About this opportunity

The Department of the Navy Naval Sea Systems Command (NAVSEA) is seeking a small business contractor to provide Waterfront and Alteration Installation Team (AIT) services in support of Maritime Electronic Warfare (EW) Systems. The solicitation requires comprehensive support for modernization, installation, and technical assistance for Electronic Warfare, Electro-Optical, and Electronic Attack systems on U.S. Navy and Coast Guard vessels. Contractor responsibilities include providing on-site representatives, technical support, industrial planning, logistics support, and AIT services at multiple U.S. and overseas locations. The evaluation criteria will focus on technical approach, management approach, personnel approach, past performance, and cost/price. Key proposal submission deadlines include a question submission deadline of June 7, 2024, and a proposal due date of July 12, 2024 at 2:00 PM local time.

The contract is designated as a total small business set-aside under NAICS code 336611 (Ship Building and Repairing) with a contract structure including a base year and four one-year option periods. The performance will occur at various shipyard facilities, naval stations, and potentially in different geographic combatant command areas of responsibility. Pricing will be structured with fixed-price labor contract line items (CLINs), cost-reimbursable other direct cost (ODC) CLINs, and surge labor and ODC CLINs. Contractors must be prepared to manage contract resources, coordinate functional areas, and provide necessary labor, materials, tools, and resources to meet the Statement of Work requirements. The solicitation emphasizes system operability verification testing, maritime EW system installation, and related hull, structural, mechanical, and electrical support services.

Notice text

6 versions

Update #6 · Latest ·

AMENDMENT 0005:

The reason for this amendment is to update the following Section L paragraphs:
1.) Proposal submission POCs under Section L.2.2.
2.) Page limitations for Technical Approach under Section L.3.0.
All other terms and conditions remain unchanged.

AMENDMENT 0004:

The reason for this amendment is to:
1.) Address vendor quetions.
2.) Update Technical Scenario 1 of Attachment 16.
3.) Extend the closing date to 12 July 2024.
All other terms and conditions remain unchanged.

AMENDMENT 0003:

The reason for this amendment is to:

1.) Address vendor questions.

2.) Update SOW para. 3.4.1 and SOW para. 6.1.3 as specified in vendor question responses.

3.) Add a POC in Section L.2.2 and remove reference to retrieval of LCU Draw ings in L.3.1.1.2 as they w ere added as Attachment 002a in Amendment 0002.

4.) Update Attachments 13 and 15 as specified in vendor question responses.

5.) Replace 252.204-7012 w ith 252.204-7012 (DEVIATION 2024-O0013). All other terms and conditions remain unchanged

AMENDMENT 0002:

The reason for this amendment is to update the following:
1. Address vendor questions.
2. Update Attachments 005, 006, and 013.
3. Add Attachment 002a and remove Attachment 002 note.
4. Update Statement of Work para. 7.0.
5. Update Section L para. L.2.3.5 and L.3.0.
All other terms and conditions remain unchanged.

AMENDMENT 0001:

The reason for this amendment is to:
1. Extend the due date for receipt of questions to 07 June 2024 in clause L-215-H007.
2. Extend the RFP Closing Date to 28 June 2024. 

3. Upload the following attachments in Section J: Attachment 005, Attachment 006, Attachment 013, Attachment 015, Attachment 016.
4. Address vendor questions.
5. Update various SOW and Section L paragraphs.
6. Add Attachment 02 note in Section J regarding LCU Draw ings.
7. Add Wage Determination 2015-5535 REV 22 (Attachment 017).
All other terms and conditions remain unchanged.

SOLICITATION

Update #5 ·

AMENDMENT 0004:

The reason for this amendment is to:
1.) Address vendor quetions.
2.) Update Technical Scenario 1 of Attachment 16.
3.) Extend the closing date to 12 July 2024.
All other terms and conditions remain unchanged.

AMENDMENT 0003:

The reason for this amendment is to:

1.) Address vendor questions.

2.) Update SOW para. 3.4.1 and SOW para. 6.1.3 as specified in vendor question responses.

3.) Add a POC in Section L.2.2 and remove reference to retrieval of LCU Draw ings in L.3.1.1.2 as they w ere added as Attachment 002a in Amendment 0002.

4.) Update Attachments 13 and 15 as specified in vendor question responses.

5.) Replace 252.204-7012 w ith 252.204-7012 (DEVIATION 2024-O0013). All other terms and conditions remain unchanged

AMENDMENT 0002:

The reason for this amendment is to update the following:
1. Address vendor questions.
2. Update Attachments 005, 006, and 013.
3. Add Attachment 002a and remove Attachment 002 note.
4. Update Statement of Work para. 7.0.
5. Update Section L para. L.2.3.5 and L.3.0.
All other terms and conditions remain unchanged.

AMENDMENT 0001:

The reason for this amendment is to:
1. Extend the due date for receipt of questions to 07 June 2024 in clause L-215-H007.
2. Extend the RFP Closing Date to 28 June 2024. 

3. Upload the following attachments in Section J: Attachment 005, Attachment 006, Attachment 013, Attachment 015, Attachment 016.
4. Address vendor questions.
5. Update various SOW and Section L paragraphs.
6. Add Attachment 02 note in Section J regarding LCU Draw ings.
7. Add Wage Determination 2015-5535 REV 22 (Attachment 017).
All other terms and conditions remain unchanged.

SOLICITATION

Update #4 ·

AMENDMENT 0003:

The reason for this amendment is to:

1.) Address vendor questions.

2.) Update SOW para. 3.4.1 and SOW para. 6.1.3 as specified in vendor question responses.

3.) Add a POC in Section L.2.2 and remove reference to retrieval of LCU Draw ings in L.3.1.1.2 as they w ere added as Attachment 002a in Amendment 0002.

4.) Update Attachments 13 and 15 as specified in vendor question responses.

5.) Replace 252.204-7012 w ith 252.204-7012 (DEVIATION 2024-O0013). All other terms and conditions remain unchanged

AMENDMENT 0002:

The reason for this amendment is to update the following:
1. Address vendor questions.
2. Update Attachments 005, 006, and 013.
3. Add Attachment 002a and remove Attachment 002 note.
4. Update Statement of Work para. 7.0.
5. Update Section L para. L.2.3.5 and L.3.0.
All other terms and conditions remain unchanged.

AMENDMENT 0001:

The reason for this amendment is to:
1. Extend the due date for receipt of questions to 07 June 2024 in clause L-215-H007.
2. Extend the RFP Closing Date to 28 June 2024. 

3. Upload the following attachments in Section J: Attachment 005, Attachment 006, Attachment 013, Attachment 015, Attachment 016.
4. Address vendor questions.
5. Update various SOW and Section L paragraphs.
6. Add Attachment 02 note in Section J regarding LCU Draw ings.
7. Add Wage Determination 2015-5535 REV 22 (Attachment 017).
All other terms and conditions remain unchanged.

SOLICITATION

Update #3 ·

AMENDMENT 0002:

The reason for this amendment is to update the following:
1. Address vendor questions.
2. Update Attachments 005, 006, and 013.
3. Add Attachment 002a and remove Attachment 002 note.
4. Update Statement of Work para. 7.0.
5. Update Section L para. L.2.3.5 and L.3.0.
All other terms and conditions remain unchanged.

AMENDMENT 0001:

The reason for this amendment is to:
1. Extend the due date for receipt of questions to 07 June 2024 in clause L-215-H007.
2. Extend the RFP Closing Date to 28 June 2024. 

3. Upload the following attachments in Section J: Attachment 005, Attachment 006, Attachment 013, Attachment 015, Attachment 016.
4. Address vendor questions.
5. Update various SOW and Section L paragraphs.
6. Add Attachment 02 note in Section J regarding LCU Draw ings.
7. Add Wage Determination 2015-5535 REV 22 (Attachment 017).
All other terms and conditions remain unchanged.

SOLICITATION

Update #2 ·

AMENDMENT 0001:

The reason for this amendment is to:
1. Extend the due date for receipt of questions to 07 June 2024 in clause L-215-H007.
2. Extend the RFP Closing Date to 28 June 2024. 

3. Upload the following attachments in Section J: Attachment 005, Attachment 006, Attachment 013, Attachment 015, Attachment 016.
4. Address vendor questions.
5. Update various SOW and Section L paragraphs.
6. Add Attachment 02 note in Section J regarding LCU Draw ings.
7. Add Wage Determination 2015-5535 REV 22 (Attachment 017).
All other terms and conditions remain unchanged.

SOLICITATION

Update #1 ·

SOLICITATION

Files

File Type Posted
24RWM44_sol_0005.pdf PDF
24RWM44_sol_0005_att1.pdf PDF
24RWM44_SOL_0004.zip ZIP file
24RWM44_SOL_0003.zip ZIP file
24RWM44_SOL_0002.pdf PDF
24RWM44_SOL_0001.pdf PDF
24RWM44_SOL.pdf PDF

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Waterfront and Alternation Installation Team (AIT) services in support of Maritime Electronic Warfare (EW) Systems Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Imaging and Electronic Warfare Systems Special Support Equipment (SSE) Unit Fabrication and Maintenance NAICS 334290 Naval Sea Systems Command No set-aside
NSLC IT Support Services Sources Sought Mechanicsburg, Pennsylvania 17055, United States · NAICS 541330 Naval Sea Systems Command No set-aside
Cap NAICS 334511 Naval Supply Systems Command No set-aside
Towed array subasem NAICS 334290 Naval Supply Systems Command No set-aside
MIW and SMCM Engineering Support - SEAPORT NAICS 541330 Naval Sea Systems Command Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors