Sources Sought - ERCIP Energy Resilience: PL-1 Electrical Power Supply, Buckley SFB, CO
Closed Pre-Solicitation Posted
A newer solicitation was posted. See the latest solicitation from .
- Solicitation number
- W9128F23SM028
- Agency
- ENDIST Omaha US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Y1NZ Construction Of Other Utilities
- Place of performance
- Aurora, Colorado 80011, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers is conducting market research to identify potential prime construction contractors with a minimum single job bonding capability of $10M for a project involving the replacement of end-of-life cable and switchgear, and the installation of a redundant backup commercial power feed. The project, which is expected to cost between $5M and $10M, will also involve the removal of existing high-risk single points of failure to improve mission reliability. Responses to this Sources Sought Notice are due by 2:00 p.m. CST, 25 August 2023.
Products and Services to be provided:
- Replacement of end-of-life cable and switchgear.
- Installation of a redundant backup commercial power feed.
- Removal of existing high-risk single points of failure.
- Installation of a new external ATO feed line.
- Demolition of the existing "igloo" switchgear area.
Notice text
This is a Sources Sought Notice and is for market research purposes only. THIS IS NOT A REQUEST FOR PROPOSAL, QUOTATION OR BID. NO SOLICITATION IS CURRENTLY AVAILABLE.
The U.S. Army Corps of Engineers, Omaha District is conducting market research to identify sources (Small Businesses and Other-than-Small Businesses) that have the knowledge, skills, and capability to perform the work concerning the potential project described below. The Government requests responses from POTENTIAL PRIME CONSTRUCTION CONTRACTORS WITH COMPANY BONDING CAPABILITY (SINGLE JOB) OF AT LEAST $10M. The Government will use the responses to this source sought announcement to make appropriate acquisition decisions for this project.
Responses are to be sent via email to Scott.Dwyer@usace.army.mil no later than 2:00 p.m. CST, 25 August 2023. Please include the Sources Sought Notice Identification Number in the Subject line of the email submission.
PROJECT DESCRIPTION:
This project will be executed using a design-bid-build (DBB) project delivery method, which will require the contractor to provide the government with a complete facility and warranty based on the Request for Proposal (RFP).
This project will replace end of life cable and switchgear considered to be at the end of their useful life and install a redundant, new backup commercial power feed of same capacity to the PL-1, which will improve resiliency by creating the redundancy mandated by Uptime Institute (UTI) Tier IV Standards in accordance with (IAW) Paragraph 12 of AFI 32-1062, AFSPC Supplement. This project will also eliminate several existing high risks, single points of failure, any one of which may cause lengthy risk to mission reliability. Listed below are goals for the project:
1. Install a new external ATO feed line for the Replacement and Redundant feeder line to connect to inside the PL-1 area. Will need to source work with local power utility (XCEL).
2. Replace the primary power feed line inside the PL-1 area
3. Provide new redundant power feed line to the PL-1 area.
4. Provide new ATO-Type switchgear lineups
5. Demolish the existing "igloo" switchgear area.
6. Remove the existing primary power feed line inside the PL-1 area
SUBMISSION DETAILS:
All interested, capable, qualified (under NAICS code 236220 - Commercial and Institutional Building Construction) and responsive contractors are encouraged to reply to this market survey request. Interested PRIME CONTRACTORS ONLY should submit a narrative demonstrating their experience in construction projects of similar nature as described above. Narratives shall be no longer than 10 pages. Email responses are required.
Please include the following information in your response/narrative:
• Company name, address, and point of contact, with phone number and email address
• Business size to include any official teaming arrangements as a partnership or joint venture
• Details of similar projects and state whether you were the Prime or Subcontractor
• Start and end dates of construction work
• Project references (including owner with phone number and email address)
• Project cost, terms, and complexity of job
• Information on your bonding capability - SPECIFICALLY IDENTIFY PERFORMANCE AND PAYMENT BONDS CAPACITIES
Responses will be shared with Government personnel and the project management team on a need to know basis, but otherwise will be held in strict confidence.
PLEASE NOTE: AT THIS TIME, WE ARE ONLY INTERESTED IN RESPONSES FROM COMPANIES WHO HAVE THE ABILITY TO BE PRIME CONTRACTORS WITH BONDING CAPABILITY (SINGLE JOB) OF AT LEAST $10,000,000.00.
In accordance with (IAW) FAR 36.204, the magnitude of this project is expected to be between $5,000,000 and $10,000,000.
Telephone inquiries will NOT be accepted.
Thank you for your assistance in helping complete this market research survey.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Construct Redundant Electrical Supply, Buckley SFB, CO | Solicitation | |
| Construct Redundant Electrical Supply, Buckley SFB, CO | Pre-Solicitation | |
| Sources Sought - ERCIP Energy Resilience: PL-1 Electrical Power Supply, Buckley SFB, CO | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity