West Shore Lake Pontchartrain, WSLP-102 Levee Reach & I-10 West Floodwall Crossing, St. John the Baptist Parish, Louisiana
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912P823B0040
- Agency
-
ENDIST New Orleans
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- New Orleans, Louisiana 70118, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, New Orleans District is soliciting proposals for construction services for the West Shore Lake Pontchartrain Hurricane and Storm Damage Risk Reduction Project in St. John the Baptist Parish, Louisiana. Services sought include clearing and grubbing, floodwall and stop log construction, installation of metal structures, drainage features, excavation and embankment work. Bids are due by August 15, 2023 with an opening date of August 22, 2023. Evaluation will be based on technical qualifications and price with award to the responsible bidder with the lowest price.
The solicitation is unrestricted with no set-aside designation. The primary NAICS code is 237110 for water and sewer line and related structures construction while the dominant PSC code covers levee, dike, and flood control work. The project scope encompasses approximately 3.5 miles of levee reinforcement and a new floodwall crossing under Interstate 10 to be completed by 2025. The estimated value is between $25-100 million to be performed in St. John the Baptist Parish, Louisiana. Current contractors for related work include B&K Construction, SLSCO Ltd., and Dynamic Group LLC.
Notice text
8 versions
Update #8 · Latest ·
BID ABSTRACT W912P823B0040 WSLP -102
W912P823B0040 VIRTUAL BID OPENING WILL BE HELD 23 AUGUST 2023 AT 11:00 A.M.
AUDIO TELECONFERENCE BID OPENING INFORMATION:
Join from the meeting link
https://usace1.webex.com/usace1/j.php?MTID=m4055f7a555bd425ae24577c2e443d375
Join by meeting number
Meeting number (access code): 2763 810 6734
Meeting password: cKFsN4cq$33
Tap to join from a mobile device (attendees only)
+1-844-800-2712,,27638106734## (Customer Access Code) US Toll Free
+1-669-234-1177,,27638106734## (Customer Access Code) US Toll
Join by phone
+1-844-800-2712 US Toll Free
+1-669-234-1177 US Toll
Global call-in numbers | Toll-free calling restrictions
Join from a video system or application
Dial 27638106734@usace1.webex.com
You can also dial 207.182.190.20 and enter your meeting number.
Amendment 0004- Provide answers to bidders' questions. Bid opening date 22 August 2023 at 11:00 A.M. CST remain unchanged.
Amendment 0003- Extend the Bid Opening date to August 22, 2023 at 11:00 A.M. CST. All questions due no later than 8:00 a.m. Wednesday, 16 August, 2023.
Solicitation package for W912P823B0040. Questions are due no later than 13 July 2023 at 2:00 PM, CST
Plans for W912P823B0040
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Amendment 0001- Extend the Bid submission date to August 15, 2023, at 10:30AM CST.
Amendment 0002- Provide answ ers to bidders' questions. Provide revisions to plans and specifications. All questions due no later than 8:00 a.m. Monday, 7 August, 2023.
Update #7 ·
W912P823B0040 VIRTUAL BID OPENING WILL BE HELD 23 AUGUST 2023 AT 11:00 A.M.
AUDIO TELECONFERENCE BID OPENING INFORMATION:
Join from the meeting link
https://usace1.webex.com/usace1/j.php?MTID=m4055f7a555bd425ae24577c2e443d375
Join by meeting number
Meeting number (access code): 2763 810 6734
Meeting password: cKFsN4cq$33
Tap to join from a mobile device (attendees only)
+1-844-800-2712,,27638106734## (Customer Access Code) US Toll Free
+1-669-234-1177,,27638106734## (Customer Access Code) US Toll
Join by phone
+1-844-800-2712 US Toll Free
+1-669-234-1177 US Toll
Global call-in numbers | Toll-free calling restrictions
Join from a video system or application
Dial 27638106734@usace1.webex.com
You can also dial 207.182.190.20 and enter your meeting number.
Amendment 0004- Provide answers to bidders' questions. Bid opening date 22 August 2023 at 11:00 A.M. CST remain unchanged.
Amendment 0003- Extend the Bid Opening date to August 22, 2023 at 11:00 A.M. CST. All questions due no later than 8:00 a.m. Wednesday, 16 August, 2023.
Solicitation package for W912P823B0040. Questions are due no later than 13 July 2023 at 2:00 PM, CST
Plans for W912P823B0040
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Amendment 0001- Extend the Bid submission date to August 15, 2023, at 10:30AM CST.
Amendment 0002- Provide answ ers to bidders' questions. Provide revisions to plans and specifications. All questions due no later than 8:00 a.m. Monday, 7 August, 2023.
Update #6 ·
Amendment 0004- Provide answers to bidders' questions. Bid opening date 22 August 2023 at 11:00 A.M. CST remain unchanged.
Amendment 0003- Extend the Bid Opening date to August 22, 2023 at 11:00 A.M. CST. All questions due no later than 8:00 a.m. Wednesday, 16 August, 2023.
Solicitation package for W912P823B0040. Questions are due no later than 13 July 2023 at 2:00 PM, CST
Plans for W912P823B0040
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Amendment 0001- Extend the Bid submission date to August 15, 2023, at 10:30AM CST.
Amendment 0002- Provide answ ers to bidders' questions. Provide revisions to plans and specifications. All questions due no later than 8:00 a.m. Monday, 7 August, 2023.
Update #5 ·
Amendment 0003- Extend the Bid Opening date to August 22, 2023 at 11:00 A.M. CST. All questions due no later than 8:00 a.m. Wednesday, 16 August, 2023.
Solicitation package for W912P823B0040. Questions are due no later than 13 July 2023 at 2:00 PM, CST
Plans for W912P823B0040
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Amendment 0001- Extend the Bid submission date to August 15, 2023, at 10:30AM CST.
Amendment 0002- Provide answ ers to bidders' questions. Provide revisions to plans and specifications. All questions due no later than 8:00 a.m. Monday, 7 August, 2023.
Update #4 ·
Solicitation package for W912P823B0040. Questions are due no later than 13 July 2023 at 2:00 PM, CST
Plans for W912P823B0040
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Amendment 0001- Extend the Bid submission date to August 15, 2023, at 10:30AM CST.
Amendment 0002- Provide answ ers to bidders' questions. Provide revisions to plans and specifications. All questions due no later than 8:00 a.m. Monday, 7 August, 2023.
Update #3 ·
Solicitation package for W912P823B0040. Questions are due no later than 13 July 2023 at 2:00 PM, CST
Plans for W912P823B0040
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Amendment 0001- Extend the Bid submission date to August 15, 2023, at 10:30AM CST.
Update #2 ·
Solicitation package for W912P823B004. Questions are due no later than 13 July 2023 at 2:00 PM, CST
PLans for W912P823B0040
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Update #1 ·
Solicitation package for W912P823B0040.. Questions are due no later than 13 July 2023 at 2:00 PM, CST
The work consists of clearing and grubbing; floodwall and stop log construction, placement of steel sheet piling, H-piling, geotextile, geogrid, grouted riprap, prestressed concrete piles; installation of metal ladders, stairs, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction, slide gates, slide gates and hoist, precast concrete bridge, excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill, electrical work, and other related incidental work.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| West Shore Lake Pontchartrain, WSLP-102 Levee Reach & I-10 West Floodwall Crossing, St. John the Baptist Parish, Louisiana | Award Notice | |
| This notice | Solicitation | |
| West Shore Lake Pontchartrain, WSLP-102 Levee Reach & I-10 West Floodwall Crossing, St. John the Baptist Parish, Louisiana | Pre-Solicitation |
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity