UT FLAP 218(1) Sheep Creek Loop

Closed Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
6982AF22B000002
Agency
Federal Highway Administration Department of Transportation
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Y1LB Construction Of Highways, Roads, Streets, Bridges, And Railways
Place of performance
Manila, Utah 84046, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is for a reconstruction and improvement project located on Highway 218 in Daggett County, Utah. The Department of Transportation Federal Highway Administration seeks to widen 1.85 miles of the Sheep Creek Geologic Loop roadway and perform other upgrades such as drainage improvements, guardrail replacement, and pavement markings. Construction is anticipated to occur between March 2022 and September 2022. The anticipated advertisement is in October 2021, with a bid opening in November 2021 and award in December 2021.

There is no set-aside designation for this project. Significant work items include 4,600 cubic yards of roadway excavation, 1,050 cubic yards of unclassified borrow, 5,700 tons of roadway aggregate, 3,800 tons of asphalt concrete pavement, and 40 linear feet of an 8-foot by 4-foot reinforced concrete box culvert. The engineer's estimate for total project costs is between $2.5 million to $3.5 million. Weekday road closures will be permitted during construction with access required for local permit holders and property owners.

Notice text

THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

PROJECT DESCRIPTION:  The UT FLAP 218(1), Sheep Creek Geologic Loop Project is located on Highway 218 approximately 7 miles south of Manila, UT in Northeast Utah. The project crosses through private and Ashley National Forest (USFS) Lands, providing access to the Flaming Gorge-Uintas National Scenic Byway. The route is categorized as a rural recreational and scenic roadway in level terrain and is maintained by Dagget County. This project proposes reconstruction, widening, minor profile adjustments, guardrail replacement, and drainage improvements of 1.85 miles of roadway on the Sheep Creek Geologic Loop.

Major work elements include widening the roadway to a consistent width and vertical and horizontal alignment changes to correct roadway geometry and improve safety.  Construction will generally include cut slopes, embankment, aggregate base course, and paving. Improvements include clearing roadside vegetation, stabilization of shoulders, drainage improvements (including a concrete box culvert), cattleguard installation, pavement markings, and updating signing.  Select pullouts and access road intersections will also be rehabilitated or reconstructed.    

SIGNIFICANT QUANTITIES (Schedule A):

  • 20401-0000 Roadway Excavation: 4,600 CUYD
  • 20403-0000 Unclassified Borrow: 1,050 CUYD
  • 30202-2000 Roadway Aggregate, Method 2: 5,700 TON
  • 40301-0100 Asphalt Concrete Pavement, Type 1: 3,800 TON
  • 60222-1800 8 Feet Span, 4 Feet Rise Reinforced Concrete Box Culvert, Double Barrel: 40 LNFT

ENGINEER’S ESTIMATE:  Estimated total cost is $2.5M - $3.5M.

CONSTRUCTION DURATION:  Construction is anticipated between March 2022 and September 2022.

MISCELLANEOUS:

Weekday road closures to public traffic will be allowed during a large portion of the construction activities.  Access through the closure to USFS permit holders and local property owners will be required at all times.   For all other work, construction-caused delays to public traffic will be limited to a maximum of 30 minutes per passage through the project.

Perform pre-construction nesting bird survey within 7 days before vegetation removal performed prior to August 1. 

Due to weather restrictions, on-site construction typically cannot occur until March.

Seeding must take place between the dates of September 15 and November 15. 

ADDITIONAL INFORMATION FOR NOTICE

Anticipated advertisement in October 2021.

Anticipated bid opening in November 2021.

Anticipated Award in December 2021.

Anticipated Notice to Proceed in January 2022.

Anticipated Ground-Breaking Construction March 2022

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
UT FLAP 218(1) Sheep Creek Loop Award Award Notice
UT FLAP 218(1) Sheep Creek Loop Latest solicitation Solicitation
UT FLAP 218(1) Sheep Creek Loop Pre-Solicitation
UT FLAP 218(1) Sheep Creek Loop This notice Pre-Solicitation
UT FLAP 218(1) Sheep Creek Loop Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity