Construct Redundant Electrical Supply, Buckley SFB, CO

Closed Pre-Solicitation Posted

A newer solicitation was posted. See the latest solicitation from .

Solicitation number
W9128F24R0066
Agency
ENDIST Omaha US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1JZ Construction Of Miscellaneous Buildings
Place of performance
Aurora, Colorado 80011, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Army Corps of Engineers Engineering District Omaha (ENDIST Omaha) is seeking proposals for the construction of a redundant electrical supply system at Buckley Space Force Base in Colorado. The project will involve replacing aging electrical infrastructure and installing a new backup commercial power feed to improve the resilience and reliability of the base's power supply. The solicitation will use a best-value trade-off source selection procedure, and proposals are tentatively due on August 21, 2024.

This procurement is a small business set-aside, with an estimated project value between $5 million and $10 million. The project will be executed using a design-bid-build delivery method, and the scope includes installing a new external alternate feed line, replacing the primary power feed line, providing a new redundant power feed line, and demolishing the existing "igloo" switchgear area.

Notice text

An an estimated date of 17 July, 2024, this office will issue a solicitation for Construct Redundant Electrical Supply, Buckley Space Force Base, Colorado. Colorado. This solicitation will use trade-off source selection procedures under Best-value continuum.

Proposals will be tentatively due on 21 August 2024.

No amount is to be charged for solicitation documents.

This soclitation is a SMALL BUSINESS SET-ASIDE.

This project will be executed using a design-bid-build (DBB) project delivery method.

Estimate of the magnitude of this project is between $5M - $10M.

PROJECT DESCRIPTION: This project will replace end of life cable and switchgear considered to be at the end of their useful life and install a redundant, new backup commercial power feed of same capacity to the PL-1, which will improve resiliency by creating the redundancy mandated by Uptime Institute (UTI) Tier IV Standards in accordance with (IAW) Paragraph 12 of AFI 32-062, AFSPC Supplement. This project will also eliminate several existing high risks, single points of failure, any one of which may cause lengthy risk to mission reliability. Listed below are goals for the project:

  1. Install a new external ATO feed line for the Replacement and Redundant feeder line to connect to inside the PL-1 area. Will need to source work with local power utility (XCEL).
  2. Replace the primary power feed line inside the PL-1 area
  3. Provide new redundant power feed line to the PL-1 area.
  4. Provide new ATO-Type switchgear lineups
  5. Demolish the existing "igloo" switchgear area.
  6. Remove the existing primary power feed line inside the PL-1 area.

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Construct Redundant Electrical Supply, Buckley SFB, CO Latest solicitation Solicitation
Construct Redundant Electrical Supply, Buckley SFB, CO This notice Pre-Solicitation
Sources Sought - ERCIP Energy Resilience: PL-1 Electrical Power Supply, Buckley SFB, CO Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity