About this opportunity
Trinidad State College, a Colorado state institution, is soliciting sealed bids under IFB TSC IFB2027000049 for Phase 2 window replacement at its Berg Building, with bids due November 17, 2026 at 3:00 p.m. MST. Preference is given to Colorado resident bidders and Colorado labor, and at least 80% of the work must be performed by Colorado labor.
Bidders must have operated under the same business name for at least two years, completed at least two similar projects each exceeding $750,000 in hard costs, hold bonding capacity up to $1,000,000, and have no prior termination by the State for non-performance. A bid bond equal to 5% of the total bid is required, along with payment and performance bonds of not less than 50% of the contract value.
Addendum 1 covers removal and replacement of exterior windows on the first and second floors, with third- and fourth-floor replacements designated as Add Alternates 1 and 2 and three boiler room windows excluded. New fixed aluminum windows with simulated divided lights must achieve a maximum U-value of 0.36 and a maximum SHGC of 0.36, using Manko 3345i Series components with cove profile exterior muntins. The contractor is responsible for asbestos abatement during window removal and assumes potential lead-based paint on windows and sills pending testing. The Buy Clean Colorado Act applies to glass materials, requiring Global Warming Potential documentation, and Colorado prevailing wage applies with wages reported through LCP Tracker. The Rev 1 advertisement describes the project as a boiler system installation and building automation system upgrade, with window replacement as Phase 2.
The estimated cost is $880,000, and no liquidated damages apply. Windows are ordered December 1, 2026, on-site work starts April 1, 2027, and completion is targeted for June 30, 2027, under a phased schedule coordinated with the College to maintain building operations. The College requires procurement by mid-December 2026 to use expiring project funds. Award notification is anticipated November 19, 2026, with contract approval by November 30, 2026. The mandatory pre-bid walkthrough was held November 9, 2026. Sealed hardcopy bids go to Penny Bueno, Berg Building Room 109, and the virtual public opening follows at 3:15 p.m. the same day via Microsoft Teams.