Weighted Rate (for scoring purposes only): $ 103.50
Instructions for Proposer:
Enter text and data in yellow highlighted fields. Cells with formulas are protected from editing. See additional comments inserted below.
File details come from the government source that posted it. Updated .