This is an Advertisement for Bids issued by Trinidad State College, a Colorado state institution, for a design-bid-build construction project to install a boiler system and upgrade the associated building automation system at the Berg Building, with window replacement as Phase 2 of the project. The project, numbered 2023-088M22 (Notice Number TSC IFB2027000049), has an estimated total cost of $880,000. The scope of work includes full construction contracting services as specified in the accompanying drawings, specifications, and supporting documents. A mandatory pre-bid conference and site tour will be held on November 9, 2026, at 10:00 AM at the Berg Building (600 Prospect Street, Trinidad, Colorado 81082). Sealed bids must be submitted by November 17, 2026, at 3:00 PM MST, with a virtual public bid opening occurring at 3:15 PM the same day via Microsoft Teams. The anticipated award notification is November 19, 2026, with contract approval expected by November 30, 2026. Construction is anticipated to begin December 1, 2026, with work commencing on-site April 1, 2027, and completion targeted for June 30, 2027.

Bidders must meet minimum qualifications including no prior termination by the State for non-performance, operation under the same business name for at least two years, and demonstrated experience on at least two similar projects each exceeding $750,000 in hard costs. A bid bond or proposal guaranty equal to 5% of the total bid amount and a bonding capacity letter up to $1,000,000 are required, with costs included in the bid. Since the project exceeds $500,000, it is subject to the Buy Clean Colorado Act requirements, Colorado prevailing wage rates, and payment/performance bonds of not less than 50% of the contract value. Colorado labor must constitute at least 80% of the work performed. Additionally, contractors awarded contracts of this size must utilize LCPTracker for labor compliance and certified payroll reporting. Preference is given to Colorado resident bidders and Colorado labor per state law. All bid submittals become the property of Colorado, and the State reserves the right to reject any or all proposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADVERTISEMENT FOR BIDS

Design / Bid / Build State of Colorado Trinidad State College

Notice Number: TSC IFB2027000049 Project Number: 2023-088M22 Project Title: INSTALL BOILER SYSTEM AND UPGRADE ASSOCIATED BUILDING AUTOMATION SYSTEM, BERG, PH 2 (Window Replacement) Estimated Project Cost: $880,000

NOTICES

For all projects with a total dollar value above $150,000 Notice of Final Settlement is required by C.R.S. §38-26-107(1). Final Settlement, if required, will be advertised in the same location as the original solicitation.

For State Public Works C.R.S. §8-17-101 - Colorado labor shall be employed to perform at least 80% of the work. Colorado labor means any person who is a resident of the state of Colorado at the time of the Public Works project.

All respondents accept the conditions of this AFB, including but not limited to, the following:

a. All submittals shall become the property of the State of Colorado and will not be returned.

b. Late submittals shall not be evaluated.

c. The State reserves the right to reject any or all proposals on the basis of being unresponsive to this AFB or for failure to disclose requested information.

d. The State shall not be liable for any costs incurred by respondents in the preparation of submittals and proposals nor in costs related to any element of the selection and contract negotiation process.

The respondent has reviewed Appendix F and by responding has agreed that the terms and conditions of the sample Contractor’s Design/Bid/Build (D/B/B) Agreement (SC-6.21) and General Terms and Conditions of the Contractor’s Design/Bid/Build Agreement (SC- 6.23) are expressly workable without reservation. Any exceptions to the contract must be communicated formally in writing before the bid closes.

Per C.R.S. §24-92-117, a public construction project in the amount of five hundred thousand dollars or more shall be subject to the Buy Clean Colorado (BCCO) Act program requirements. The BCCO Act requires the Office of the State Architect to establish a maximum acceptable global warming potential (GWP) limit for each category of eligible materials, which include asphalt and asphalt mixtures, cement and concrete mixtures, glass, post-tension steel, reinforcing steel, structural steel, and wood structural elements. For any solicitation for a contract for the design of an eligible project, a State Agency or institution shall require the designer who is awarded the contract to include, in project specifications when final construction documents are released, a current Environmental Product Declaration (EPD) that meets the maximum acceptable GWP limits for each eligible material specified for the project. A contractor that is awarded a contract for an eligible project shall not install any eligible materials on the project until the contractor submits an EPD for each eligible material procured for the project.

Per C.R.S. §24-92-Part 2, a public construction project in the amount of five hundred thousand dollars or more shall be subject to the State prevailing wage rate, of the regular, holiday, and overtime wages paid and the general prevailing payments on behalf of employees to lawful welfare, pension, vacation, apprentice training, and educational funds in the State, for each employee needed to execute the contract. Payments to the funds must constitute an ordinary business expense deduction for federal income tax purposes by contractors and subcontractors. Contractors are required to pay their employees at weekly intervals and shall comply with the enforcement provisions of C.R.S. §24-92-209. Contractors awarded a project of this size will be required to utilize the LCPTracker cloud-based labor compliance and certified payroll application.

Preference shall be given to Colorado resident bidders and for Colorado labor, as provided by law.

Per C.R.S. §24-105-201 If the construction value is $50,000 or greater a Bid Bond and Power of Attorney or Proposal Guaranty is required in an amount not less than 5% of the total Bid.

PROJECT OVERVIEW

The State of Colorado, Trinidad State College, is soliciting bids from qualified contractors for the INSTALL BOILER SYSTEM AND UPGRADE ASSOCIATED BUILDING AUTOMATION SYSTEM, BERG, PH 2 (Window Replacement) project.

Scope of Services

The scope of services will include full Construction Contracting Services for the project specified during the process of construction and warranty period to the State as per the Advertisement for Bid. Specific tasks to be performed by the Contractor include those generally performed by the construction community where the Contractor is the prime vendor to the State. Bidders shall reference the drawings, specifications, and supporting documents in the Appendices for an understanding of the entire scope of the project.

Per C.R.S. §38-26-106, if a contract amounts to $150,000 or more, the awarded contractor shall provide payment and performance bonds not less than 50% of the value of the contract. The costs associated with this bond are to be included in the contractor’s bid.

MINIMUM REQUIREMENTS

Notice is hereby given to all interested parties that all firms will be required to meet all minimum requirements to be considered for this project. Interested bidders should be prepared to show evidence of the following to be considered as qualified, as a minimum:

1. Not previously terminated by the State for non-performance on a State Buildings contract or procurement.

1. The bidding contractor must have been in the same business, under the same name for the last two (2) years.

Demonstrated specific contracting experience in projects of similar scope and complexity for at least two (2) projects each in excess of $750,000 (hard costs), utilizing the expertise present in their Colorado Office; and Demonstrated bonding capability up to $1,000,000 for an individual project coincidentally with current and anticipated workloads; provide letter from surety that affirms this capacity.

Attended and signed in at the Mandatory Pre-Bid Conference Firms meeting the minimum requirements may obtain the bidding documents on the website accompanying this advertisement.

MANDATORY PRE-BID CONFERENCE AND SITE TOUR

A mandatory Pre-Bid Meeting will be held at:

Building Address: Berg Building - 600 Prospect St., Trinidad, CO 81082 Room: Meet at Front Entrance Date/Time November 09, 2026 / 10:00 AM

SCHEDULE

The following is a tentative schedule of events for the Bid Submittal process and an outline of the schedule for the balance of the project. All dates are subject to change and changes in the schedule will be issued via addendum.

Advertisement for Bids IssuedNovember 3, 2026Mandatory Pre-Bid Conference and Site TourNovember 9, 2026, 10:00 amRequest for Clarifications DueNovember 10, 2026Final Addendum Issued (anticipated)November 13, 2026Bid Submittals Due (date and Time)November 17, 2026, 3:00 PM
Public Bid OpeningNovember 17, 2026, 3:15 PM
Award Intent Notification (anticipated)November 19, 2026
Contract Approval (anticipated)November 30, 2026
Anticipated Construction StartOrder Windows: Dec 1, 2026
On Site: April 1, 2027
Anticipated Construction FinishJune 30, 2027

The above schedule is tentative. Responding firms shall be notified of revisions in a timely manner by email or posted on ColoradoVSS website. Respondents may elect to verify times and dates by email, but no earlier than 36 hours before the scheduled date and time.

QUESTIONS, CLARIFICATIONS AND ADDENDA

Owner initiated changes to this AFB will be issued under numerically sequenced addenda.

Owner initiated changes to this AFB will be posted in the form of addenda on ColoradoVSS.

Questions and requests for clarifications regarding this project shall be submitted before the deadline listed in the above Schedule.

Communication regarding the project during the procurement, outside of the this submission process or scheduled procurement milestones is not permitted.

POINT OF CONTACT/CLARIFICATION

Name: Jeff Dryden Agency: NV 5 (Owner’s Representative) Email Address: Jeff.Dryden@NV5.com Phone: 719-920-8049

BIDDING

Bids shall be submitted on the required bid form as indicated on the Information for Bidders document (SBP-6.12) in Appendix A.

A hard copy of the sealed bid submittal is due November 17, 2026 and shall be received no later than 3:00 PM MST, and shall be submitted as described in the Information for Bidders (SBP-6.12)

Bid Forms and Appendices to be included with bid submittal:

Bid Form (SBP-6.13) Bid Bond (SBP-6.14) Bid Alternates (SBP-6.131)

Late bid submittals will be rejected without consideration. The State of Colorado assume no responsibility for costs related to the preparation of bid submittals.

BID OPENING

Opening of the bid submittals will be a virtual public bid opening. Bids will be opened on Teams:

https://teams.microsoft.com/meet/2761406482928145?p=ND96oDWs5ilFHjJqgPe.

Virtual public bid opening will take place at the date and time identified in Schedule

APPENDICES:

Appendix A:Information for Bidders (SBP-6.12)
Appendix B:Bid Form (SBP-6.13)
Appendix B1:Bid Alternates (SBP-6.131)
Appendix B3:Bid Bond (SBP-6.14)
Appendix C:Sample: Direct Labor Burden Calculation (SBP-6.18)
Appendix D:Applicable Prevailing Wage and Apprenticeship and Fringe Rates
Appendix F:Sample: SC6.21 and SC6.23 Design/Bid/Build Contractor’s Agreement and General Conditions of the Contract

OSA-AFB-1 pg. 5

REV 7/2025