Granville Health System Imaging Renovation - MRI, CT, Nuc Med - General Construction/Renovation
Solicitation number
373GHS00004
Issued by
Gates County, North Carolina

About this file

The document is a Table of Contents (Document 00 01 10) for the MRI, CT, and Nuclear Imaging Renovations project at Granville Medical Center in Oxford, North Carolina, prepared by Haskell (Project 1785003) with an original date of March 31, 2025 and an Addendum 2 dated May 9, 2025. The comprehensive table of contents spans multiple divisions including Procurement and Contracting Requirements (Division 00), General Requirements (Division 01), Existing Conditions (Division 02), Concrete, Metals, Wood/Plastics/Composites, Thermal and Moisture Protection, Openings, Finishes, Specialties, and Special Construction. The document provides a detailed breakdown of sections and page counts for the construction documents, indicating a complex renovation project involving medical imaging facilities.

The table of contents suggests a significant healthcare renovation project with substantial technical complexity, particularly in specialized areas like RFI/EMI shielding, X-ray shielding, and modular shielding rooms. Notable sections include extensive requirements for quality control, administrative procedures, infection control, and minority business enterprise participation. The project appears to involve comprehensive renovations across multiple technical domains, with specific attention to healthcare-specific construction requirements, including specialized glazing, radiation-resistant materials, and detailed technical specifications for medical imaging infrastructure. The document indicates multiple divisions are "NOT USED", focusing the project scope on specific critical renovation elements for the medical imaging suites.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MRI, CT, and Nuclear Imaging Renovations Granville Medical Center Oxford, North Carolina

00 01 10 - Table of Contents - Page 1

Construction Documents Haskell Project 1785003

March 31, 2025 Addendum 2, May 9, 2025

DOCUMENT 00 01 10

TABLE OF CONTENTS

Division 00 – Procurement and Contracting Requirements

00 01 01 – Project Title Page

00 01 07 – Seals Page

00 01 10 – Table of Contents

00 11 13 – Advertisement for Bids

00 21 00 – Instructions

00 21 14 – Instructions to Bidders and General Conditions of the Contract

00 25 19 – Document Clarification Request (DCR)

00 26 00 – Procurement Substitution Procedures

00 31 00 – Available Project Information

00 31 02 – Shielding Report [PENDING] ................................................................................................ #

00 41 00 – Bid Form

00 42 14 – Form of Proposal

00 43 24 – Document Clarification Request (DCR) Form

00 43 25 – Substitution Request Form (During Procurement)

00 43 39 – Minority Business Enterprise Statement of Intent Form

00 43 40 – Identification of HUB Certified/Minority Business Participation

00 45 39 – Minority Business Enterprise Affidavits

00 45 41 – State of North Carolina Affidavit A – Listing of Good Faith Efforts

00 45 42 – State of North Carolina Affidavit B – Intent to Perform Contract with Own Workforce

00 45 43 – State of North Carolina Affidavit C – Portion of the Work to be Performed by HUB Certified/Minority Businesses

00 45 44 – State of North Carolina Affidavit D – Good Faith Efforts

00 52 00 – Agreement Form

00 52 01 – Construction Contract

00 61 13 – Performance and Payment Bond Forms

00 61 13.13 – Performance Bond Form

00 61 13.16 – Payment Bond Form

00 63 13 – Request for Interpretation Form (During Construction)

00 63 25 – Substitution Request Form (During Construction)

00 65 36 – General Building Guarantee

00 65 37 – Watertightness Guarantee

00 72 00 – General Conditions

00 73 39 – Minority Business Enterprise Requirements

00 73 40 – Outreach Plan for Minority Business Participation in Building Construction

Division 01 – General Requirements

01 10 00 – Summary

01 20 00 – Price and Payment Procedures

00 01 10 - Table of Contents - Page 2

Haskell Project 1785003

01 22 00 – Unit Prices

01 23 00 – Alternates

01 25 00 – Substitution Procedures

01 26 13 – Requests for Interpretation

01 26 54 – Proposal Worksheet Summaries

01 30 00 – Administrative Requirements

01 30 01 – Submittal Data Sheet

01 32 16 – Construction Progress Schedule

01 35 01 – General Project Procedures

01 35 13.19 – Special Project Procedures for Healthcare Facilities

01 35 33 – Infection Control Procedures

01 35 46 – Indoor Air Quality Procedures

01 40 00 – Quality Requirements

01 42 16 – Definitions

01 43 03 – Owner’s Quality Assurance

01 45 17 – Contractor’s Quality Control

01 45 33 – Code-Required Special Inspections and Procedures

01 45 34 – Special Inspections – Reports

01 50 00 – Temporary Facilities and Controls

01 51 00 – Temporary Utilities

01 58 13 – Temporary Project Signage

01 60 00 – Product Requirements

01 70 00 – Execution and Closeout Requirements

01 78 00 – Closeout Submittals

01 79 00 – Demonstration and Training

Division 02 – Existing Conditions

02 41 00 – Demolition

Division 03 – Concrete (SEE ALSO STRUCTURAL DRAWINGS)

03 05 16 – Underslab Vapor Retarder

03 30 00 – Cast-in-Place Concrete

03 54 00 – Cast Underlayment

Divisions 04 – Masonry (NOT USED)

Division 05 – Metals

05 45 00 – Metal Support Assemblies

Division 06 – Wood, Plastics, and Composites

06 10 00 – Rough Carpentry

06 40 00 – Architectural Woodwork

06 61 16 – Solid Surfacing Fabrications

Division 07 – Thermal and Moisture Protection

07 01 51 – Existing Roof Modifications

07 62 00 – Sheet Metal Flashing and Trim

00 01 10 - Table of Contents - Page 3

Haskell Project 1785003

07 81 00 – Applied Fireproofing

07 84 00 – Firestopping

07 92 00 – Joint Sealants

Division 08 – Openings

08 12 13 – Hollow Metal Frames

08 14 16 – Flush Wood Doors

08 14 73 – Sliding Wood Doors

08 31 00 – Access Doors and Panels

08 34 50 – Radiation Shielding Frames

08 71 00 – Door Hardware

08 80 00 – Glazing

08 88 13 – Fire-Rated Glazing

08 88 49 – Radiation-Resistant Glazing

Division 09 – Finishes

09 05 61 – Common Work Results for Flooring Preparation

09 05 63 – Relative-Humidity Checklist

09 05 64 – Relative-Humidity Report Form

09 21 16 – Gypsum Board Assemblies

09 51 00 – Suspended Acoustical Ceilings

09 54 16 – Luminous Ceilings

09 65 00 – Resilient Flooring

09 91 23 – Interior Painting

Division 10 – Specialties

10 21 23 – Cubicle Curtains

10 26 23.13 – Impact-Resistant Wall Protection

10 28 13 – Toilet Accessories

10 44 00 – Fire Protection Specialties

Divisions 11 and 12 (NOT USED)

Division 13 – Special Construction

13 49 13 – Integrated X-Ray Shielding Assemblies

13 49 23 – Integrated RFI/EMI Shielding Assemblies

13 49 26 – Modular RFI-Shielding Rooms

Divisions 14 through 20 (NOT USED)

Division 21 – Fire Suppression (NOT USED)

Division 22 – Plumbing (SEE DRAWINGS)

Division 23 – Heating, Ventilating, and Air-Conditioning (SEE DRAWINGS)

Divisions 24 and 25 (NOT USED)

Division 26 – Electrical (SEE DRAWINGS)

Divisions 27 through 49 (NOT USED)