Lehigh County Authority solicited sealed bids through PennBid for the Main Pump House and Dewatering Improvements at Kline's Island Wastewater Treatment Plant in Allentown, Pennsylvania, with bids due October 20, 2026 at 11:00 a.m. prevailing time after Addendum 3 extended the deadline from October 16. Attendance at the mandatory pre-bid conference and site visit held September 17, 2026 was required, and bids from parties not present were not accepted.
The work is split into four separate contracts: General Construction (Bid No. 50661G), Mechanical (Bid No. 50661M), Electrical (Bid No. 50661E), and Plumbing (Bid No. 50661P). Bidders must demonstrate a minimum of five years' experience and at least ten completed projects of similar nature, and each bid must carry security equal to 10% of the bid total, in the form of a bid bond or certified check. Addendum 1 replaced the aluminum perimeter trim section with suspended decorative grids specifying Armstrong Axiom Classic components in extruded 6063 aluminum, with single-source responsibility across trades. Addendum 2 establishes the Draper, Inc. FlexShade cassette roller shade as basis-of-design, requires ANSI/WCMA A100.1, NFPA 701, and GREENGUARD Gold certifications, and mandates manufacturer-authorized installers with at least three years of documented experience. Addendum 2 also specifies replacement lavatory and shower enclosure components on Drawing P-7.1. Addendum 3 revised structural steel quality assurance to AWS D1.1/D1.1M and removed duplicate General Conditions and Health and Safety sections.
Addendum 1 clarifies project budgets of $775,000 for General Construction, $320,000 for Mechanical, $450,000 for Electrical, and $185,000 for Plumbing. Work is performed at Kline's Island Wastewater Treatment Plant.
Questions were due October 14, 2026 at 4:00 p.m. through PennBid's Public Q&A tab. A combined bid tabulation for Bid No. 50661 is posted, reflecting bids received through PennBid.
Opportunity text
Online Sealed Bids will be received by the LEHIGH COUNTY AUTHORITY via the PennBid Program until 11:00 a.m. prevailing time on Tuesday, October 20, 2026. All bids will be publicly opened online and posted. The project is titled "Main Pump House and Dewatering Improvements" and will consist of four contracts: General Construction Bid No. 50661G Mechanical Construction Bid No. 50661M Electrical Construction Bid No. 50661E Plumbing Construction Bid No. 50661P All documents and solicitation details are available online for no cost at PennBid (www.pennbid.net) A mandatory pre-bid conference will be held at 10:00 AM prevailing time on Thursday, September 17, 2026 at the Kline's Island Wastewater Treatment Plant, Training Room located at 112 Union Street, Allentown, PA 18102. Bids from parties not present at the pre-bid conference and site visit will not be accepted. Each Bid must be accompanied by Bid security in the form of a Bid bond (in the required form) or certified check for ten percent of the Bid total. It is a requirement of this Contract that Bidder shall have a minimum of (5) years' experience and at least (10) completed projects of similar nature to the Work required by this Project. Questions and inquiries should be addressed through PennBid's "Public Q & A" tab. The deadline for all questions and inquiries is 4:00 PM Wednesday, October 14, 2026. The Lehigh County Authority hereby reserves the right, which is understood and agreed to by all Bidders, to reject any or all Bids and to waive any omissions, errors, or irregularities in any Bid.
Files
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity