Y1DA--657-26-109JB, Upgrade Master Boiler Program Logic Controls l STL
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 36C25526R0051
- Agency
- Veterans Integrated Service Network 15 Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Points of contact
-
- Kevin A Mahoney kevin.mahoney3@va.gov (913) 684-0141
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 15 is procuring construction services to upgrade the boiler control system at the Jefferson Barracks VA Energy Plant. The scope includes replacing outdated hardware and software across the Plant Master Panel, three boiler PLCs, and the SCADA system with modern, supported platforms such as CompactLogix 5000 Series PLCs, PanelView Plus 7 Graphic Terminals, a Windows 11 PC, and iFIX v2024 SCADA software. Key requirements include developing and implementing a phased cutover plan to minimize system downtime, providing updated electrical drawings, and establishing communication between all upgraded components. The prime contractor must perform at least 15 percent of the general construction labor. Proposals will be evaluated using the Best Value Lowest Price Technically Acceptable Source Selection Process. The solicitation package will be available for download by December 30, 2025, and proposals are due by January 28, 2026.
This procurement is set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSB), and interested contractors must be registered in both SAM and the Veteran Small Business Certification (VetCert) database. The estimated project cost ranges between $250,000 and $500,000, with a performance period of 180 calendar days. The NAICS code is 238220 (Plumbing, Heating, and Air-Conditioning Contractors), and the PSC category is Y1DA (Construction of Hospitals and Infirmaries). One site visit is scheduled for interested contractors to review the existing systems at the facility. Contractors should prepare their proposals to address system reliability, safety improvements, integration capabilities, and the detailed technical requirements outlined in the statement of work for each component of the upgrade project.
Notice text
657-26-109JB Upgrade Master Boiler Program Logic Controls
STATEMENT OF WORK (SOW)
for CONSTRUCTION PROJECT:
This contract is for CONSTRUCTION services to upgrade the boiler control system at the Jefferson Barracks VA Energy Plant.
Description: The existing boiler control system relies on outdated hardware and software that are no longer supported, increasing the risk of failure and limiting maintainability. This project upgrades the Plant Master Panel, three boiler PLCs, and SCADA system to modern, supported platforms, improving system reliability, safety, and integration. The following outlines the SOW for the different components:
Plant Master Panel SOW:
Replace the existing PLC with a CompactLogix 5000 Series PLC and 5069 I/O modules.
Replace existing PanelView HMI with a PanelView Plus 7 Graphic Terminal.
Provide updated electrical drawings and integrate all new components into the existing panel.
Program the new PLC and establish communication with each boiler, auxiliary equipment, and the SCADA system.
Boiler PLC SOW: For each of the three boilers:
Remove the existing obsolete PLC and replace it with a CompactLogix 5000 Series PLC and 5069 I/O modules.
Replace the existing PanelView HMI with a PanelView Plus 7 Graphic Terminal.
Provide updated electrical drawings and integrate all new components into the existing panel.
Program the new PLC and establish communication with each boiler, auxiliary equipment, and the SCADA system.
Upgrade Obsolete O2 PCC-III-Z000 to Latest PCC-IV-Z000 Control
SCADA system SOW:
Replace the existing Windows 7-based Dell PC with a modern PC operating on Windows 11.
Replace the obsolete printer with a new Canon All-in-One Inkjet printer.
Replace the obsolete Ethernet switch with a new SonicWall switch.
Install and license iFIX v2024 SCADA software.
Maintain use of existing Ethernet cable runs between the Master Panel, Boiler Panels, Switch, and SCADA system.
Migration Cutover SOW: A phased cutover plan shall be developed and implemented to minimize system downtime. This plan is designed to avoid downtime during SCADA migration, limit downtime to one boiler at a time during boiler PLC upgrades and restrict full
system downtime to the Plant Master Panel migration only. The plan shall include the following steps:
Install the new SCADA PC and run iFIX 2024 in parallel with the existing system.
Download PLC programs to new PLCs prior to cutover.
Simulate the new SCADA application on iFIX 2024.
Coordinate and execute cutover for each boiler PLC individually.
Migrate hardware and monitor performance.
Allow time between boiler migrations to validate functionality.
Repeat for all three boiler systems.
Schedule and execute cutover for the Plant Master Panel.
Migrate hardware and monitor system performance.
The contractor shall furnish all labor, supervision, materials, products, tools, equipment, temporary structures and any other resources necessary to complete the work as described in this SOW, whether specifically listed or implied by the scope. The contractor shall provide a high level of quality and workmanship. The contractor is responsible for the removal and disposal of any project-related equipment and materials.
Note: Contractor to abide by all work & requirements set in the final release for construction project specifications.
Project shall conform to all Records Management and Privacy Language.
The period of performance for this project will be 180 calendar days after NTP issue date.
END OF STATEMENT OF WORK
Pursuant to 38 USC 8127(d) and in accordance with Public Law 109-461, the Veterans Benefits, Healthcare and Information Technology Act of 2006, this procurement is set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) only.
The project construction cost range is between $250,000 and $500,000. The North American Industry Classification Code (NAICS) for this procurement is 238220 with a small business size standard $19.0 million. The duration of the project is estimated to be 180 calendar days after receipt of notice to proceed. This completion period includes final inspection and clean-up. Award will be made utilizing the Best Value Lowest Price Technically Acceptable Source Selection Process in accordance with Federal Acquisition Regulation Part 15. The successful prime contractor must perform no less than 15 percent of the General Construction labor for NAICS Code 238220. Proposal submission instructions will be included in the solicitation package. The government plans to award without discussions but reserves the right to hold discussions if necessary. The offeror is responsible to monitor and download any amendments from the SAM Contract Opportunities website, which may be issued to this pre-solicitation.
In accordance with FAR 52.204-7, registration in SAM is required and in accordance with FAR 2.101, prospective contractors must be registered in SAM (System of Award Management) under the applicable NAICS. Additionally, in accordance with the Veterans Affairs Acquisition Regulation (VAAR) 802.101, VIP Registration prospective (SDVOSB) and (VOSB) contractors must be registered in the VIP database which is now the Veteran Small Business Certification (VetCert) under the applicable NAICS. Firms may obtain SAM- information at http://www.SAM.gov and VIP information at Veteran Small Business Certification (sba.gov). The solicitation package and drawings should be available for download on or before December 30, 2025 and the proposal due date will be on or about January 28,2026. An organized site visit will be scheduled, and the information will be made available at time of solicitation issuance. Only one site visit will be scheduled and interested offerors are highly encouraged to attend. No hard copies of the solicitation or drawings will be provided; and telephone requests or questions will NOT be accepted. Please email requests or questions to maria.hoover@va.gov and kevin.mahoney3@va.gov and ensure that the subject line reads " Upgrade Master Boiler Program Logic Controls l STL, Project #657-26-109JB, Solicitation No. 36C25526R0051 .
Attachments
| File | Type | Posted |
|---|---|---|
| 36C25526R0051.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Upgrade Master Program Boiler Logic Control-657-26-109JB | Award Notice | |
| Y1DA--657-26-109JB, Upgrade Master Boiler Program Logic Controls l STL | Solicitation | |
| Y1DA--657-26-109JB, Upgrade Master Boiler Program Logic Controls l STL | Solicitation | |
| Y1DA--657-26-109JB, Upgrade Master Boiler Program Logic Controls l STL | Solicitation | |
| Upgrade Master Program Boiler Logic Control-657-26-109JB | Solicitation | |
| Y1DA--657-26-109JB, Upgrade Master Boiler Program Logic Controls l STL | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity