- Tinker AFB MAC BOA - WWYK240176 - Replace Industrial Waste Lift Stations 6N & 6S, B62501
- Solicitation number
- FA813726R0043
About this file
This Statement of Work (SOW) outlines the design-build replacement of industrial waste lift stations 6N and 6S at Tinker Air Force Base (TAFB), Oklahoma for project WWYK240176, work task 15311657. The contractor shall furnish all design/engineering services, materials, labor, equipment, testing services, quality control, and associated work to deliver two fully operational and functioning lift station systems. The contractor must perform site investigation to verify existing conditions and is responsible for identifying all necessary logistical, architectural, and structural work elements. Government-provided information regarding floor plans, dimensions, structural/mechanical/electrical data, and utility locations is approximate and must be field verified by the contractor.
The contractor must provide key personnel including a Project Manager (minimum 10 years combined experience), Design Project Manager (Oklahoma-licensed Registered Architect or Professional Engineer with 10 years' experience, including 5 years managing design-build projects), Quality Control Manager, Site Safety and Health Officer, and Project Superintendent (minimum 5 years construction experience, 2 as superintendent). All personnel require current/valid licenses and certifications. Construction shall occur during normal duty hours (0700–1600 Monday-Friday) with utility outages as exception. Work is sequenced to maintain lift station operation throughout: reroute gravity drains to 6N, demolish 6S, construct new lift stations and meter vault, then demolish 6N. Design submittals are required at 35%, 65%, 95%, and 100% completion, with all designs to comply with UFC standards, NFPA codes, Tinker AFB facility standards, and other applicable regulations. Material submittals for major components must accompany the 95% design. The contractor shall submit baseline schedule within 10 days of Notice to Proceed, maintain monthly schedule updates with cost loading totaling 100% of contract value, and provide weekly progress reports. Final 10% of contract value is reserved pending completion of all closeout items, punch list resolution, and final inspection. O&M manuals and training shall be provided minimum 30 days prior to final inspection, and DD Form 1354 (Transfer and Acceptance of Military Real Property) must be submitted 14 days prior to final inspection.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work - 1 of 27 MACB Design-Build SOW_v3_Mar 24
STATEMENT OF WORK
Replace Industrial Waste Lifts 6N & 6S, B62501
Project #: WWYK240176 Work Task #: 15311657
Revision: 0 Issued: 28 January 2026
1. SCOPE
1.1 GENERAL
The work to be performed under the terms of this Order consists of furnishing all design/engineering services, materials, labor, plant, tools, transportation, equipment, testing services, quality control and incidentals required to accomplish the replacement of the industrial waste lift stations 6N and 6S at Tinker Air Force Base (AFB), Oklahoma (reference the project drawings for additional location information).
The Contractor shall perform a site investigation to verify existing conditions. If necessary, additional as-built drawings are available from 72 ABW/CE - Engineering Support, located in B400.
The Contractor shall be responsible for identifying the necessary logistical, architectural, and structural work elements required to perform the work as described herein. Assemblies, framework, fixtures, or apparatus not readily identified on the project drawings or this Statement of Work (SOW) shall be provided by the Contractor as required for a complete, fully operating, and functioning system or systems ready for use by the Government.
Information such as floor plan layouts and dimensions; structural, mechanical, and electrical data;
and location of underground utilities provided by the Government for existing and new construction are based on available as-built documentation, field observation, and equipment selected as design basis by the Government. This information is to be considered approximate and shall be field verified by the Contractor.
1.2 DEFINITIONS
1.2.1 Contracting Officer (CO)
An individual with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the contracting officer acting within the limits of their authority as delegated by the CO.
The CO is the ONLY person authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.
1.2.2 Contracting Officer’s Representative (COR)
An individual designated by the Contracting Officer to perform specific technical or administrative functions.
The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the Order. It shall be the Contractor’s responsibility to contact the CO concerning any matters where the Contractor believes that the direction received from the COR may affect price, quality, quantity, delivery, or any other term or condition of the Order prior to performing work or purchase of material.
25 Sep 25 Statement of Work - 2 of 27 WWYK240176
1.3 CONTRACTOR PERSONNEL
1.3.1 General Requirements
The Contractor shall ensure that employees and subcontractor employees have current/valid licenses and certifications necessary to perform their functions. Any cost or time associated with obtaining licenses or certifications shall be at the Contractor’s expense.
Personnel shall be easily recognized as a Contractor employee or subcontractor. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain the company name and employee name. The badge shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times. The badge shall clearly identify the individual as a Contractor employee.
1.3.2 Key Personnel
The Contractor shall, at a minimum, provide the following key personnel. Submit resumes for personnel fulfilling each of the key positions described below within five (5) calendar days after
NTP.
Exceptions or variances to experience requirements must have prior approval from the Contracting Officer (CO)/Contracting Officer's Representative (COR); exceptions/variances will be considered where the Contractor can demonstrate comparable experience and/or competency.
Forward any requests for variance to the CO; include resumes for personnel listing the qualifications to be considered (e.g. education, experience, professional certifications, etc.).
Required experience levels shall be maintained throughout the duration of the agreement. When personnel changes are required, resumes and a revised organization chart shall be submitted to the CO within five (5) business days of a vacated or filled position.
One Contractor employee may hold up to two (2) key positions; exceptions are noted below (e.g.
a Project Superintendent cannot fulfill the role of the Quality Control Manager). Contractor employees holding more than one key position must meet the minimum requirements for both positions.
1.3.2.1 Project Manager (PM)
The PM will be responsible for the overall performance of this Order. The PM shall have a minimum of ten (10) years combined experience in the following positions: Project Superintendent, Quality Control Manager, Project Manager, Project Engineer, or Construction Manager with general contracting firm(s) engaged in multi-trade commercial construction contracts. The individual must have at least two (2) years' experience as a Project/Program Manager. Provide the name of PM, in writing, to the CO upon award of the Order.
The Contractor shall designate an Alternate PM who may act on behalf of the Contractor when the PM is absent. Qualifications for the Alternate are the same as for the PM. Provide the name of the Alternate, in writing, to the CO upon award of the Order.
The PM or Alternate shall have direct oversight of project planning, design, and construction activities. The PM shall provide overall Order management, including full authority to develop proposals, negotiate, and sign modifications to Orders; provide
25 Sep 25 Statement of Work - 3 of 27 WWYK240176 subcontract administration; review material submittals and shop drawings; and shall attend all status meetings, site visits, and pre-final/final inspections.
The CO must be able to contact the PM or Alternate by phone at all times. Throughout the life of this agreement, the PM or Alternate shall be available to meet with the CO at Tinker AFB within one (1) hour of telephone notification during normal duty hours.
The PM or the alternate may fulfill the role of the Design Project Manager.
1.3.2.2 Design Project Manager
The Design Project Manager will be responsible for the overall performance of the pre-construction/design portions of this contract. The Design Project Manager shall be licensed in the State of Oklahoma as a Registered Architect or Professional Engineer;
Design Project Manager shall have a minimum of ten (10) years’ previous experience in project management, with at least five (5) of those years managing design-build projects similar in size and complexity. The name of the Design Project Manager shall be designated in writing to the CO upon award of the Order.
The Design Project Manager shall provide direct oversite and overall management of the design process, including coordinating day to day production; schedule adherence;
quality control of all design submittals; verification that designs meet applicable codes and standards (including Air Force/DoD standards); review of material submittals and shop drawings; and answering construction RFIs related the design. The Design Program Manager shall attend all design status meetings, initial pre-design meetings, site visits, and design review conferences.
The Design Project Manager may fulfill the role of the Project Manager or alternate.
1.3.2.3 Quality Control Manager (QCM)
The QCM is responsible for management of the Contractor Quality Control (CQC) Program. The QCM shall have the minimum qualifications set forth in specification section 01 45 00.00 10, Quality Control (for purposes of this SOW, QCM is equivalent to CQC System Manager).
The Contractor shall designate an Alternate QCM who may act on behalf of the Contractor when the QCM is absent. Qualifications for the Alternate(s) are the same as for the QCM.
Contractor may designate additional quality control (QC) staff as specified in 01 45 00.00 10 (e.g. Assistant QC Manager or QC specialists).
Provide the names of QC staff to the CO upon award of the Order as a part of the Quality Control Plan.
The QCM and their staff shall coordinate and review all material and shop drawing submittals, including those of subcontractors, offsite fabricators, and suppliers; prepare quality control (QC) reports; schedule and coordinate testing procedures; and attend all status meetings, site visits, and pre-final/final inspections.
The Contractor's QC staff shall maintain a presence at the site at all times when work is being performed to ensure that the materials and workmanship are in accordance with the project drawings and technical specifications, as well as approved shop drawings and material submittals. The QCM or Alternate shall visit the project site daily.
25 Sep 25 Statement of Work - 4 of 27 WWYK240176
For additional information regarding the requirements for Contractor’s Quality Control Program, refer to specification section 01 45 00.00 10.
The QCM may serve as the Site Safety and Health Officer.
1.3.2.4 Site Safety and Health Officer (SSHO)
The SSHO is responsible for management of the Contractor Health and Safety Program (for purposes of this SOW, the Health and Safety Program is equivalent to Safety and Occupational Health Program in EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual). The SSHO shall have the minimum qualifications set forth in EM 385-1-1.
The Contractor shall designate an Alternate SSHO who may act on behalf of the Contractor when the SSHO is absent. Qualifications for the Alternate(s) are the same as for the SSHO.
Provide the names of the SSHO and Alternate to the CO upon award of the Order as a part of the Health and Safety Plan.
The SSHO or Alternate shall visit the construction site daily to ensure full compliance with all health and safety requirements.
When the SSHO or Alternate is not on site, a Designated Representative (DR) may be used (reference EM 385-1-1). The SSHO, an Alternate, or a DR shall be on the construction site at all times when work is being performed.
1.3.2.5 Project Superintendent
The Superintendent must have a minimum of five (5) years’ experience in construction with at least two (2) of those years as a superintendent on commercial projects similar in size and complexity to the requirements of this Order. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.
The Contractor shall designate an Alternate Superintendent who may act on behalf of the Contractor when the Superintendent is absent. Qualifications for the Alternate are the same as for the Superintendent, except previous experience as a superintendent is not required; subcontractors will not be used as Alternates.
Provide the names of the Superintendent and the Alternate to the CO upon award of the Order.
The Superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence for the Order. Superintendents shall provide on-site supervision; submit progress reports; schedule and coordinate subcontractors and material suppliers; and attend all status meetings, site visits and pre-final/final inspections.
An individual Superintendent may be assigned to more than one Order; however, the Superintendent shall not be assigned to more than 5 active Orders at Tinker AFB unless approved by the CO. Alternates may only be assigned to a single Order/job site.
The Superintendent shall visit the Order/job site daily. Either the Superintendent or the Alternate shall be at the job site at all times when work is being performed. The
25 Sep 25 Statement of Work - 5 of 27 WWYK240176
Superintendent must arrive at the job site within 30 minutes of telephone direction from the CO, Contract Specialist, or Construction Quality Assurance (QA) Inspector.
The Superintendent or Alternate(s) cannot be a member of the QC staff.
The Superintendent or Alternate(s) can be the Designated Representative (reference section SITE SAFETY AND HEALTH OFFICER elsewhere in this document).
1.3.3 Subcontractors
Subcontractor firms performing design shall be authorized to offer engineering or architectural services in a US State or Territory. An Oklahoma license will not be required for individuals responsible for signing/sealing documents.
All subcontractor firms shall be licensed in their specialty where required; Contractor will provide a copy of these licenses as part of the QC Plan.
1.4 BADGES
AFMC Form 387, Air Force Material Command Identification Cards (i.e. contractor badges) are required for Contractor personnel to access/work on Tinker AFB. The Contractor must have all personnel badged prior to commencing work.
Contractor shall designate an employee to act as Certifying Official for all personnel requiring badges. The designated Certifying Official shall complete the Appointment of Security Representative letter and submit to the COR upon award of the Order; a copy of this letter (Attachment 1) is included on the attached CD.
Upon approval, Contractor’s Certifying Official will be responsible for completing AFMC Form 496, Application for AFMC Identification Card, for all personnel requiring a contractor badge. Badges are issued at Bldg. 6611, Pass and ID.
Badges shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times.
1.5 QUALITY CONTROL
It is the Contractor’s responsibility to provide, inspect, and document the level of quality that has been established by the minimum standards of the project drawings, specifications, and this SOW.
The QCM shall direct the execution of the Contractor’s QC Plan.
Quality control shall be executed in accordance with specification section 01 45 00.00 10. The QC program shall include, but is not limited to the following:
1.5.1 Inspection System
The Contractor shall establish an inspection system which monitors the execution of any task completed under this Order. The Contractor must specify the areas to be inspected on a scheduled or unscheduled basis, how often inspections will be accomplished, and titles of the individuals who will perform the inspections.
1.5.2 Deficiency Prevention
The Contractor shall establish a method for identifying, correcting, and preventing future recurrence of quality deficiencies.
25 Sep 25 Statement of Work - 6 of 27 WWYK240176
1.5.3 Inspection Files
In accordance with specification section 01 45 00.00 10, the Contractor shall maintain records of all required inspections conducted by the QCM and the necessary corrective actions taken. This documentation shall be submitted to the Government weekly with the progress reports (reference section PROGRESS REPORTS elsewhere in this document) throughout the life of the Order.
1.6 HEALTH AND SAFETY
1.6.1 Commander’s Statement of Safety Intent
The safety of everyone on Tinker AFB is our top priority. All individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment.
Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precautions to prevent accidents and preserve the health/safety of each contractor and government employee.
1.6.2 Occupational Safety and Health Administration (OSHA) Voluntary Protection Program (VPP)
The Contractor is hereby notified that TAFB has achieved or is pursuing VPP Star ratings across multiple sites. Additional information regarding VPP can be found at the following link:
http://www.osha.gov/dcsp/vpp/index.html
The Voluntary Protection Plan applies to all construction and service contracts that have Contractor employees working more than 1000 hours per quarter on Tinker AFB. Refer to specification section 00 71 00, General Safety Requirements for Construction on Tinker AFB for additional requirements related to VPP.
1.6.3 Emergency Evacuation Procedures
Contractor employees shall follow the direction of Government employees in regard to emergency evacuation procedures, i.e. fire, tornado, or bomb threats. It is the responsibility of the Contractor to provide guidance and establish procedures for responding to an emergency for their employees. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.
1.6.4 Mishap Reporting
The Contractor shall notify the CO and the COR as soon as practical after any mishaps, including recordable accidents, incidents, and near misses as defined in EM 385-1-1 Appendix Q; and any injuries, illness, or property damage which occur on the installation while performing work under this Order.
Refer to specification section 00 71 00 for additional requirements related to mishap reporting.
1.7 BIOENVIRONMENTAL REGULATIONS
(1) To assist in the evaluation of health hazards & to provide emergency medical treatment, Contractor must have Material Data Sheets (MDS) for hazardous materials reviewed and exchange of HAZCOM information accomplished prior to use. Process hazardous material in accordance with specification section 00 72 00, Environmental Requirements for Construction on Tinker AFB.
http://www.osha.gov/dcsp/vpp/index.html
25 Sep 25 Statement of Work - 7 of 27 WWYK240176
(2) Ventilation measurements must be in accordance with current edition of ACGIH Ventilation Manual and 29 CFR 1910.94.
(3) Welding, cutting, or brazing operations must be in accordance with 29 CFR 1910.252. The Contractor shall not operate welders near chlorinated hydrocarbons.
(4) Hazardous noise levels in the vicinity of DoD Active Duty and Civilian personnel must be in accordance with OSHA 29 CFR 1910.95 and AFI 48-127, Occupational Noise and Hearing Conservation Program.
(5) Where confined spaces may be involved, ensure confined space entry permits are acquired prior to entering a confined space. Personal Protective Equipment (PPE) must be in accordance with 29 CFR 1910.146 and AFOSH Std 91-25.
1.8 OUTAGES AND CLOSURES
Request utility outages and/or closures in accordance with TAFB Standard Operating Procedure Planned and Emergency Outages. Outages may be required to be performed outside of normal duty hours. The Contractor shall provide temporary lighting and power that may be required for continued performance of User's mission during outages.
1.9 EXISTING WORK
In accordance with FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, the Contractor shall take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government; any damaged items shall be repaired or replaced as directed by the CO.
The Contractor shall remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
The Contractor shall repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the CO. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
2. PROJECT SPECIFIC REQUIREMENTS
2.1 GOVERNMENT OCCUPANCY OF FACILITIES
The construction area, a reasonable buffer area, and any approved staging areas will be cleared of all Government materials and personnel prior to the start of construction.
Contractor shall consult with the Government Project Manager/Construction QA Inspector and the Using Agency to coordinate procedures; means of access; space for storage of materials and equipment; and use of approaches, corridors, and stairways in such a way that accommodates the continued performance of the User’s mission during construction.
2.2 WORKING HOURS
In accordance with specification section 00 70 00, General Requirements for Construction on Tinker Air Force Base, construction shall take place during normal duty hours (0700 – 1600 Monday-Friday); utility outages will be the exception.
The Contractor has the responsibility to manage and maintain the construction schedule; the Contractor may request authorization to work weekends, holidays, and additional shifts as
25 Sep 25 Statement of Work - 8 of 27 WWYK240176 required to accomplish the work per their baseline schedule (reference section CONSTRUCTION SCHEDULE elsewhere in this document).
Work outside normal duty hours to meet schedule will be performed at no additional cost to the Government; this is to include all testing, inspection, and acceptance actions.
2.3 SEQUENCING
There is a Government-required sequence for this order. Operation of a lift station is required throughout the construction period.
Construction will be sequenced as follows:
(1) Existing gravity drain(s) to IWLS 6S to be rerouted to IWLS 6N.
(2) Demolish IWLS 6S.
(3) Construct new IWLS, IWVV and meter vault as indicated.
(4) Demolish IWLS 6N
Sequencing discussed above shall be reflected in the Contractor's construction schedule.
2.4 FOD AWARENESS AND PREVENTION TRAINING
In accordance with specification section 00 71 00 all Contractor personnel working on this Order will be required to complete Foreign Object Debris (FOD) awareness and prevention training.
The work to be performed for this Order will not require the Contractor to work in or travel through areas near operational and/or production aircraft or related components.
The work to be performed requires that special attention be given to tools when working in and around the flight line. The Contractor shall utilize a means of tracking tools for the duration of this project. A list of tools signed by the Contractor’s Quality Control Manager shall be provided to the Construction QA Inspector prior to construction start with periodic updates submitted during construction and final list at completion. All tools shall be accounted for at the end of each day and at the completion of the project.
2.5 AIRFIELD OPERATIONS
The work to be performed under this Order is not located in an Airfield Operations area.
2.6 CONTROLLED/RESTRICTED AREA(S)
Work to be performed under this Order is not located in a controlled/restricted area.
2.7 AFFIRMATIVE PROCUREMENT
The Government has performed an initial assessment and determined that no products listed in the EPA Comprehensive Procurement Guideline, USDA Biopreferred, Energy Star, or FEMP Low Standby Power programs are anticipated to be used in this Order.
2.8 ENVIRONMENTAL MANAGEMENT (EM) SURVEY
During the demolition of the industrial waste station, it is presumed that asbestos-containing materials (ACM) and/or lead-based paint (LBP) will not be present. The contractor is required to test materials once they are exposed. If the contractor encounters any suspect environmental conditions at any time, they must immediately notify the Contracting Officer (CO) and the Contracting Officer's Representative (COR).
25 Sep 25 Statement of Work - 9 of 27 WWYK240176
The Contractor shall be responsible for the proper cleaning, sampling, testing, and abandonment of in-service IW pipes. The Contractor shall adhere to all applicable federal, state, and local regulations regarding wastewater discharge and disposal. The Contractor shall provide all labor, materials, and equipment necessary to complete the abandonment process in a safe and environmentally sound manner. The Contractor shall submit a detailed abandonment plan to the COR for approval prior to commencing any work. This process shall include, at a minimum:
complete isolation of the pipe segment, removal of all residual solids and liquids by a licensed waste hauler, verification that no free liquids remain, secure capping of all ends, and completely filling the pipe void with a flowable fill or grout material as approved by the COR. All documentation, including sampling results and disposal manifests, shall be provided to the COR upon completion of the work.
The Contractor shall be responsible for the cleaning of the in-service IW pipes prior to abandonment. The Contractor shall provide all necessary labor, equipment, and materials to perform the cleaning in accordance with all applicable regulations. The Contractor shall be responsible for obtaining any necessary permits for the cleaning and disposal of rinse water. All costs associated with the cleaning, sampling, and disposal shall be included in the Contractor's proposal.
The Contractor shall be responsible for the proper characterization, transportation, and disposal of all construction and demolition debris generated during the project. The Contractor shall conduct sampling and analysis of the debris to determine if it is hazardous waste. The Contractor shall dispose of all waste in accordance with all applicable federal, state, and local regulations. The Contractor shall provide the COR with copies of all waste characterization reports, transportation manifests, and certificates of disposal.
If evidence of soil contamination is present, the Contractor is required to conduct soil testing at the project site prior to, during, or after construction. At a minimum, testing will be required if contamination is visually observed, if required by environmental regulators, or if any soil is to be transported for off-site disposal. The Contractor shall cooperate with the 72 ABW/CEIEC Hazardous Waste Program Manager via the COR in conducting such testing. If soil contamination is discovered, the Contractor shall implement appropriate measures to contain and remediate the contamination in accordance with all applicable regulations. If soil is to be hauled off-site, the Contractor shall be responsible for characterizing the soil and disposing of it at an approved facility in accordance with all applicable regulations. The Contractor shall provide the 72 ABW/CEIEC Hazardous Waste Program Manager with copies of all soil characterization reports and disposal manifests. If at any time the Contractor encounters suspect environmental conditions not identified above, they shall notify the CO and the COR.
3. PRECONSTRUCTION & CONSTRUCTION SERVICES BY CONTRACTOR
3.1 CORRESPONDENCE
All electronic correspondence related to the awarded Order shall be addressed to the CO, Contract Specialist, Government Project Manager, Construction QA Inspector, the COR, and the respective organizational workflow accounts. Hardcopy correspondence will be addressed to the CO, the Contract Specialist, and the COR.
Contact information for the above will be provided at the Post Award meeting.
25 Sep 25 Statement of Work - 10 of 27 WWYK240176
All electronic correspondence from the Contractor regarding a specific Order shall follow a standardized subject line naming convention. Subject line for all electronic correspondence shall be as follows:
• WWYK###### Project Title: Subject of E-mail
3.2 DOCUMENTATION
All documents shall be submitted in accordance with specification section 01 33 00, Submittal Requirements. The Contractor shall submit all documents electronically via optical disk, e-mail, or a file transfer service such as DoD SAFE; except as modified by section DESIGN SUBMITTALS below.
All documents submitted by the Contractor requiring a signature shall be submitted to the CO and the COR with an electronic digital signature. All documents submitted by the Contractor requiring further action and signature by the Government shall be capable of being digitally signed and saved by the Government representative(s) as required.
3.2.1 Document Format
3.2.1.1 Specifications/Reports/Material Submittals
Specifications, design analyses, reports for calculations, material submittals, warranty information, and similar documents shall be letter sized (8-1/2” x 11”), submitted in Adobe Acrobat (.pdf) format. Black and white documents are preferred but color copies will be accepted if they are necessary to convey intent.
3.2.1.2 Drawings
All drawings produced by the Contractor shall be created utilizing Computer-Aided Design and Drafting (CADD) software. The drawing files shall be in AutoCAD (.dwg) format and adhere to the drawing standards contained in Tri-Services A/E/C CADD Standard Release 6.0.
Drawing size shall be ANSI D (22” x 34”). Drawing scale shall be at least 1"=30' for civil/site drawings and 1/8"=1' for all other plan drawings; text and other non-scale annotation elements shall be sized to produce clear and legible prints at half-size.
Contractor shall use English scales and dimensions.
Drawings submitted by the Contractor shall be .pdf format; in addition, final design drawings and as-built record drawings shall be submitted in .dwg format. Hard copy submittals, when required, shall be printed at half-size (11" x 17").
Reference specification sections 01 33 00; 01 33 16.00 10, Design Data (Design After Award); and 01 78 00, Closeout Submittals, for additional requirements regarding developing and submitting design, shop, and as-built drawings.
3.2.2 File Naming Conventions
All documents submitted by the Contractor shall follow a standardized file naming convention as indicated below. File naming conventions shall be strictly adhered to and may only be modified by the Contracting Officer and/or the COR. File names shall have no spaces.
The following items in the below naming conventions are defined as followed:
• WWYK###### = Project number as defined by Civil Engineering Example: WWYK201234
• YYYYMMDD = Effective date of document or report
25 Sep 25 Statement of Work - 11 of 27 WWYK240176
• ZZZ = Contractor’s Company Initials
• 001 = Submittal Number or Serial Report Number
(1) Proposals:
WWYK######_Proposal#_ZZZ_Document Description
Example: WWYK201234_Proposal1_ACS_Cost Proposal
(2) RFIs:
WWYK######_RFI_001
(3) Submittals:
WWYK######_FORM#_001 (Brief Description of Submittal)
Example: WWYK201234_AF3000_004 CeramicTile
(4) Daily Reports:
WWYK######_Daily Report_001_YYYYMMDD
(5) Progress Reports:
WWYK######_PR_001_YYYYMMDD
(6) Other Miscellaneous Documents/Reports:
WWYK######_Form Name, Number, Or Description_YYYYMMDD
3.3 DESIGN/CONSTRUCTION SCHEDULE
In accordance with FAR 52.236-15, Schedules for Construction Contracts, the Contractor shall submit a baseline design/construction schedule to the COR for approval within ten (10) calendar days after the NTP is issued. An approved schedule will be required prior to commencement of work.
Contractor’s schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the Order performance period. The schedule shall consider the major work elements, as well as submittal reviews, mobilization, material delivery times, anticipated weather delays, and final inspection/closeout.
3.3.1 Schedule Format
The schedule shall be developed in accordance with specification section 01 32 16.00 20, Small Project Construction Progress Schedules, utilizing the Network Analysis Schedule (NAS)/Critical Path Method format.
The schedule shall generally match the schedule submitted with the Contractor’s accepted proposal, with the following additional information included:
(1) Order start (NTP) and end dates.
(2) Additional detail/breakdown of major work elements, as necessary.
(3) Cost Loading data entered for all work items. Cost loading must total to 100 percent of the value of the Order.
Any partial progress payments for materials, as approved by the CO, shall be entered separately on the schedule.
25 Sep 25 Statement of Work - 12 of 27 WWYK240176
The schedule will reserve, as a minimum, the final 10% of an Order for final acceptance. No progress payments will be made against this final 10% of the Order until all closeout items have been submitted, all punch list items have been resolved, and final inspection/acceptance has been completed.
3.3.2 Schedule Updates
Contractor shall keep the schedule current, reflecting actual start and end dates for work elements, activity progress, and plan for completing the remaining work. The Contractor shall submit the updated schedule at monthly intervals, with the first progress report of the month.
Reference specification section 01 32 16.00 20 for additional information.
In addition, the Contractor shall submit updated baseline design/construction schedules when directed by the CO or the COR. Examples of when a new baseline schedule may be required include instances where the period of performance has been revised through modification to the Order; or as part of a ‘get well plan’ for construction that is significantly behind schedule.
3.3.3 Coordination with Government Activities
In developing the schedule, the Contractor shall account for the following milestones and Government review times in addition to construction activities:
DELIVERY SCHEDULE & SUBMITTALS
Item of Work & Deliverables Government Review Time
(calendar days) Remarks
Post-Award Conference/Pre-design Conference/Notice to Proceed (NTP) 1 day At Tinker AFB
Baseline Schedule and Schedule of Values/Draft Progress Report 14 days Provide within 10 days of
NTP
35% Design Submittal 14 days Government comments will be provided to contractor prior to AER
35% Project presentation to AERP and review conference 7 days
AERP meetings are held each Thursday at Tinker AFB or by teleconference
65% Design Submittal 14 days
65% review conference 7 days
At Tinker AFB or by teleconference; may be waived by Contracting Officer
95% Pre-final Design Submittal 14 days Submit with AF3000
95% review conference 7 days
At Tinker AFB or by teleconference; may be waived by Contracting Officer
25 Sep 25 Statement of Work - 13 of 27 WWYK240176
DELIVERY SCHEDULE & SUBMITTALS
Item of Work & Deliverables Government Review Time
(calendar days) Remarks
100% Final Submittal (Issued for Construction) 7 days
Initial submittal provided electronically; provide final documents as specified elsewhere in this SOW after approval.
Government Back Check 7 days
SD-01 Preconstruction Submittals (except as noted below) 14 days
Provide all preconstruction submittals (except design) minimum of 30-days prior to design completion/ construction NTP
Health and Safety Plan 21 days
Internal Combustion Engines Plan 21 days
Entry Access List / Vehicle Entry Access List 14 days Must be approved prior to obtaining access to controlled/secure areas
Airfield Construction Waiver 60 days Must be provided by 1st business day of month
Notice of Proposed Construction (FAA Form 7460-1) 60 days Must be provided by 1st business day of month
Request for Contractor Staging Area 30 days Must be approved prior to mobilization
Storm Water Pollution Prevention Plan (SWPPP) 21 days
Must be approved prior to submitting Tinker Excavation Permit Request
Water System Construction Permits 30 days
Chemical/Hazardous Material Request/Authorization 21 days
Spray Painting Plan 21 days
Abatement Submittals (asbestos, lead based paint) 21 days
25 Sep 25 Statement of Work - 14 of 27 WWYK240176
DELIVERY SCHEDULE & SUBMITTALS
Item of Work & Deliverables Government Review Time
(calendar days) Remarks
Material Submittals
(SD-03, SD-04, SD-07, SD-08)
14 days
Provide material submittals for major components of the work with 95% design submittal
Pre-Construction Conference/NTP: Begin Mobilization 1 day At Tinker AFB; may be waived by CO
Outages 21 days
Closures (roadway, parking aisles, etc.) 45 days
Tinker Excavation Permit Request 14 days SWPPP must be approved prior to submittal
Construction Submittals
(SD-06, SD-09)
14 days
Final/Closeout Submittals
(SD-10, SD-11)
14 days Must be approved prior to final inspection.
Pre-final Inspection 7-day Minimum Notice
Contractor must have completed internal pre-final and resolved all punch list items from this inspection
Final Inspection 7-day Minimum Notice
All final/closeout submittals must be approved.
Contractor must have resolved all punch list items from pre-final inspection
Note: Information provided in this table is provided to assist the Contractor in developing the construction schedule. Review times may vary depending on the complexity of the submittal.
3.4 PROGRESS REPORTING
Progress reports are used for computing payments, and for monitoring the progress against the Contractor’s baseline schedule.
The Contractor shall develop a progress report utilizing the ‘Reports’ feature of their scheduling software. Contractor developed reports shall provide the same information as AF Form 3065, Contract Progress Report. The progress report shall utilize the same work elements and schedule of values/cost loading data developed for the design/construction schedule.
25 Sep 25 Statement of Work - 15 of 27 WWYK240176
Contractor shall submit a draft version of the progress report to the CO and the COR for approval within ten (10) calendar days after the NTP is issued (with the Baseline Schedule).
After approval, the Contractor shall submit progress reports weekly, or as directed by the CO, throughout the life of the Order. For each progress report, the Contractor shall include the following:
(1) Percentage of work completed for each work element during the reporting period.
(2) Cumulative percentage of work completed for each work element to date.
(3) Cumulative percentage of work completed for all work elements (percent of Order completion).
(4) Scheduled cumulative percentage of work completed for all work elements, based on the baseline Order schedule (scheduled percent of Order completion).
Progress report’s will be reviewed by the Construction QA Inspector and/or the Project Manager, who will in turn provide a recommendation to the COR to approve/disapprove the progress report; approval of the Contractor’s progress report does not constitute acceptance of the work as being 100% in compliance with the Order requirements (i.e. project specifications, drawings, and this SOW).
In the event that the Contractor’s reported progress deviates from the baseline schedule, the CO may elect to hold progress meetings.
3.5 DESIGN/ENGINEERING
3.5.1 Contractor’s Design Requirements
The Government has provided a SOW (this document), design narrative, and drawings (including as-built information) stating current site conditions and project objectives/ requirements for the Contractor’s use in preparing a complete design, ready for construction.
Design is to be accomplished in accordance with specification section 01 33 16.00 10. The Contractor’s design effort shall include the following submissions:
• Preliminary Design (35%)
• Intermediate Design (65%)
• Pre-Final Design (95%)
• Final Design/Issued for construction (100%)
The Preliminary Design submittal (35%) shall be presented to the Architectural/Engineering Review Board (AERB); meetings are scheduled for every Thursday, 0800-100. At this meeting, the contractor will present the design package, discussing such items as: project scope, design approach, identified code deficiencies, deviations from the contract documents, etc.
3.5.2 Minimum Design Guidance Documents
The Contractor, as a minimum, is required to comply with the current editions of each of the following publications for design and construction. The term ‘most current’ is understood to mean, “Most current as of the date the solicitation is issued.”
Codes/standards/regulations referenced by these publications are included as a part of this SOW to the extent referenced. In case of conflict between the project documents (SOW and drawings), 25 Sep 25 Statement of Work - 16 of 27 WWYK240176
Unified Facility Criteria (UFCs), governing codes/standards, and the Tinker AFB facility standards, the Contractor shall submit a request for information (RFI) to the Government for resolution.
3.5.2.1 General
(1) UFC 1-200-01, DoD Building Code
(2) UFC 1-200-02, High Performance and Sustainable Building Requirements
(3) UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings
(4) Tinker AFB Facility Standard
3.5.2.2 Civil
(1) UFC 3-201-01, Civil Engineering
(2) UFC 3-230-01 Water Storage, Distribution, and Transmission
(3) UFC 3-240-01 Wastewater Collection and Treatment
(4) UFC 3-250-01, Pavement Design for Roads and Parking Areas
(5) UFC 4-022-03, Security Fences and Gates
3.5.2.3 Architectural – N/A
3.5.2.4 Structural – N/A
3.5.2.5 Mechanical
(1) UFC 3-240-01 Domestic Wastewater Treatment
(2) UFC 3-401-01, Mechanical Engineering
(3) UFC 3-410-01, Heating, Ventilating, and Air Conditioning Systems
(4) UFC 3-410-02, Direct Digital Control for HVAC and Other Building Control Systems
(5) UFC 4-410-04, Industrial Ventilation
(6) UFC 3- 420-01, Plumbing Systems
(7) UFC 3-420-02FA, Compressed Air
(8) UFC 3-450-01, Noise and Vibration Control
(9) Tinker AFB Mechanical Standard
3.5.2.6 Electrical
(1) UFC 3-501-01, Electrical Engineering
(2) UFC 3-520-01, Interior Electrical Systems
(3) UFC 3-530-01, Interior and Exterior Lighting Systems and Controls
(4) UFC 3-575-01, Lightning and Static Electricity Protection Systems
(5) Air Force Manual (AFMAN) 32-1065, Grounding and Electrical Systems
(6) NFPA 70 National Electrical Code
(7) NFPA 780 Standard for Installation of Lighting Protection System
25 Sep 25 Statement of Work - 17 of 27 WWYK240176
(8) Tinker AFB Electrical Standard
3.5.2.7 Fire Protection- N/A
3.5.3 Design Submittals
All design submittals shall be submitted in accordance with specification sections 01 33 00 and 01 33 16.00 16; for design submittals, only the final design submittal (95%) will be submitted with an AF Form 3000. Upon completion of the 95% review, the contractor will receive the submittal and AF 3000 back with one of the following three designations: Approved; Approved with Comments; or Disapproved.
• Approved: Provide the signed/sealed 'Issued for Construction' submittal in electronic format (as described below).
• Approved with Comments: Provide an unsealed 'Issued for Construction' submittal in electronic format. The electronic submittal will serve as back check set; once Government has verified that all comments have been addressed, submit signed/sealed documents (as described below).
• Disapproved: Resubmit in accordance with specification section 01 33 00.
Material submittals (SD-03, SD-04, SD-07, SD-08) for major components of the work shall be provided during the pre-Final design phase (earlier for long lead items) in accordance with 01 33 00; information provided as part of the design documents (for example, cut sheets attached to a design analysis/narrative) will not be considered as meeting submittal requirements.
Shop drawings used as design drawings shall be in accordance with the requirements of specification section 01 33 16.00 16.
3.5.3.1 Preliminary Design (35% Design)
The preliminary design shows the essential components of the proposed design and conveys that the Contractor fully understands the contract requirements and has included all elements of work to complete the project.
The documents shall include the following minimum information, as applicable to the project:
• Changes necessary to comply with Government comments/scope refinements resulting from the initial design conference.
• Site plans, floor plans, elevations, building sections, and wall sections that have been further developed from preliminary documents provided by the government.
• Single-line schematic drawings for mechanical, electrical, communications, etc.
• Listing of proposed Unified Federal Guide Specification (UFGS) sections applicable to the project.
• Design analysis that includes design narrative and analysis, including code analysis by all disciplines.
• Listing of Government furnished materials.
25 Sep 25 Statement of Work - 18 of 27 WWYK240176
• Previous meeting minutes and documentation of any other communication between the Government and the Contractor that influenced the design.
3.5.3.2 Intermediate Design (65% Design)
Intermediate design builds upon the preliminary design and demonstrates that design development is in full progress. Intermediate Design can be performed in conjunction with Government approval of the Contractor’s responses to the review comments on the Preliminary Design submittal.
The documents shall include the following minimum information, as applicable to the project:
• Any changes necessary to comply with Government comments to the Preliminary Design submittal.
• Complete site and landscaping plans.
• Architectural plans with complete floor and roof plans; elevations, building sections, wall sections; interior/exterior finish schedules; color boards; and other details and notes as required.
• Structural plans.
• Mechanical, fire protection, plumbing, and electrical plans with details, notes, and equipment schedules. Equipment layouts showing clearances required for maintenance and/or code.
• Specifications in rough draft (redlines/strikeouts).
• Design analysis that includes design narrative and analysis. The design analysis shall include all design assumptions and calculations for all disciplines, code analysis by all disciplines, manufacturers’ material and equipment cut sheets for major equipment/fixtures.
• Updated construction schedule to include any work phasing to accommodate Government operations.
• Copies of previous design review comments and responses; previous meeting minutes; and documentation of any other communication between the Government and the Contractor that influenced the design.
3.5.3.3 Pre-Final Design (95% Design)
The pre-final design represents what the contractor believes to be a complete design, ready for construction. Pre-Final Design can be performed in conjunction with Government approval of the Contractor’s responses to the review comments on the Intermediate (65%) Design.
The documents shall include the following minimum information, as applicable to the project:
• Any changes necessary to comply with Government comments to the intermediate design.
• Complete construction drawings and specifications.
25 Sep 25 Statement of Work - 19 of 27 WWYK240176
• Submittal Register (generated from Contractor's specifications).
• Final design analysis.
• Material submittals (SD-03, SD-04, SD-07, SD-08) for all major components of work (generated from Contractor’s specifications).
• Color boards and finishes.
• Recovered Material Determination Form (RMDF).
• Final construction schedule to include any work phasing to accommodate Government operations.
• Copies of previous design review comments and responses; previous meeting minutes; and documentation of any other communication between the Government and the Contractor that influenced the design.
3.5.3.4 Final Design (100% Design)
Final ‘issued for construction’ versions of documents submitted for Pre-Final (95%) review.
The documents shall include the following minimum information, as applicable to the project:
• Any changes necessary to comply with Government comments to the Pre-Final Design.
• Sealed construction drawings and specifications.
• Submittal Register (generated from Contractor’s specifications).
• Sealed design analysis.
• Corrected material submittals.
• Signed RMDF.
4. DESIGN-BUILD APPROACH/OBJECTIVES
The following is provided as a starting point for the contractor’s design; in addition, a project narrative (Attachment 3) has been provided which includes discussions of the existing facility systems and functional requirements for the new building systems. This information should not be considered complete; the Contractor and their Designer of Record (DOR) shall be responsible for thoroughly reviewing the information provided, performing their own site investigations and code review, and completing the design/construction for a complete and useable project.
4.1 CIVIL DEMOLITION
4.1.1 Existing Lift Station Removal
(1) Refer to drawings for demolition work.
(2) This Design Build, KTR will design need foundation.
(3) All buried tanks must be evaluated for hydrostatic uplift (buoyancy), and their foundations shall be designed accordingly by a structural engineer of record (SER)
25 Sep 25 Statement of Work - 20 of 27 WWYK240176
4.2 CIVIL CONSTRUCTION
4.2.1 New Lift Station and Site Work
(1) Refer to drawings for new work.
4.3 ARCHITECTURAL DEMOLITION – N/A
4.4 ARCHITECTURAL CONSTRUCTION – N/A
4.5 STRUCTURAL DEMOLITION – N/A
4.6 STRUCTURAL CONSTRUCTION – N/A
4.7 FIRE PROTECTION DEMOLITION – N/A
4.8 FIRE PROTECTION CONSTRUCTION – N/A
4.9 MECHANICAL DEMOLITION – N/A
4.10 MECHANICAL CONSTRUCTION – N/A
4.11 PLUMBING DEMOLITION
4.11.1 Existing Industrial Waste Lift Station
(1) Refer to drawings for demolition work.
(2) Demolish pumps, piping, rails, and appurtenances in each sump according to the phasing plan.
4.12 PLUMBING CONSTRUCTION
4.12.1 New Industrial Waste Lift Station
(1) Refer to drawings for new work.
(2) Provide signed and sealed construction documents for new work. DOR to verify pump flow rates, T.S.P., HP, float control system and Honeywell EBI connection required for new
IWLS.
(3) Installation shall be designed and constructed IAW UFC 3-420-01, Plumbing Systems, UFC 3-240-01, Domestic Wastewater Treatment, and the TAFB Mechanical Standard.
4.13 ELECTRICAL DEMOLITION
4.13.1 Existing Electrical
(1) Refer to drawing to coordinate the construction sequencing for demolition.
4.14 ELECTRICAL CONSTRUCTION
4.14.1 New Electrical
(1) Existing electrical service for the Industrial Waste Lift Station 6N & 6S (Facility B62502) is fed from Panel MDP 2119-PNL-6, which is a 480/277 Volt, 3 Phase, 100 Amp Service (CKT 1, 3, 5) in (Facility 2119). This panel is on Emergency Generator.
(2) Validate that the existing electrical service conductors are in good shape and can support the new lift station pumps.
(3) Refer to drawing for electrical Scope of Work.
25 Sep 25 Statement of Work - 21 of 27 WWYK240176
4.13 ORDER OF PRECEDENCE
In the event of a conflict or inconsistency between any of the provisions of this contract, precedence shall be applied in the following order:
(1) Any portions of the accepted proposal which both conform to and exceed the requirements of the solicitation.
(2)…
This is the start of the file's text. The full file is on GovTribe.