About this opportunity

The U.S. Army Corps of Engineers, Portland District, seeks the purchase and installation of blade seals for Powerhouse II Main Unit Kaplan turbines at Bonneville Lock and Dam, with proposals due September 25 and anticipated contract award on or about September 30.

Place of performance is Bonneville Dam, Cascade Locks, Oregon. The contractor will design and fabricate one-piece solid seals for five-bladed Kaplan turbine runners on Main Unit 16, with a second set for Unit 17 offered as optional. The seals must have redundant sealing edges, be field-molded solid at site, and contain no glue, cold bonding, hot bonding, adhesive, or epoxy. The Government will provide drawings and dimensions; the contractor furnishes all supervision, labor, equipment, and materials except those Government-identified items.

The Government requests expedited fabrication, delivery, and installation at the earliest practicable opportunity following award. Final seal design and dimensions will be finalized through discussions between the awarded contractor and Bonneville Dam engineering immediately after contract award. Contractor personnel performing on-site installation work must be familiar with hydro generator powerhouses and Kaplan blade seal installation procedures. While not all personnel must be fluent in English, at least one representative must be fluent in both English and any non-English language spoken by other workers to facilitate safety training translation. All individuals will receive mandatory Affected Persons training post-award for compliance with the hazardous energy control program; upon completion, they receive a personal lock and identifying nametag for facility access at Bonneville Dam.

NAICS code is 339991 (Gasket, Packing, and Sealing Device Manufacturing); PSC code is 5330 (Packing and Gasket Materials). An RFI Log and Reference Drawings have been added to attachments as of September 26.

Notice text

2 versions

Update #2 · Latest ·

**Updated to add the RFI Log and Reference Drawings. See the Attachments section for the newly added documents.**

GENERAL STATEMENT

US Army Corps of Engineers, Portland District, Bonneville Lock and Dam are soliciting for the purchase and installation of blade seals for Powerhouse II Main Unit Kaplan turbines. The turbine runners are 5-bladed vertical axis Kaplans. The contractor will supply and install turbine blade seals on the Kaplan turbine of Main Unit 16. The second set of blade seals for Unit 17 is optional, as defined in this Performance Work Statement. The contractor will provide seals based on drawings and dimensions provided by the Government. The Government requests expedited fabrication, delivery, and installation at the earliest practicable opportunity following contract award. The Government anticipates contract award on or about 9/30/2026. This date is for planning purposes only and does not alter the Contractors performance obligations, which begin upon contract award.

PERFORMANCE STANDARDS AND GUIDELINE REQUIREMENTS

The Contractor shall furnish all supervision, labor, equipment, materials necessary to perform the work required under these specifications except for those items specifically identified as government provided. The Contractor shall place all trash and litter pickup in dumpsters located on the project. Telephone service will not be provided. The Contractor will furnish, deliver, and install newly manufactured Kaplan blade seals and all accessories at Bonneville Lock and Dam as detailed in this PWS. Contractor shall also provide required documentation as stated in section 5.1.3 of this PWS. Description of Supply and Service Supply Turbine Blade Seals. The Contractor is responsible for designing and fabricating one-piece solid seals for five-bladed Kaplan turbine runners. The seals are required to have redundant sealing edges, no split, and field-molded solid at site. No gluing, cold bonding, or hotbonding using additional material are permitted. The seals will need to be bonded without any external additional material (adhesive or elastomer) to ensure identical material properties across the entire seal and geometric continuity of the seal edges. The nominal packing size will have an OD of 45.252-inch and an ID of 43.993-inch. The blade seals are original to the 1980s installation and final seal dimensions are to be verified prior to delivery and installation. Approximate dimensions are provided herein for pricing purposes only. The seal housing (turbine hub bore and turbine blade trunnion sleeve) dimensions will be confirmed prior to the supplier coming to site for installation. For compatibility with material selection, the outer surface the seal will be against is cast steel. The inner surface of the blade seal housing is stainless steel. The seals shall be designed to fit within the existing packing box dimensions as shown on the supplied reference drawings:

Drawing Description                              Number

330 - 5 X A Runner Hub Assy Sect        4296-JL-1

Follower (Seal Ring)                              6532-T-2

Runner Hub Assy Plan                           4296-JO-1

Runner Hub Assy Plan                           4296-JM-1

Blade                                                      6530-CR-1

Runner Hub                                            6529-BB-1

** See solicitation document for more details **

Update #1 ·

GENERAL STATEMENT

US Army Corps of Engineers, Portland District, Bonneville Lock and Dam are soliciting for the purchase and installation of blade seals for Powerhouse II Main Unit Kaplan turbines. The turbine runners are 5-bladed vertical axis Kaplans. The contractor will supply and install turbine blade seals on the Kaplan turbine of Main Unit 16. The second set of blade seals for Unit 17 is optional, as defined in this Performance Work Statement. The contractor will provide seals based on drawings and dimensions provided by the Government. The Government requests expedited fabrication, delivery, and installation at the earliest practicable opportunity following contract award. The Government anticipates contract award on or about 9/30/2026. This date is for planning purposes only and does not alter the Contractors performance obligations, which begin upon contract award.

PERFORMANCE STANDARDS AND GUIDELINE REQUIREMENTS

The Contractor shall furnish all supervision, labor, equipment, materials necessary to perform the work required under these specifications except for those items specifically identified as government provided. The Contractor shall place all trash and litter pickup in dumpsters located on the project. Telephone service will not be provided. The Contractor will furnish, deliver, and install newly manufactured Kaplan blade seals and all accessories at Bonneville Lock and Dam as detailed in this PWS. Contractor shall also provide required documentation as stated in section 5.1.3 of this PWS. Description of Supply and Service Supply Turbine Blade Seals. The Contractor is responsible for designing and fabricating one-piece solid seals for five-bladed Kaplan turbine runners. The seals are required to have redundant sealing edges, no split, and field-molded solid at site. No gluing, cold bonding, or hotbonding using additional material are permitted. The seals will need to be bonded without any external additional material (adhesive or elastomer) to ensure identical material properties across the entire seal and geometric continuity of the seal edges. The nominal packing size will have an OD of 45.252-inch and an ID of 43.993-inch. The blade seals are original to the 1980s installation and final seal dimensions are to be verified prior to delivery and installation. Approximate dimensions are provided herein for pricing purposes only. The seal housing (turbine hub bore and turbine blade trunnion sleeve) dimensions will be confirmed prior to the supplier coming to site for installation. For compatibility with material selection, the outer surface the seal will be against is cast steel. The inner surface of the blade seal housing is stainless steel. The seals shall be designed to fit within the existing packing box dimensions as shown on the supplied reference drawings:

Drawing Description                              Number

330 - 5 X A Runner Hub Assy Sect        4296-JL-1

Follower (Seal Ring)                              6532-T-2

Runner Hub Assy Plan                           4296-JO-1

Runner Hub Assy Plan                           4296-JM-1

Blade                                                      6530-CR-1

Runner Hub                                            6529-BB-1

** See solicitation document for more details **

Files

File Type Posted
RFI Log.xlsx XLSX spreadsheet
RFI Log.xlsx XLSX spreadsheet
Reference Drawings.pdf PDF

Similar open opportunities

Opportunity Agency Set-aside Responses due
John day DAM navigation lock tainter valve (TV) repairs TV3 and TV4 Location and Access Details. Oregon Side Physical Access, Near Rufus, OR 97050 accessible via I-84, Exit 109. Washington Side (Closest Town), Goldendale, WA 98620 approximately 20 miles north across the river. River Location, Mile 216.6 on the Columbia River, joining Sherman County, Oregon, and Klickitat County, Washington. 98628 · NAICS 237990 ENDIST Portland No set-aside
Navigation lock tainter valve (TV) repair, TV1 The Dalles Dam (Washington side), Lyle, WA 98635. 98635 · NAICS 237990 ENDIST Portland No set-aside
TDA Isolated Phase Bus and Duct Inspection The Dalles Dam in The Dalles, Oregon. Access to The Dalles Dam is from I-84 Exit 88 97058 · NAICS 541380 ENDIST Portland No set-aside
John day DAM unit 10 packing box replacement John Day Dam, Sherman County, Oregonthe John Day Dam On The Columbia River Between Sherman County, Oregon, And Klickitat County, Washington. Rufus, Oregon 97050, United States · NAICS 237990 ENDIST Portland No set-aside
Illinois River Basin, Brandon Road L and D, Joliet, Illinois, Flushing Lock and Dam Gates Fabrication NAICS 326199 ENDIST Rock Island Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors