UT ERFO 70014(2) Santaquin Canyon Road
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 6982AF23SS0001
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Santaquin, Utah 84655, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice seeks interested contractors to repair numerous sites along the UT ERFO 70014(2) Santaquin Canyon Road that were damaged in a 2019 flood event. The Department of Transportation Federal Highway Administration intends to procure construction services including embankment construction, retaining wall construction, concrete box culvert construction, aggregate placement, and asphalt paving. Interested contractors must submit a statement of intent, certifications, bonding information, and descriptions of relevant past performance by October 18, 2022 to be considered for the set-aside. Evaluation will consider the contractor's capability to bond for a single $5 million project and experience on similar natural resource projects.
There is no set-aside designated for this procurement. Interested contractors must qualify as a small business, HUBZone, woman-owned, 8(a), veteran-owned, or service-disabled veteran-owned small business. The work is estimated between $2-5 million and will involve repairing approximately 500 cubic yards of special rock embankment, 7,000 square feet of MSE walls, 1,000 tons of roadway aggregate, 500 tons of asphalt, and 250 linear feet of reinforced concrete box culvert between May 2023 and July 2024. The anticipated solicitation date is December 2022 with an award by February 2023.
Notice text
Sources Sought Number: 6982AF23SS0001
Project Number and Name: UT ERFO 70014(2) Santaquin Canyon Road
THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
THIS NOTICE IS BEING ISSUED TO DETERMINE IF THERE IS SUFFICIENT INTEREST FROM QUALIFIED PRIME CONTRACTORS who are Small Business concerns (SBCs), HUBZone small businesses, Woman Owned Small Businesses (WOSBs), 8(a) small businesses, Service Disabled Veteran-Owned Small Businesses (SDVOSBs), or Veteran Owned Small Businesses (VOSBs) and who intend to submit a bid for this solicitation to allow for a set-aside in one of these programs MUST submit the following by e-mail to CFLAcquisitions@dot.gov for receipt by close of business (2 p.m. local Denver time) on October 18, 2022. Please put the project name in the subject line:
(1) A positive statement of your intention to submit a bid for this solicitation as a Prime Contractor;
(2) A copy of the letter from SBA stating date of HUBZone small business certification or acceptance to the 8(a) small business program. In the case of a Service Disabled Veteran Owned Small Business (SDVOSB) or a Veteran Owned Business (VOSB) concern, you must provide proof of eligibility (DD form 214 or a letter of adjudication from the Veterans Administration). This information must be provided in order to determine eligibility – DO NOT SEND COPIES OF YOUR SAM PROFILE AS CERTIFICATION;
(3) Letter from bonding agent stating your firm’s capability to bond for a single project of $5 million dollars, your firm’s aggregate bonding capacity; and
(4) Provide a list of road construction projects of equal or greater value and scope to the UT ERFO 70014(2) Santaquin Canyon Road project in which you performed (as the prime contractor) work in natural resource sensitive areas and work elements including embankment construction, retaining wall construction, concrete box culvert construction, aggregate placement, and asphalt paving. State whether your firm was the prime contractor or subcontractor on the project. DO NOT SEND INFORMATION ON PROJECTS THAT DO NOT INCLUDE THE ABOVE WORK.
The size of a small business firm includes all parents, subsidiaries, affiliates, etc. Refer to the Code of Federal Regulations 13 CFR 121.103 for information on how the SBA determines affiliation and 13 CFR 121.108 regarding the penalties for misrepresentation of size status. All firms should be certified in the All firms should be certified in the System for Award Management (SAM) located at https://www.sam.gov/
A Qualified HUBZone SBC receiving a HUBZone contract for general construction must spend at least 50% of the cost of the contract incurred for personnel on its own employees or employees of other qualified HUBZone SBCs. This requirement may be met by expending at least 50% of the cost of the contract incurred for personnel on its employees or it may subcontract at least 35% of the cost of the contract performance incurred for personnel to one or more qualified HUBZone SBCs. A qualified HUBZone SBC prime contractor may not, however, subcontract more than 50% of the cost of the contract incurred for personnel to non-qualified HUBZone SBCs.
PROJECT DESCRIPTION:
The UT ERFO 70014(2) Santaquin Canyon Road project is located in Utah County, UT within the Uinta-Wasatch-Cache National Forest, approximately 4 miles south of Santaquin, UT. This project will provide repairs to numerous sites damaged in a 2019 flood event.
SCOPE OF THE WORK:
The proposed repairs include embankment construction, retaining wall construction, concrete box culvert construction, aggregate placement, and asphalt paving. These repairs will be accomplished to restore safe passage to the travelling public. The roadway is currently closed and will remain closed until repairs are complete. Diversions of the creek will be required during box culvert and retaining wall construction.
PRINCIPAL WORK ITEMS:
Description, Unit, Est. Quantity
Special Rock Embankment, CUYD, 500
Mechanically Stabilized Earth (MSE) Wall, SQFT, 7,000
Roadway Aggregate, TON, 1,000
Asphalt, TON, 500
Reinforced Concrete Box Culvert, LNFT, 250
ANTICIPATED SCHEDULE:
The anticipated advertisement date is December 2022 with an award date of February 2023. Construction is anticipated to occur between May 2023 and July 2024.
ESTIMATED COST RANGE:
The proposed project is estimated at a cost of between $2,000,000 and $5,000,000.
Notice history
| Notice | Type | Posted |
|---|---|---|
| UT ERFO 70014(2) Santaquin Canyon | Award Notice | |
| UT ERFO 70014(2) Santaquin Canyon Road | Solicitation | |
| UT ERFO 70014(2) Santaquin Canyon Road | Pre-Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| UT NP ARCH 100(2) Bridges on Delicate Arch Road | Federal Highway Administration | No set-aside | |
| GAOA Tony Grove Dam Spillway Capacity & Seismic Mitigation, Uinta/Wasatch/Cache National Forest | Forest Service | Total Small Business | |
| GOGA 336173 - Repair Conzelman Road | National Office | No set-aside | |
| AZ BL COLO 7528(1) Burro Creek Road | Federal Highway Administration | Total Small Business | |
| BRCA 310427 Southbound Shuttle Stop | National Office | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity