This document is a special provisions section of the Tinker Air Force Base General Requirements specification that establishes mandatory procedures and safety protocols for contractors performing work on or near the active airfield.

Contractors must submit written runway and taxiway closure requests to the Contracting Officer at least 45 calendar days in advance, including the specific location, requested date, estimated duration, detailed work description, required equipment list, and personnel estimate. Base Operations coordinates the actual closure schedule, and contractors bear responsibility for having all personnel, materials, and equipment ready on the approved date; Base Operations cannot accommodate closure extensions under normal circumstances. Safety requirements mandate that contractors provide all personnel with ear plugs and/or ear muffs to protect against high-level noise from jet aircraft, in addition to all OSHA-required safety equipment. Contractors must maintain clean work sites free of Foreign Object Debris (FOD) to prevent aircraft damage and must obtain control tower clearance before crossing active runways or taxiways. Vehicles operating on landing areas within 1,000 feet of runway ends must display approved low-intensity amber flashing lights, and repeated crossings require use of Government-furnished two-way radios restricted to control tower communication. Temporary structures exceeding 12 feet above ground within 1,000 feet of a runway or 50 feet elsewhere require written Government approval submitted at least 21 calendar days prior to use. Contractors must remove all materials and equipment daily and are prohibited from stockpiling materials or storing equipment within 1,000 feet of runway centerlines. Emergency evacuation procedures require contractors to identify a safe evacuation area on the first workday and immediately vacate the work site and move all personnel and equipment to that designated area upon emergency orders. Contractors must maintain on-site equipment capable of cleaning loose materials from runways, taxiways, ramps, and aprons, and must complete full-length runway and taxiway inspections accompanied by Government representatives to ensure complete removal of personnel, debris, materials, equipment, and tools.

View the file

Other files

File Type Posted
240176_ROUND 3_PRE BID RFIs_For Signature 2 - COR Signed.pdf PDF
240176_Site Visit Sign In.pdf PDF
SOW Att 02a_Controlled Area Training.pptx PPTX presentation
240176_ATT 11_Submittal Register.pdf PDF
240176_Final_ Plan Set.pdf PDF
WWYK143004_CU502.pdf PDF
WWYK143004_CU513.pdf PDF
WWYK143004_CU501.pdf PDF
WWYK143004_CU505.pdf PDF
20090026A.pdf PDF
B02119.txt TXT text file
690255.pdf PDF
480211.pdf PDF
Combined As-Built Record Dwgs.pdf PDF
FIRE SUPPRESSION GEODESIC SHOP DRAWINGS AS-BUILTS.pdf PDF
2025 TAFB Mechanical Standard_Signed.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
01 32 16.00 20.pdf PDF
tinkerafb_INRMP.pdf PDF
afman32-7003.pdf PDF
afman48-148.pdf PDF
dafi13-213_tinkerafbsup.pdf PDF
017800_Attch1_DD1354.pdf PDF
007200_Attch14_Information for New Boilers.pdf PDF
017800_Attch2_DD1354 Checklist.docx DOCX document
007200_Attch9_EMS Awareness Training.pdf PDF
Solicitation - FA813726R0043.pdf PDF
240176_ATT09_SOW.pdf PDF
240176_STATEMENT OF WORK-Amendment 1.pdf PDF
240176_ATT 11_Submittal Register.xlsx XLSX spreadsheet
240176_ATT 10_Design Narrative.pdf PDF
Industrial Waste Lines 1969.pdf PDF
WWYK143004_CU507.pdf PDF
WWYK143004_CU503.pdf PDF
WWYK143004_CU500.pdf PDF
WWYK143004_CU504.pdf PDF
Pages from 910139.pdf PDF
20010298.pdf PDF
710237.pdf PDF
430515.pdf PDF
2025 TAFB Electrical Standards - Signed.pdf PDF
01 78 00.pdf PDF
UMRL.pdf PDF
ERDCITL_TR12-6_r6.pdf PDF
ufc_3_260_01_2019_c1.pdf PDF
EM_385-1-1.pdf PDF
tinkerafb_INRMP_App G.pdf PDF
dafi21-101.pdf PDF
dafi13-213.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 05

SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD ON TINKER AFB

PART 1 GENERAL

The following provisions shall apply when work is required to take place on the active airfield, within the clear zones, or in the primary surfaces as defined by Unified Facilities Criteria 3- 260-1, Airfield and Heliport Planning and Design.

1.1 CLOSURES

a. All runway and taxiway closures require coordination and scheduling with Base Operations. Written requests for closures shall be submitted to the Contracting Officer no less than 45 calendar days prior to the requested date of closure. The request shall include:

1. The nomenclature of the runway/taxiway to be closed

2. The area of the runway/taxiway where the work is to take place

3. The requested date of closure

4. The estimated duration of closure

5. A detailed description of the work to be performed

6. A list of the equipment required to perform the work

7. An estimate of the personnel required to perform the work

b. The Contracting Officer shall coordinate with Base Ops to close the requested runway/taxiway on or as close as possible to the date requested and for the length of time requested. The Contracting Officer shall notify the contractor, in writing, of the date and length of time approved for closure.

c. It is the responsibility of the contractor to have the necessary personnel, materials, and equipment ready to start work on the approved date of closure and to complete the work in the time requested. Under most circumstances, Base Operations will be unable to adjust flight and runway/taxiway utilization schedules to accommodate extensions to closures.

d. The contractor shall notify the Contracting Officer, in writing, when the work on the closed runway/taxiway is complete.

1.2 SAFETY

1.2.1 Personnel

The contractor shall provide all of his personnel ear plugs and/or ear muffs to prevent injury to their auditory systems while working on the Airfield. Jet aircraft operating on the runways, taxiways, and aprons make these areas zones of high-level noise. The government will not be held liable for auditory system damage due to non or improper use of noise protection equipment.

This requirement is in addition to the contractor providing his personnel with safety equipment required by OSHA for the work to be performed.

January 2022 Page 1 Section 00 80 05

1.2.2 Aircraft

The contractor shall maintain a clean work site and shall implement all measures necessary to insure that material and equipment do not interfere with or damage aircraft operating or parked in areas of the airfield that are not closed. NO FOD.

1.3 ACCESS RESTRICTIONS

No unescorted contractor vehicles, equipment, or personnel shall be on or cross any active runway or taxiway unless clearance is requested from, and granted by, the control tower. All contractor vehicles and mechanized equipment operating on the landing areas (the first 1,000 feet from either end of the runway) will be identified by approved, mounted, low intensity, amber flashing lights. When contractor operations require repeated vehicle or personnel crossing of an active runway, taxiway, or other controlled area, a two-way radio, furnished by the Government, will be used to maintain contact with the control tower. Use of the radio for other purposes will be strictly prohibited. The radio will be returned to the Government at the end of each workday, and will be reacquired as necessary.

1.4 HEIGHT RESTRICTIONS

The construction of any temporary structure or the use of any equipment that extends more than 12 feet above the ground within 1000 feet of a runway or that extends 50 feet above the ground elsewhere on Tinker AFB shall be approved by the Government prior to installation or use. Written request for approval shall be submitted to the Contracting Officer no later than 21 calendar days prior to the date needed.

1.5 CLEANLINESS

The contractor shall maintain the cleanliness of his work site and all traversed runways, taxiways, aprons, and ramps at all times. He shall utilize methods and equipment to prevent spilling or dropping materials in these areas and shall utilize whatever method or equipment necessary to insure the removal of loose materials from these areas. The contractor shall remove all material and equipment to his staging area at the end of each work day. No material is to be stockpiled nor equipment stored within 1000 feet of the centerline of a runway.

1.6 EMERGENCIES

1.6.1 Evacuation Area

On the first day of work on the airfield, the contractor, a representative of the Contracting Officer, and a representative of Base Ops shall identify an area a safe distance from the runway where the contractor is to move his personnel and equipment during an aircraft emergency.

1.6.2 Evacuation

During an aircraft emergency, the contractor shall vacate the work site.

He shall move all personnel and equipment to the designated evacuation area. Evacuation orders will be given on short notice and will require expeditious action by the contractor.

January 2022 Page 2 Section 00 80 05

1.7 INSPECTION AND CLEANING

The contractor shall maintain, on site and in good working order, equipment capable of cleaning loose materials from the runway, taxiway, ramp, or apron. The contractor, accompanied by a Government representative, may be required to inspect the entire length of the runway and taxiway to insure that all personnel, debris, material, equipment, and tools have been removed from these areas.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --