4-Addendum 1 w Attach.pdf

PDF 3 MB Posted

Attached to
Main Pump House and Dewatering Improvements
Solicitation number
US.250316
Issued by
Lehigh County, Pennsylvania

About this file

This is Addendum No. 1, issued September 28, 2026, for a construction project by Lehigh County Authority involving the Main Pump House and Dewatering Improvements at Kline's Island Wastewater Treatment Plant. The project comprises four separate contracts: General Construction (Bid No. 50661G), Mechanical Construction (Bid No. 50661M), Electrical Construction (Bid No. 50661E), and Plumbing Construction (Bid No. 50661P). The addendum modifies the original bid documents by updating the Table of Contents, adding a Substitution Request Form (Section 00 26 25), and replacing Section 09 54 36 "Aluminum Perimeter Trims" with "Suspended Decorative Grids" specifications. The addendum includes a sign-in sheet from the mandatory pre-bid meeting held on September 17, 2026, and incorporates clarifications regarding project budgets (General Contractor: $775,000; Mechanical: $320,000; Electrical: $450,000; Plumbing: $185,000), temporary trailer requirements, unit pricing labor inclusions, RTU quantities, fire alarm system specifications, and electrical installation methods. The revised bid due date is Friday, October 16, 2026, at 11:00 a.m. via PennBid.

The Suspended Decorative Grids specification requires Armstrong Axiom Classic perimeter trim components manufactured from extruded aluminum alloy 6063, available in straight sections (10 feet standard, 12 feet for select sizes) and curved profiles to accommodate interior and exterior radii applications. The specification mandates single-source responsibility with coordination requirements among multiple trades and includes sustainable materials preferences for products with Health Product Declarations, low VOC emissions, Environmental Product Declarations, and LEED V5 compliance. The warranty period for perimeter trim components is ten years from substantial completion, with Armstrong commercial products carrying a thirty-year warranty when installed as a complete system. Installation must comply with ASTM C 635, ASTM C 636, and ASTM E 580 standards, and seismic components must be included if required by building code. Substitution requests must be submitted ten working days prior to bid closing with complete product data, samples, technical specifications, and documentation of equal or superior performance and quality.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 1 Page 1 of 2 09/28/26

Addendum No. 1 Issued: September 28, 2026

Project Name: Lehigh County Authority

Kline’s Island Wastewater Treatment Plant

Main Pump House and Dewatering Improvements

Bid # 50661

Project Owner: Lehigh County Authority

Construction: CHA Consulting, One East Broad St., Suite 310

Bethlehem, PA 18018

BID DUE DATE: Friday, October 16, 2026 @ 11:00 a.m. via PennBid

1.0 GENERAL INFORMATION:

1.1 This addendum consists of 17 pages including the following attachments:

• 1 page of a sign-in sheet from the pre-bid meeting held on 9/17/26.

• 3 pages of Table of Contents dated 9/28/26.

• 4 pages of 00 26 25 Substitution Request Form.

• 7 pages of 09 54 36 Suspended Decorative Grids.

2.0 CHANGES TO PREVIOUS ADDENDA:

2.1 None.

3.0 CHANGES TO THE BIDDING REQUIREMENTS, CONTRACT FORMS, &

CONDITIONS OF THE CONTRACT:

3.1 None.

4.0 CHANGES TO THE SPECIFICATIONS:

4.1 DELETE 00 01 10 Table of Contents in its entirety and REPLACE with the attached 00 01 10

Table of Contents, Addendum No. 1 dated 9/28/26.

4.2 ADD attached 00 26 25 Substitution Request Form.

4.3 DELETE 09 54 36 Aluminum Perimeter Trims in its entirety and REPLACE with the attached

09 54 36 Suspended Decorative Grids.

The following clarifications, amendments, additions, deletions, revisions and/or modifications shall become part of the Contract and DELETE or modify the original bidding documents to the extent indicated or stated herein.

Addendum No. 1 Page 2 of 2 09/28/26

5.0 CHANGES TO THE DRAWINGS:

5.1 None.

6.0 BIDDER QUESTIONS:

Below are the questions received during bidding as of September 28, 2026.

6.1 Question: Are there budgets for each contract?

Response: General Contractor Budget: $775,000; Mechanical Contractor Budget: $320,000;

Electrical Contractor Budget: $450,000; Plumbing Contractor Budget: $185,000

6.2 Question: Do the temporary trailers need any restrooms, furniture, benches, lockers, etc.?

Response: The trailers do not need restrooms, furniture, benches or lockers.

6.3 Question: Electrical Base Bid Allowance – Should #2-1, #2-2 & #2-3 include labor?

Response: All unit pricing must include prevailing wage labor, material costs, necessary equipment, and all items associated with that scope portrayed.

6.4 Question: Just clarifying that there are 2 RTUs on this project one on the main pump building and the other on the dewatering building?

Response: Correct, one for each building.

6.5 Question: Is fire alarm wiring installed above ceiling required to be in conduit?

Response: No.

6.6 Question: Where new electrical is required but existing walls are not getting opened up or removed is surface mounted conduit an approved installation method?

Response: Yes, painted to match existing walls.

6.7 Question: What fire alarm system / company is currently installed in the main pump house?

Response: There is no fire alarm system.

6.8 Question: What fire alarm system / company is currently installed in the dewatering building?

Response: There is no fire alarm system.

6.9 Question: If a new fire system would be provided for each building would this system be required to be installed throughout the existing buildings and not just in the renovations area?

Response: Just in the areas indicated on the bid documents.

END OF ADDENDUM NO. 1

LEHIGH COUNTY AUTHORITY – KLINE’S ISLAND WWTP ISSUE FOR BID

LCA BID NO. 50661

MAIN PUMP HOUSE AND DEWATERING IMPROVEMENTS

TABLE OF CONTENTS 00 01 10 - 1

Addendum No. 1 9/28/26

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

001113 Notice to Bidders .......................................................................................................................... 0-1

002113 Instructions to Bidders (LCA) .................................................................................................... 0-18

002625 Substitution Request Form............................................................................................................ 0-4

022113.1 Public Works Employment Verification Form............................................................................. 0-2

PROCUREMENT FORMS AND SUPPLEMENTS

004113G General Contract Bid Form (LCA) ............................................................................................... 0-6

004113M Mechanical Contract Bid Form (LCA) ......................................................................................... 0-6

004113P Plumbing Contract Bid Form (LCA) ............................................................................................ 0-6

004113E Electrical Contract Bid Form (LCA) ............................................................................................ 0-6

004117 Agreement of Surety ..................................................................................................................... 0-1

004313 Bid Bond (LCA) ........................................................................................................................... 0-2

004314 Certificate as to Corporate Principal ............................................................................................. 0-1

004336 List of Proposed Subcontractors ................................................................................................... 0-1

004513 Experience Questionnaire ............................................................................................................. 0-3

004519 Affidavit of Non-Collusion ........................................................................................................... 0-1

004520 Contractor's Certification of Authority and Qualification to do Business in Pennsylvania ......... 0-1

CONTRACTING AND PROJECT FORMS AND SUPPLEMENTS

005213 Agreement (LCA) ......................................................................................................................... 0-8

006113 Performance Bond (LCA)............................................................................................................. 0-3

006115 Payment Bond (LCA) ................................................................................................................... 0-3

006172 Waiver of Liens/Mechanic’s Lien Waiver ................................................................................... 0-3

006216 Sample Certificate of Insurance .................................................................................................... 0-1

CONDITIONS OF THE CONTRACT

007000 General Conditions including Supplementary Conditions (LCA) ............................................. 0-63

007319 Health and Safety Requirements ................................................................................................ 0-24

007343 Pennsylvania Prevailing Wage Rate Requirements ..................................................................... 0-2

007346.1 PA L&I Form LLC-25 Blank ....................................................................................................... 0-2

007346.13 Prevailing Wage Rate Determination Schedule ........................................................................... 0-8

008200 Safety and Health Management Plan Project Requirements ...................................................... 0-24

DIVISION 01 – GENERAL REQUIREMENTS

011000 Summary of Work ........................................................................................................................ 1-8

011400 Work Restrictions ......................................................................................................................... 1-6

012000 Measurement and Payment ........................................................................................................... 1-3

012100 Allowances .................................................................................................................................... 1-2

012200 Unit Prices ..................................................................................................................................... 1-1

012300 Alternates ...................................................................................................................................... 1-1

TABLE OF CONTENTS 00 01 10 - 2

012600 Contract Modification Procedures ................................................................................................ 1-3

DIVISION 01 – GENERAL REQUIREMENTS (CONTINUED)

012900 Payment Procedures ...................................................................................................................... 1-4

013100 Project Management and Coordination ........................................................................................ 1-4

013116 Multiple Contract Coordination .................................................................................................. 1-10

013200 Construction Progress Documentation ......................................................................................... 1-5

013300 Submittal Procedures .................................................................................................................... 1-5

014000 Quality Requirements ................................................................................................................... 1-6

014200 References ..................................................................................................................................... 1-2

015000 Temporary Facilities & Controls .................................................................................................. 1-9

016600 Product Storage and Handling Requirements ............................................................................... 1-3

017300 Execution Requirements ............................................................................................................... 1-5

017329 Cutting and Patching ..................................................................................................................... 1-3

017419 Construction Waste Management ................................................................................................. 1-3

017700 Closeout Procedures...................................................................................................................... 1-5

017839 Project Record Documents ........................................................................................................... 1-5

DIVISION 02 – EXISTING CONDITIONS

024119 Selective Demolition .................................................................................................................... 1-8

028233 Asbestos Containing Materials .................................................................................................... 1-8

028319 Lead Based Paint Awareness ........................................................................................................ 1-6

DIVISION 03 – CONCRETE

035416 Hydraulic Cement Underlayment ................................................................................................ 1-4

DIVISION 04 – MASONRY

040110 Masonry Cleaning ......................................................................................................................... 1-6

040120.63 Brick Masonry Repair ................................................................................................................... 1-6

040120.64 Brick Masonry Repointing ........................................................................................................... 1-4

042200 Concrete Unit Masonry ............................................................................................................... 1-12

DIVISION 05 – METALS

051200 Structural Steel Framing ............................................................................................................... 1-6

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

061000 Rough Carpentry ........................................................................................................................... 1-6

064023 Interior Architectural Woodwork ................................................................................................. 1-8

064116 Plastic-Laminate-Clad Architectural Cabinets ............................................................................. 1-6

064219 Plastic-Laminate-Faced Wood Paneling ...................................................................................... 1-4

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

072500 Weather Barriers ........................................................................................................................... 1-4

TABLE OF CONTENTS 00 01 10 - 3

DIVISION 08 – OPENINGS

081113 Hollow Metal Doors and Frames .................................................................................................. 1-8

081213 Hollow Metal Frames ................................................................................................................... 1-4

081416 Flush Wood Doors ........................................................................................................................ 1-8

084213 Aluminum Framed Entrances ....................................................................................................... 1-8

085413 Fiberglass Windows ...................................................................................................................... 1-6

088000 Glazing .......................................................................................................................................... 1-8

DIVISION 09 – FINISHES

092216 Non-Structural Metal Framing ..................................................................................................... 1-6

092900 Gypsum Board .............................................................................................................................. 1-6

093013 Ceramic Tiling .............................................................................................................................. 1-8

093023 Glass Mosaic Tiling ...................................................................................................................... 1-6

095123 Acoustical Tile Ceilings ................................................................................................................ 1-6

095436 Suspended Decorative Grids ......................................................................................................... 1-8

096723 Resinous Flooring ......................................................................................................................... 1-8

099123 Interior Painting ............................................................................................................................ 1-8

099600 High Performance Coatings .......................................................................................................... 1-4

DIVISION 10 – SPECIALTIES

101416 Plaques .......................................................................................................................................... 1-4

102600 Wall and Door Protection ............................................................................................................. 1-4

DIVISION 12 – FURNISHINGS

122413 Roller Window Shades ................................................................................................................. 1-6

123605 Metal Fabrications, Countertop Support Brackets ....................................................................... 1-6

123640 Stone Countertops ......................................................................................................................... 1-6

123653 Laboratory Worksurfaces ............................................................................................................. 1-8

123661.16 Solid Surfacing Countertops ......................................................................................................... 1-4

ATTACHMENTS

A - Asbestos Testing Results

TABLE OF CONTENTS 00 01 10 - 4

[THIS PAGE INTENTIONALLY LEFT BLANK]

SUBSTITUTION REQUEST FORM 00 26 25 - 1

SECTION 00 26 25

SUBSTITUTION REQUEST FORM

A. Submissions for approved substitutions will be permitted and processed in accord with Article

10 of Document 002113 “Instructions to Bidders”.

B. Submissions will be "received dated" immediately upon arrival at the office of Engineer.

C. All Submissions must be received ten (10) days prior to bid or they may not be reviewed.

D. Reviewer's General Criteria for review will be:

1. Burden of proof of performance equality and completeness of this submittal is the responsibility of the submitter.

2. Reviewers will not be required to complete the submittal, that is, select from options or between models and lines of products.

3. Reviewer will not be required to seek information from the manufacturer's literature on file in the office, or information from other locations.

4. Product must be equal, or better, in those features and performance which specified product provides.

5. When in the reviewer's opinion, significant deficiencies are established, further review of submitted data is not required.

G. Reviewer will note action (approval or disapproval), the date, and their initials.

H. If a submittal is disapproved, reviewer will make notations that will be adequate to guide a later reviewer to the same conclusion. Sample notations may be: "Submittal vague", "incomplete", or "product equality not substantiated".

I. Submittals received after closing time will be "received dated," marked "late", initialed, and filed without review.

J. Submittals will be filed in the project file until completion of the project, then destroyed.

K. Approval of a substitute item will be communicated to bidders in the form of an Addendum.

SUBSTITUTION REQUEST FORM 00 26 25 - 2

TO:

CHA

1 E. Broad St., Suite 310

Bethlehem, PA 18018

PROJECT

PRIME BIDDER

CONTRACTOR/SUPPLIER

We hereby submit for consideration, the following product instead of specified item for above project:

SECTION/DRAWING PARAGRAPH/DETAIL SPECIFIED ITEM

Proposed Substitution:

MANUFACTURER’S HOME OFFICE: LOCAL REPRESENTATIVE:

Address: _______________________ Address: _______________________

Telephone: _______________________ Telephone: _______________________

Contact: _______________________ Contact: _______________________

Attached to this request is product data, specifications, performance tests and data, and color samples.

The attached information also includes any modifications of the Contract Documents which would be required if this substitution is utilized for this Project.

The undersigned states that as a Prime Bidder on the above referenced Project the following statements are true.

1. The Prime Bidder has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. That the product manufacturer will provide the same warranty for the Substitution as for the specified Product.

3. That the use of this product will not have an adverse effect on any other trade or Prime

Contractor or the Construction Schedule.

4. That the use of this product does not affect the dimensions shown on the Drawings unless specifically stated in the attached information.

Reason for Substitution:

SUBSTITUTION REQUEST FORM 00 26 25 - 3

ATTACHMENTS (If not applicable, write N/A in space provided)

No. 1 Complete product data, including technical data and laboratory tests, if applicable.

No. 2 Drawings indicating dimensional changes.

No. 3 Complete description of changes to drawings and specifications which proposed substitution will require for its proper installation.

No. 4 Necessary samples and substantiating data to prove equal quality, performance, and appearance to that which is specified. Clearly mark manufacturer's literature to indicate equality in performance.

Differences in quality of materials and construction shall be indicated.

No. 5 List of names and addresses of three similar projects on which product was used, date of installation, and Engineer/Engineer's name, address, and telephone numbers.

Fill in blanks below (Provide attachments if more space is necessary)

A. Does the substitution affect dimensions indicated on the Contract Drawings?

Yes No If yes, clearly indicate changes:

B. Will the undersigned pay for changes to the building design, including engineering and detailing costs caused by the requested substitution?

C. What effect does substitution have on other trades, other contracts, and Contract Completion Date?

D. What effect does substitution have on applicable code requirements?

E. List differences between proposed substitution and specified item:

F. Identify manufacturer's guarantees:

G. Identify cost impact; Provide attachments showing proposed credit:

SUBSTITUTION REQUEST FORM 00 26 25 - 4

Undersigned attests function and quality equivalent or superior to specified item.

CERTIFICATION OF EQUAL PERFORMANCE:

Submitted by: Title:

Company:

Address:

Date:

Telephone: E-mail:

Signature:

For Use by the Engineer:

Accepted Accepted as Noted:

Not Accepted Received Too Late:

Reviewer: Date:

REMARKS:

END OF SECTION 00 26 25

SUSPENDED DECORATIVE GRIDS 09 54 36 - 1

SECTION 09 54 36

SUSPENDED DECORATIVE GRIDS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general conditions of Contract, including General and Supplementary Conditions and Divisions-1 Specification sections apply to work of this section.

1.2 SUMMARY

A. Section Includes:

1. Extruded Aluminum Perimeter Trims

2. Related Sections:

a. Section 08 44 00 – Curtain Wall and Glazed Assemblies

b. Section 09 51 00 (09510) – Acoustical Ceilings

c. Section 09 20 00 (09250) – Plaster and Gypsum Board

d. Divisions 23 (15) – HVAC

e. Division 26 (16) Sections - Electrical Work

f. Section 26 50 00 Lighting

3. Alternates

B. Prior Approval: Unless otherwise provided for in the Contract documents, proposed product substitutions may be submitted no later than TEN (10) working days prior to the date established for receipt of bids. Acceptability of a proposed substitution is contingent upon the Architect’s review of the proposal for acceptability and approved products will be set forth by the Addenda.

If included in a Bid are substitute products which have not been approved by Addenda, the specified products shall be provided without additional compensation.

C. Submittals that do not provide adequate data for the product evaluation will not be considered.

The proposed substitution must meet all requirements of this section, including but not necessarily limited to, the following: Single source materials suppliers (if specified in Section 1.5); panel design, size, composition, color, and finish; suspension system component profiles and sizes;

compliance with the referenced standards.

1.3 REFERENCES

A. American Society for Testing and Materials (ASTM):

1. ASTM C 635 Standard Specifications for Metal Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings.

SUSPENDED DECORATIVE GRIDS 09 54 36 - 2

2. ASTM C 636 Recommended Practices for Installation of Metal Ceiling Suspension

Systems for Acoustical Tile and Lay-in Panels.

3. ASTM E 580 Installation of Metal Suspension Systems in Areas Requiring Moderate

Seismic Restraint

4. ASCE 7 American Society of Civil Engineers, Minimum Design Loads for Buildings and

Other Structures

B. International Code Council-Evaluation Services - AC 156 Acceptance Criteria for Seismic

Qualification Testing of Non-structural Components

C. LEED - Leadership in Energy and Environmental Design is a set of rating systems for the design, construction, operation, and maintenance of green buildings. American National Standards

Institute (ANSI)

D. ANSI H35.1 Properties and Characteristics of Wrought Aluminum Alloys

1.4 SYSTEMS DESCRIPTION

A. The Armstrong Axiom Classic system is a premium, pre-engineered perimeter trim solution designed for suspended acoustical and drywall ceiling assemblies. Manufactured from high-grade extruded aluminum, it features a crisp, structural profile that ensures straightness and durability superior to traditional roll-formed steel. The system is engineered to provide a clean, factory-finished edge detail for floating ceiling "clouds," bulkheads, pocket transitions, and perimeter elevations where a wall-to-wall ceiling configuration is not utilized.

B. Equipped with integrated channels and specialized field-locating clips, the Axiom Classic trim allows for seamless mechanical integration with standard 15/16-inch and 9/16-inch suspension grids, as well as drywall framing systems. Available in both factory-straight sections and custom-curved radii, the system accommodates varying profile heights (ranging from 2 inches to 14 inches) to create a distinct, monolithic fascia that effectively conceals the exposed suspension grid and the raw edges of ceiling panels.

1.5 SUBMITTALS

A. Product Data: Submit manufacturer’s technical data for perimeter components and each type of suspension system required.

B. Samples: Minimum 3-inch-wide samples of specified component.

C. Shop Drawings: Layout and details of acoustical ceilings. Show locations of items that are to be coordinated with or supported by the ceilings.

1.6 SUSTAINABLE MATERIALS

A. Transparency: Manufacturers will be given preference when they provide documentation to support sustainable requirements for the following: Material ingredient transparency, Removal of

Red List Ingredients per LBCV3, Life Cycle impact information, Low-Emitting Materials, and

Clean Air performance.

SUSPENDED DECORATIVE GRIDS 09 54 36 - 3

B. Health Product Declaration (HPD). The end use product has a published, complete Health Product

Declaration with disclosure at a minimum of 1000ppm of known hazards in compliance with the

Health Product Declaration Open Standard.

C. Declare Label. The end use product has a published Declare label by the International Living

Future Institute with disclosure of 100 ppm with a designation of Red List Free or Compliant (less than 1% proprietary ingredients).

D. Low Emitting products with VOC emissions data. Preference will be given to manufacturers that can provide emissions data showing their products meet any of the following:

CDPH/EHLB/Standard Method v1.2-2017; Indoor Air Quality Certified to SCS-105 v4.2-2023;

Gold VOC Certificate OR Clearchem.

E. Life cycle analysis. Products that have communicated lifecycle data through Environmental

Product Declarations (EPDs) will be preferred.

F. End of Life Programs/Recycling: Where applicable, manufacturers that provide the option for recycling of their products into new products at end-of-life through take-back programs will be preferred.

G. Products meeting LEED V5 requirements including:

1. Storage & Collection of Recyclables

2. Construction and Demolition Waste Management Planning

3. Building Life-Cycle Impact Reduction

4. Building Product Disclosure and Optimization Environmental Product Declarations

5. Building Product Disclosure and Optimization Sourcing of Raw Materials

6. Building Product Disclosure and Optimization Material Ingredients

7. Construction and Demolition Waste Management

1.7 QUALITY ASSURANCE

A. Single-Source Responsibility: Provide perimeter trim components and grid components by a single manufacturer.

B. Coordination of Work: Coordinate acoustical ceiling work with installers of related work including, but not limited to building insulation, gypsum board, light fixtures, mechanical systems, electrical systems, and sprinklers.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver perimeter trim components to project site in original, unopened packages and store them in a fully enclosed space where they will be protected against damage from moisture, direct sunlight, surface contamination, and other causes.

B. Before installing components permit them to reach room temperature and a stabilized moisture content.

C. Handle components carefully to avoid damage.

SUSPENDED DECORATIVE GRIDS 09 54 36 - 4

1.9 PROJECT CONDITIONS

A. Space Enclosure:

1. Building areas to receive ceilings shall be free of construction dust and debris. Products with can be installed up to 120°F (49°C) and in spaces before the building is enclosed, where HVAC systems are cycled or not operating. Cannot be used in exterior applications where standing water is present or where moisture will come in direct contact with the ceiling.

1.10 WARRANTY

A. Perimeter Trim System: Submit a written warranty executed by the manufacturer, agreeing to repair or replace components that fail within the warranty period. Failures include, but are not limited to:

1. Rusting and manufacturer’s defects

B. Warranty Period:

1. Perimeter Trim Components: Ten (10) years from date of substantial completion.

C. Armstrong commercial trim components, suspension systems and ceiling products have a thirty

(30) year warranty when installed together and used under normal conditions.

D. The Warranty shall not deprive the Owner of other rights the Owner may have under other provisions of the Contract Documents and will be in addition to and run concurrent with other warranties made by the Contractor under the requirements of the Contract Documents.

PART 2 - PRODUCTS

2.1 PERIMETER TRIM

A. Product/Manufacturer: Axiom® Classic Perimeter Trim; Armstrong World Industries, Inc.

B. Components: Edge trim system for suspended ceiling system, extruded aluminum alloy 6063 trim channel, 10 foot straight (12 foot straight in 2”, 4” and 6”) or curved profiles to minimum

18” (24” for 3” high) inside and outside radii for acoustical and for drywall applications.

1. Axiom Trim Channel Straight: (2”) (3”) (4”) (6”) (8”) (10”) (12”) (14”) (16”) wide face with 3/4 inch horizontal legs, straight sections with special bosses formed for attachment to the Axiom tee-bar connection clip or hanging clip; commercial quality, extruded aluminum, factory-finished in (factory-applied baked polyester paint to match Armstrong)

( ) color; (custom paint finish color-matched to approved sample).

a. AX2STR - 2" Straight Perimeter Trim

b. AX2STR12 - 2" Straight Perimeter Trim

c. AX3STR - 3" Straight Perimeter Trim

d. AX4STR - 4" Straight Perimeter Trim

SUSPENDED DECORATIVE GRIDS 09 54 36 - 5

e. AX4STR12 - 4" Straight Perimeter Trim

f. AX6STR - 6" Straight Perimeter Trim

g. AX6STR12 - 6" Straight Perimeter Trim

h. AX8STR - 8" Straight Perimeter Trim

i. AX10STR - 10" Straight Perimeter Trim

j. AX12STR - 12" Straight Perimeter Trim

k. AX14STR - 14" Straight Perimeter Trim

2. AX16STR - 16" Straight Perimeter Trim

3. Axiom Trim Channel Curved: As Indicated on Drawings.

a. AX2CUR - 2" Curved Perimeter Trim

b. AX3CUR - 3" Curved Perimeter Trim

c. AX4CUR - 4" Curved Perimeter Trim

d. AX6CUR - 6" Curved Perimeter Trim

e. AX8CUR - 8" Curved Perimeter Trim

f. AX10CUR - 10" Curved Perimeter Trim

g. AX12CUR - 12" Curved Perimeter Trim

h. AX14CUR - 14" Curved Perimeter Trim

i. AX16CUR - 16" Curved Perimeter Trim

4. Axiom Inside Corner Posts (Straight Only): As Indicated on Drawings.

a. AX2ISCPCTN – 2” Axiom Classic Inside Corner Post

b. AX4ISCPCTN – 4” Axiom Classic Inside Corner Post

c. AX6ISCPCTN – 6” Axiom Classic Inside Corner Post

d. AX8ISCPCTN – 8” Axiom Classic Inside Corner Post

e. AX10ISCPCTN – 10” Axiom Classic Inside Corner Post

f. AX12ISCPCTN – 12” Axiom Classic Inside Corner Post

5. Axiom Outside Corner Posts (Straight Only): As Indicated on Drawings.

a. AX2OSCPCTN – 2” Axiom Classic Outside Corner Post

b. AX4OSCPCTN – 4” Axiom Classic Outside Corner Post

c. AX6OSCPCTN – 6” Axiom Classic Outside Corner Post

d. AX8OSCPCTN – 8” Axiom Classic Outside Corner Post

e. AX10OSCPCTN – 10” Axiom Classic Outside Corner Post

f. AX12OSCPCTN – 12” Axiom Classic Outside Corner Post

6. Axiom Inside Corners (Straight Only): As Indicated on Drawings.

a. AX2QSISCTN – 2” inside corner

b. AX2QSISCTN – 2” inside corner

c. AX4QSISCTN – 4” inside corner

d. AX6QSISCTN – 6” inside corner

e. AX8QSISCTN – 8” inside corner

f. AX10QSISCTN – 10” inside corner

g. AX12QSISCTN – 12” inside corner

h. AX14QSISCTN - 14" inside Corner

i. AX16QSISCTN - 16" inside Corner

7. Axiom Outside Corners (Straight Only): As Indicated on Drawings.

a. AX2QSOSCTN – 2” outside corner

b. AX4QSOSCTN – 4” outside corner

SUSPENDED DECORATIVE GRIDS 09 54 36 - 6

c. AX6QSOSCTN – 6” outside corner

d. AX8QSOSCTN – 8” outside corner

e. AX10QSOSCTN – 10” outside corner

f. AX12QSOSCTN – 12” outside corner

g. AX14QSOSCTN - 14" outside Corner

h. AX16QSOSCTN - 16" outside Corner

8. Accessories:

a. AXAC – Alignment clip, Sheet aluminum formed to fit into special trim channel bosses. Provides positive mechanical lock and screw-fastened connection to suspension members that intersect below the trim channel.

b. AX2HGC – Hanging clip, commercial quality aluminum, unfinished, used when suspension wires must be attached directly to the trim sections.

c. AXSPLICE2 – Splice with set screws, galvanized steel, unfinished, used to attached factory-mitered inside corners

d. AX4SPLICE – Splice with set screws, galvanized steel, unfinished, used to attach joints between sections of trim.

e. AXSPLICESS – Axim Splice Plate - Stainless Steel for non-ferrous project applications

f. AXTBC – T-bar Connector Clip, galvanized steel, unfinished, used to attach channel trim to supporting suspension members. (AXTBCSS Stainless Steel for non-ferrous project applications)

g. 7239 - Adjustable Trim Clip - Allows Axiom® trim to be positioned up to 3-3/4" below the grid face to accommodate deeper panel offsets (best aesthetic with Axiom

≥ 6" tall).

h. AXSPTHDC – Perimeter Trim Hold Down Clip used to secure cut edges of metal panels at the Axiom trim.

i. AXBTSTR – Drywall Bottom Trim Straight, extruded aluminum, 120 inches x 1-

9/64 inch x 27/32 inch, used to finish edges of 5/8 inch drywall that is applied to the bottom surface of the Axiom.

j. AXBTCUR – Drywall Bottom Trim Curved, extruded aluminum, 120 inches x 1-

9/64-inch x 27/32 inch, used to finish edges of 5/8 inch drywall that is applied to the bottom surface of the Axiom.

k. AXBTASTR - Bottom Trim for AcoustiBuilt ceiling systems Straight, 120 inches in length, used to finish edges of an Acoustibuilt panel that is applied to the bottom surface of the Axiom.

l. AXBTACUR - Bottom Trim for Acoustibuilt ceiling systems Curved, 120 inches in length, used to finish edges of an Acoustibuilt panel that is applied to the bottom surface of the Axiom.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Do not proceed with installation until all wet work such as concrete, terrazzo, plastering and painting has been completed and thoroughly dried out, unless expressly permitted by manufacturer’s printed recommendations.

SUSPENDED DECORATIVE GRIDS 09 54 36 - 7

3.2 PREPARATION

A. Coordinate panel layout with mechanical and electrical fixtures.

3.3 INSTALLATION

A. Install suspension system and panels in accordance with manufacturer’s instructions, and in compliance with ASTM C 636 and with the authorities having jurisdiction

B. Install seismic components if required by the building code. Seismic components to be specified on the architectural plans by the project engineer or design team.

3.4 ADJUSTING AND CLEANING

A. Clean exposed surfaces of trim, edge moldings, and suspension members. Comply with manufacturer’s instructions for cleaning and touch up of minor finish damage. Remove and replace work that cannot be successfully cleaned and repaired to permanently eliminate evidence of damage.

END OF SECTION 09 54 36

SUSPENDED DECORATIVE GRIDS 09 54 36 - 8

[THIS PAGE INTENTIONALLY LEFT BLANK]