0. 1240LT24Q0045 - Solicitation.pdf

PDF 1 MB Posted

Attached to
Sage Hen Reservoir Road Improvements
Solicitation number
1240LT24Q0045
Issued by

About this file

This document is a Solicitation for the Sage Hen Reservoir Road Improvements project. The scope of work includes crack sealing, asphalt patching, and placing a chip seal on approximately 4.65 miles of roadway. The contractor shall furnish all labor, materials, equipment, and supplies, with the work to be performed in accordance with the FP-14 Standard Specifications and supplemental project specifications.

The project is located on National Forest System Road 614 in the Emmett Ranger District of the Boise National Forest in Gem County, Idaho. The Contracting Officer's Representative will designate staging areas, and limited onsite camping may be allowed. The period of performance is expected to be between July 1, 2024 and October 1, 2025. Offers are due by June 20, 2024, and the Government contemplates award of a single Firm Fixed Price construction contract. The magnitude of the project is between $500,000 and $1,000,000.

View the file

Other files

File Type Posted
Questions-Answers 001.pdf PDF
4. Fire Precaution Standard Langauge.pdf PDF
1. Schedule of Items.pdf PDF
6. Davis-Bacon Act WD # ID20240099 - Gem.pdf PDF
3. Maps and Drawings.pdf PDF
5. Experience Questionnaire.doc DOC document
2. FSSS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1124803

USDA-FS CSA INTERMOUNTAIN 8

324 25TH ST

OGDEN UT 84401-2310

40LT

Tony Taylor tony.taylor@usda.gov

All email subject lines should contain:

Sagehen Reservoir Road Improvements -

1240LT24Q0045

TONY TAYLOR tony.taylor@usda.gov

670152

05/13/2024

1240LT24Q0045

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Boise NF - Emmett Ranger District

Sage Hen Reservoir Road Improvements

All work performed shall be in accordance with the SOW, Solicitation, all supporting documents, terms and conditions.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 458 calendar days and complete it within ________________ ________________ calendar days after receiving

52.211-10

06/20/2024

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA-FS CSA INTERMOUNTAIN 8

324 25TH ST

OGDEN UT 84401-2310

40LT

LONNIE D. ROOT

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 41

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

1240LT24Q0045

Sage Hen Reservoir Road Improvements

Period of Performance: 07/01/2024 to 10/01/2025

0001 0402 CONST BOISE CIP SAGEHEN RESERVOIR ROAD

IMPROVEMENTS

Contracting Specialist: Tony Taylor -tony.taylor@usda.gov

Contracting Officer Representative (COR): Brett

Barry - ryan.barry@usda.gov

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No: 1240LT24Q0045 Project Name: Sage Hen Reservoir Road Improvements

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 PERIOD OF PERFORMANCE

C.5 TECHNICAL SPECIFICATIONS

C.6 TECHNICAL REQUIREMENTS

C.7 ORDER OF PRECEDENCE

C.8 SITE VISIT

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

G.2 GOVERNMNET FURNISHED PROPERTY

G.3 MEASUREMENT

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 STORAGE OF FUEL AND OTHER TOXICANTS WITHIN RIPARIAN

CONSERVATION AREAS (RCA – WITHIN 300 FEET OF LIVE STREAMS

H.3 TRAFIC CONTROL

H.4 PUMPS

H.5 DRAFTING SITE ACCESS

H.6 CONSTRUCTION AND EARTHMOVING ACTIVITIES

H.7 POLLUTION CONTROL MEASURES

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

L.1 PROVISIONS

L.2 QUOTE PREPARATION INSTRUCTIONS:

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROVISIONS

M.2 QUOTE EVALUATION

M.3 TECHNICAL EVALUATION FACTORS

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

Note: * Next to an Item Number indicates that the quantity shown is a Contract Quantity per FP-14 Specification 109.02.

Contractor Name:__________________________________________ UEI:______________________

Email:____________________________________________________ Phone:____________________

Date offer will be honored through:____________________________

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

15101 Mobilization Lump Sum 1 ------------------- $

40601* Fog Seal – Bituminous Flush Coat (0.15 Gal/SQYD) CSS- 1H

SQYD 57,288 $ $

40701* Asphalt Surface Treatment, ½” Chips

SQYD 57,288 $ $

40702 Asphalt Surface Treatment, Emulsified Asphalt, CRS- 2P, (0.5gal/SQYD)

Ton 120 $ $

41401 Asphalt Pavement Crack Sealing and Filling

Lump Sum 1 ------------------- $

41801 Asphalt Concrete Pavement Patching, Type 3, Cold Patch

Lump Sum 1 ------------------- $

TOTAL: $

B.2 SCHEDULE NOTES

a) One Firm Fixed Price contract will be awarded from this solicitation; contractors must submit pricing for all items.

b) Please provide a quote expiration date with your quote. Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

c) Payment for bond premiums in accordance with FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Include bond payments under Base Item 15101 – Mobilization.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

A. This project consists of crack sealing, patching asphalt, and chip sealing approximately

4.65 miles of the roadway.

B. Quantities associated with this work are included in the Schedule of Items and in the project plans.

C. All work shall be in compliance with the contract documents. The contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies. Work includes but is not limited to: crack sealing for alligator cracking, longitudinal/transverse cracks, patching potholes, depressions, and rutting, and placing a ½” chipseal. All work will be in accordance with FP-14 and supplemental project specifications. Contractor is responsible for providing 3rd party inspection and testing for all aspects of chipseal work.

D. Allowed road closures and disruptions are included in the Forest Service Supplemental Specifications (FSSS) (Section 156 Public Traffic).

E. The Contracting Officers Representative (COR) will designate staging areas along the construction site. Limited camping for project personnel will be allowed at the site with permission of the COR. Staging of materials for the project will be allowed in designated areas inside the project boundary if approved in writing by the COR at the time of the project implementation.

• Depending on the snow and seasonal temperatures, the site is commonly accessible between May 15th and October 30th of most years.

C.2 PROJECT LOCATION

A. National Forest System Road (NFSR) 614 - The project site is located on the Emmett Ranger District, Boise National Forest, Gem County, Idaho on National Forest System Road (NFSR) #614, Township 12 North, Range 2 East, Sections 34, 35, and 36. The project begins at the intersection of NFSR 626/666, on the west side of Sage Hen Reservoir and continues 0.15 miles to intersection of NFSR 614. The remaining 4.5 miles is along NFSR 614 as shown in the plans.

B. Site Information and Limitations

The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. The road may be closed for construction activities if needed and must be approved in advance by the Forest Service. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. For chipseal/fogseal application, delays may not exceed 11 days (Monday through following Thursday) at any one time followed by an open period of no less than 3 days (Friday – Sunday).

For crack sealing and pothole repair, delays may not exceed 4 weekdays (i.e., Monday – Thursday), if necessary. The Forest Service will issue a closure order to the public after receipt of a request for closure submitted by the Contractor at least 60 days in advance. The Contractor is responsible for developing and implementing a traffic control plan that conforms to MUTCD while working within the roadway.

2. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks, and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brush guard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

3. Utilities are not available at the site for construction purposes.

C. Work Camps, Staging and Storage Areas

Areas for staging operations and storage of materials shall be approved in writing by the COR. Locations must be on hardened surfaces.

D. Inspection of Worksite

The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Per FAR 36.204(e) the magnitude of this project is between $500,000 and $1,000,000.

C.4 PERIOD OF PERFORMANCE

Performance is expected to be completed between 07/01/2024 and 10/01/2025.

C.5 TECHNICAL SPECIFICATIONS

The Standard Specifications for this project are contained within the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S. Customary Units.

Copies of this document are available on-line only at the Federal Highway Administration web site at https://highways.dot.gov/federal-lands/specs in either Microsoft Word .doc or Adobe Acrobat .pdf format.

Supplemental Project Specifications included in full text in Section J of the contract amend, supplement, or replace the Standard Specifications.

Standard Specifications (FP-14) and Forest Service Supplemental Specifications (FSSS) contained in the following list are applicable to this contract.

FSSS 101 Terms, Format, and Definitions FSSS 102 Bid, Award, and Execution of Contract FSSS 103 Scope of Work FSSS 104 Control of Work FSSS 105 Control of Material FSSS 106 Acceptance of Work FSSS 107 Legal Relations and Responsibility to the Public FSSS 108 Prosecution and Progress FSSS 109 Measurement and Payment FSSS 155 Schedules for Construction Contracts FSSS 156 Public Traffic FSSS 157 Soil Erosion Control https://highways.dot.gov/federal-lands/specs

FSSS 407 Chip Seal

NOTE: Contractors are cautioned to carefully review these Standard and Supplemental Project Specifications prior to submission of offers. All specifications in the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S. Customary Units are binding on the parties signing the contract unless amended, supplemented, or replaced with Supplemental Project Specifications.

452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C.6 TECHNICAL REQUIREMENTS

Specific construction drawings and Supplemental Project Specifications are included in Section J. All items shown or noted on plans, which are not specifically bid items, are considered indirect payment items, per FP-14, Section 109.05(b). The cost of furnishing and installing all indirect payment items will not be paid for separately but shall be included in the unit price bid for other items unless noted otherwise.

C.7 ORDER OF PRECEDENCE

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) Bid Schedule

(2) Representations and other instructions

(3) Contract clauses

(4) Other documents, exhibits, and attachments

(5) Forest Service Supplemental Specifications (FSSS)

(6) Standard Specifications (FP-14)

(7) (a) Plans, figured dimensions over scaled dimensions

(b) Plans, large scale contract plans over small-scale contract plans

(c) Schedules on contract plans over any conflicting notations on contract plans

(8) Shop drawings

C.8 SITE VISIT

No formal site visit is scheduled. NOTE per FAR 52.236-3 Site Investigation and Conditions Affecting the Work, the contractor is encouraged and expected to visit the site. Site is open to the public to visit. Coordination with the COR, Brett Barry, ryan.barry@usda.gov, to ensure accessibility to the site concerning inclement weather would be prudent.

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.211-13 Time Extensions (SEP 2000) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984)

52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than October 1, 2025. The time stated for completion shall include final cleanup of the premises.

Site construction activities shall not occur before September 3rd, 2024 due to concurrent projects within the area.

Within 5 days after work commences, the Contractor will prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the work, in accordance with Clause 52.236-15 (Schedules for Construction Contracts).

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held via Microsoft Teams.

G.2 GOVERNMNET FURNISHED PROPERTY

None.

G.3 MEASUREMENT

Units of measurement shall be as indicated in the Schedules of Items.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

452.228-71 Insurance Coverage (NOV 1996) (Alternate I) Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

• Crew Leader

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H.2 STORAGE OF FUEL AND OTHER TOXICANTS WITHIN RIPARIAN

CONSERVATION AREAS (RCA – WITHIN 300 FEET OF LIVE STREAMS

Storage of fuel and other toxicants within Riparian Conservation Areas (RCA – within 300 feet of live streams) is prohibited. Refueling of equipment may be done within the RCA only at locations approved by the Contracting Officer. A Spill Prevention & Containment Plan is required and shall be submitted to the Contracting Officer for approval prior to beginning construction. A sample plan form is available and can be obtained at the Pre-Work Meeting. A spill containment kit shall be available on site that is to accommodate potential spills from the equipment used during construction.

H.3 TRAFIC CONTROL

No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items. Signage will be required at the immediate work site, both ends of the 614 Road, the 626 Road (Ola side and Smith’s Ferry side), and at the intersection of 614/609 roads at minimum.

See Section 156 in supplemental specs for details on road closures/lane restrictions.

H.4 PUMPS

All pumps used for drafting must be outfitted with a suction screen that has a maximum opening size of 3/32”. Locate water drafting sites at a location approved by the CO.

H.5 DRAFTING SITE ACCESS

If drafting site is necessary, location must be approved by COR.

H.6 CONSTRUCTION AND EARTHMOVING ACTIVITIES

• Conduct excavation with minimal impact to any active stream channels. Store excavated material in designated stockpile areas.

• Cross streams with equipment only at dewatered areas, on temporary bridges, or at designated temporary crossings.

• Store equipment in approved staging areas when not in use. Cease all operations in the event of local precipitation events or high flows, except efforts to minimize storm damage or excessive erosion.

• Provide certified weed free erosion control materials in order to prevent the spread of noxious weeds.

H.7 POLLUTION CONTROL MEASURES

• Follow State and Federal regulations regarding spills: e.g., report any spills resulting in a detectable sheen on water to the EPA National Response Center (1-800-424- 8802).

• Report any spills over 25 gallons to the IDEQ (1-800-632-800), and initiate cleanup within 24 hours of the spill.

• Clean all equipment of external oil, grease, dirt and mud, and repair all leaks prior to arriving at the project site. Make equipment available for inspection by the C.O. and obtain approval from the C.O. before unloading at the site.

• Correct any leaks or accumulations of grease before entering streams or areas that drain directly to streams or wetlands.

• Fuel and service all equipment, including chainsaws and other hand power tools in an approved staging area.

• Keep a spill containment kit containing oil-absorbing floating booms, or other equipment such as pads and absorbent peanuts, capable of containing hazardous oil spills from the largest piece of equipment used on site. Keep the spill containment kit available on-site during all phases of construction and place in a location that facilitates an immediate response to potential petroleum leakage.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses:

https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower

Guidance to contractor employees) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY

2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN

2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab Covered Entities (DEC 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (NOV 2021) 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (NOV 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (SEP 2023) 52.219-14 Limitations on Subcontracting (OCT 2022)

☒ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

52.219-28 Post Award Small Business Program Rerepresentation (SEP 2023) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY

2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC

2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (MAY 2022) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN

2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN

2020) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997)

52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT

2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate I (APR 1984) Alternate II (APR 1984)

52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-2 Subcontracts (JUN 2020) 52.244-6 Subcontracts for Commercial Products and Commercial Services (NOV 2023) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)

Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV

1996) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988)

452.236-77 Emergency Response (NOV 1996)

52.204-21 Basic Safeguarding of Covered Contractor Information Systems (NOV 2021)

(a) Definitions. As used in this clause– “Covered contractor information system” means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

“Federal contract information” means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.

“Information” means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).

“Information system” means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

“Safeguarding” means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract

Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access;

and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

http://uscode.house.gov/

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, https://www.acquisition.gov/far/part-2#FAR_2_101 plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

https://www.acquisition.gov/far/part-25#FAR_25_105

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None.

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i)Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with…

This is the start of the file's text. The full file is on GovTribe.