Z1DA--Replace Roofs and Repair Facades Phase 1 at Northport VA Medical Center 79 Middleville RD, Northport, NY 11768
Closed Solicitation Posted
- Solicitation number
- 36C24225B0015
- Agency
-
Veterans Integrated Service Network 2
Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238160 Roofing Contractors
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Veterans Affairs Veterans Health Administration (VA) is seeking a roofing and facade renovation contractor for Buildings 61 and 62 at the Northport VA Medical Center located in Northport, New York. The project involves comprehensive roof replacement, facade repairs, and addressing potential hazardous materials like asbestos and lead-based paint. Contractors must be certified Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with NAICS code 238160 and registered in SAM.gov. The solicitation requires a mandatory pre-bid site visit on April 10, 2025, at 10:00 AM, with sealed bids due electronically by May 6, 2025, at 10:00 AM ET. Award will be made to the lowest-priced, responsive, responsible SDVOSB bidder, with evaluation based on technical specifications, compliance with subcontracting limitations, and meeting minority and female participation goals.
The contract is not set aside for a specific small business program beyond the SDVOSB requirement, and no incumbent contractors are mentioned in the documentation. The total project magnitude is estimated between $5,000,000 and $10,000,000, with a 400-calendar day period of performance from the Notice to Proceed date. The work will be performed at 79 Middleville Road in Northport, NY, and includes general construction, alterations, tuck pointing, stonework, roof replacement, storm drainage improvements, and potential asbestos abatement. The project requires 30-year warranties on asphalt shingle and EPDM roofing, with comprehensive technical specifications detailing precise renovation requirements. Work will be phased, initially focusing on the streetside of Buildings 61 and 62, with contractors expected to verify existing conditions and follow strict safety and environmental control protocols.
Notice text
2 versions
Update #2 · Latest ·
Replace Roofs and Repair Facades Phase 1; Solicitation No. 36C24225B0015; Project No. 632-16-103 at Northport VA Medical Center, 79 Middleville Rd, Northport, NY 11768.
The purpose of this amendment is to provide responses to Request for Information (RFI) and Questions, RFIs and Questions responses are hereby included. Please see below for detailed information.
Request for Information/Question Responses
1. Based on the proposed phasing plan, it shows that we ll be required to proceed with the front of Buildings 61 & 62 for phase 1, and the back of Buildings 61 & 62 or phase 2.
Is there any way we would be able work on both the front & back of Buildings 61 & 62 concurrently?
Response:
As per contract documents, the Phase 1 is a streetside of the buildings 61&62 and the Phase 2 is a courtyard of the building 61&62. It was concerns of the extent of site disturbance, and if the GC could complete both sides concurrently which requires multiple dumpsters and staging on both sides of the building (due to the tunnels between buildings limiting the ease of access from one side of the building to the other). The construction work will proceed in accordance with the terms outlined in the existing contract. The GC will provide construction phasing during project submittal phase for approval.
If we cannot work on the entirety of both buildings at once, would it be acceptable for phase 1 to completely finish Building 61, and then move to Building 62 for phase 2?
Response:
See response above.
2. Can you please provide the most recent asbestos / lead report?
Response:
See attached Environmental Report.
3. Can the Superintendent fulfill the Quality Control Manager (QCM) role?
Response:
The project superintendent will be held responsible for the equality of work. The QCM or CQC System manager should be on the site at all times during construction and is employed by the GC. It shall be provided alternate to serve in the event of the SDQC manager s absence. The requirements for alternate the same as for CQC Manager.
4. Is the QCM required to be onsite full-time, or can they make site visits as required for inspections?
Response:
See response above.
5. Can the Superintendent fulfill the Site Safety & Health Officer (SSHO) role?
Response:
The Competent person to fulfill the Site Safety & Health Officer (SSHO) role can have collateral duties as the superintendent.
6. What is the actual linear footage for the repointing?
Response:
Per the G002 General Notes F & G Contactor to verify all site dimensions and existing conditions prior to work occurring. Contractors shall report any discrepancies to the govt prior to starting construction. Commencement of the work by the contractor shall imply his acceptance of all existing conditions.
contractor shall verify all conditions and dimensions at the job site prior to the star of construction
7. What is the actual linear footage for the rebricking?
Response:
Per the G002 General Notes F & G
Contactor to verify all site dimensions and existing conditions prior to work occurring. Contractors shall report any discrepancies to the govt prior to starting construction. Commencement of the work by the contractor shall imply his acceptance of all existing conditions.
contractor shall verify all conditions and dimensions at the job site prior to the star of construction
8. What is the actual linear footage for the lintels?
Response:
Per the G002 General Notes F & G
Contactor to verify all site dimensions and existing conditions prior to work occurring. Contractors shall report any discrepancies to the govt prior to starting construction. Commencement of the work by the contractor shall imply his acceptance of all existing conditions.
contractor shall verify all conditions and dimensions at the job site prior to the star of construction
Lintel quantities and approx. sizes are notes on the Hazardous Materials Lead sheets (HL100 thru HL107)
9. What is the actual linear footage of the windowsills?
Response:
Per the G002 General Notes F & G
Contactor to verify all site dimensions and existing conditions prior to work occurring. Contractors shall report any discrepancies to the govt prior to starting construction. Commencement of the work by the contractor shall imply his acceptance of all existing conditions.
contractor shall verify all conditions and dimensions at the job site prior to the star of construction
10. Does this scope require pipe scaffolding for safety, or will a lift be acceptable in some areas?
Response:
Per specification, the scaffolding shall be as approved by a professional engineer contracted by the GC. Therefore, the GC s engineer would need to review and advise. Please note Scaffolding requirements are further noted within spec section 01 35 26 as well as within G002 demo notes U , V , & AK
11. Please confirm if the replacement roof will require a 10, 20, or 30 year warranty.
Response:
All warranty requirements are as noted within the specifications.
Per spec section 07 31 13 ASPHALT SHINGLES section 1.7 warranty notes a 30 year warranty as well as wind & algae warranty requirements.
Per spec section 07 53 23 EPDM Roofing section 1.10 warranty notes a 30 year warranty.
12. Sign-in Sheet Request.
Response:
No Further Questions.
Update #1 ·
SEE ATTACHMENTS.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Z1DA--Replace Roofs and Repair Facades Phase 1 at Northport VA Medical Center 79 Middleville RD, Northport, NY 11768 | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Y1DA--replace roofs and repair facades building 6 and 7 at the northport VA medical center project number: 632-23-112 | Veterans Integrated Service Network 2 | No set-aside | |
| Z1DA--NRM-CONST | 632-23-112 Replace Roofs and Repair Facades Buildings 6 and 7 | FY27 NRM | Veterans Integrated Service Network 2 | No set-aside | |
| Building 13 Stair and Roof Replacement at Castle Point VAMC | Veterans Integrated Service Network 2 | Service-Disabled Veteran-Owned Small Business | |
| Z2DA--657-27-103JB, FCA Replace Building 51 Roof, JB | Veterans Integrated Service Network 15 | Service-Disabled Veteran-Owned Small Business | |
| F108--620-26-206 Asbestos Abatement | Veterans Integrated Service Network 2 | Service-Disabled Veteran-Owned Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity