About this opportunity
Eagle Mountain City is requesting proposals for construction of an observatory at Walden Park under RFP EMC-FY27-05, with sealed proposals due November 5, 2026 at 12:00 PM through the State of Utah's Public Procurement Portal and anticipated award on November 18, 2026.
The scope encompasses all supplies, materials, and construction services to meet approved construction plans and building permit specifications across 15 bid schedule line items: general requirements, concrete, masonry, metals, woods and composites, thermal and moisture protection, openings, finishes, specialty work, plumbing, HVAC, electrical, earthwork, exterior improvements, and landscaping. Contractors must review the detailed specifications document, geotechnical investigation report, permit set, and approved construction plans. Work hours are 7:00 a.m. to 7:00 p.m., Monday through Saturday. The contractor assumes responsibility for locating utilities and coordinating with utility owners.
Evaluation weighs pricing at 10 percent; firm experience at 25 percent; project team experience at 25 percent; functional approach at 20 percent; technical approach at 17 percent; and introductory letter completeness at 3 percent. Proposals must not exceed 15 single-sided pages in 11- or 12-point font, organized into five tabbed sections: letter of transmittal, executive summary, detailed discussion, cost proposal, and bid form with certificates of insurance.
A bid bond of 5 percent of the maximum bid price is required with proposal submission. Upon award, the contractor must provide 100 percent performance and payment bonds and maintain general liability insurance with $1 million per occurrence and $3 million aggregate limits, commercial automobile insurance, professional liability insurance, workers' compensation, and builder's risk insurance. A one-year warranty on all materials, equipment, parts, and labor follows substantial completion. Payment is made within 30 days of the contractor's approved request, subject to up to 5 percent retainage.
Questions are due October 21, 2026 at 5:00 PM, with answers posted October 22. Melissa Yates, Purchasing Agent, is the RFP Administrator at (801) 789-6641 or Myates@EagleMountain.gov. All vendor prequalification must be completed through EagleMountain.gov/purchasing prior to contract execution.
Opportunity text
Eagle Mountain City is requesting proposals from responsible firms or individuals for construction of an observatory in Walden Park. The scope of services will include providing all supplies, materials and construction related to the site. All specifications and building requirements will need to meet the outline of the approved construction plans and building permit that is supplied with the project. The following documents will be required with bidding documents and/or with a contract award. ** Bid Bond for 5% of the total project required with the bidding documents** **Insurance verification with bid, Certificate of Insurance at contract signing** ** 100% Performance Bond will be posted by the approved contractor at contract signing ** ** 100% Payment Bond will be posted by the approved contractor at contract signing ** Any bid / proposal received after the scheduled closing time for receipt of bids will not be considered. OPENING OF BIDS / PROPOSALS: Bids / proposals will be opened on or around the closing date and time. Results will be posted after bids / proposals have been evaluated. Vendors who submit a bid / proposal will be notified of the results via email. The email will include a spreadsheet of all vendors, and the amounts of the bids / proposals submitted for the project. Please include the name and email address of your contact person in the cover letter so we can send the notification of bid results. Bids/ proposals will also be posted on Eaglemountaincity.com/purchasing. Once a vendor is chosen for the awarded contract all vendors will be notified of the vendor who will be awarded the contract. The chosen vendor will submit the remaining required insurance, bonds, and other required documentation with a signed contract.