About this opportunity
Brevard County, Florida has advanced Bid No. B-2-26-28 to award for removal and replacement of the modified bitumen roof system at the Agriculture Center, 3695 Lake Drive, Cocoa, Florida, after bids opened June 26, 2026 at 11:00 a.m., and a Notice of Award was posted July 22, 2026. The source names no set-aside, preference program, or sole-source intent.
Nailed It Roofing Solutions, LLC of Vero Beach, Florida was selected as intended awardee at $259,300, the lowest of nine bids ranging from $259,300 to $475,500. The next lowest bids were Porter Roofing Contractors, Inc. at $300,000 and MGM Contracting, Inc. at $316,260. Purchasing Manager Mary Bowers approved the award recommendation. The protest period ran July 14 through July 21, 2026 at 5:00 p.m., and bid tabulations are posted to VendorLink at www.myvendorlink.com.
The scope requires the contractor to furnish all labor, materials, tools, equipment, and transportation for removing the existing roof system and installing all associated roofing materials and hardware. The project manual was prepared by PBA Design Group, Inc. for Brevard County Government and UF/Brevard County Extension Services. Revised drawings posted June 19, 2026 supersede prior versions. Contractors may propose substitutions through Attachment C, which the County states are submitted at the contractor's risk, and any substitution deemed a material deviation results in mandatory bid rejection.
Performance conditions are substantial. The work is a single prime contract, bid lump sum, and performed during daytime hours from 7 a.m. to 5 p.m. on weekdays, with exceptions requiring seven days' advance written request. A full-time superintendent who is a direct employee of the prime contractor must be on site whenever materials are delivered or work is performed. The contractor must also engage a full-time Quality Control Manager, submit a quality control plan within ten days of Notice to Proceed, and submit a construction schedule within 14 days. Specialty work, including concrete pavement, asphalt pavement, landscaping and irrigation, coatings and sealants, and concrete and masonry, must be subcontracted to firms with at least five years of specialization experience. Metal detection sweeps are required at project end by independent specialists. Weather delay extensions are limited to daily rainfall exceeding 0.1 inches, wind speeds exceeding 25 mph, or morning temperatures of 50 degrees and falling, and only when critical path activities are delayed on a project that was on schedule.
Addendum 1 was posted May 27, 2026, and Addendum 2 was posted June 19, 2026. The draft contract is designated Attachment D.
Opportunity text
The project consists of furnishing all labor, materials, tools, equipment, and transportation necessary for the removal and replacement of the modified bitumen roof system, including all associated roofing materials and hardware, at the Agriculture Center located at 3695 Lake Drive, Cocoa, Florida 32926.