About this opportunity

This solicitation seeks proposals to replace joint packing at two penstocks located at Fort Randall Dam in Pickstown, South Dakota. The Department of the Army Corps of Engineers Omaha District is procuring the replacement of double expansion joint packing and hardware in Penstock #8, to be completed between February 15 and April 2, 2021. Additionally, the replacement of single expansion joint packing and hardware in Penstock #3, to be completed between March 15 and April 30, 2021 is sought. Offerors must demonstrate relevant experience and past performance, and submit pricing, safety plans, and technical proposals by September 1, 2020. Evaluation will consider technical compliance, past performance, and price.

The opportunity is set aside for total small business and subject to Service Contract Act wage determinations. The NAICS code is 237990 and PSC code R499 cover pipeline construction work. The solicitation is valued between $250,000-$500,000 to be completed on site at Fort Randall Dam. Safety, insurance, and bonding requirements outlined at the pre-bid conference on August 21, 2020 must be addressed in proposals. Daily reports will utilize the specified RMS system, and work hours must be coordinated with the Contracting Officer's Representative.

Notice text

2 versions

Update #2 · Latest ·

Amendment 0001 Post and contains the changes identified in the Site Visit meeting minutes.

Fort Randall Pestock Joint Packing #8: Entire work complete to replace double expansion joint packing and hardware in penstock #8 including all labor, materials, and equipment. The period of work will begin on February 15, 2021 and must be completed no later than April 2, 2021.

Fort Randall Pestock Joint Packing #3: Entire work complete to replace single expansion joint packing and hardware in penstock #3 including all labor, materials, and equipment.  The period of work will begin on March 15, 2021 and must be completed no later than April 30, 2021.

Refer to Solicitation, Specification and Drawings for more information. 

Update #1 ·

Fort Randall Pestock Joint Packing #8: Entire work complete to replace double expansion joint packing and hardware in penstock #8 including all labor, materials, and equipment. The period of work will begin on February 15, 2021 and must be completed no later than April 2, 2021.

Fort Randall Pestock Joint Packing #3: Entire work complete to replace single expansion joint packing and hardware in penstock #3 including all labor, materials, and equipment.  The period of work will begin on March 15, 2021 and must be completed no later than April 30, 2021.

Refer to Solicitation, Specification and Drawings for more information. 

Files

Notice history

Notice Type Posted
FR Penstock Joint Packing Replacement_W9128F20P0078 Award Award Notice
This notice Latest solicitation Solicitation
Pre-Solicitation Notice_FR Penstock Joint Packing Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
John day DAM unit 10 packing box replacement John Day Dam, Sherman County, Oregonthe John Day Dam On The Columbia River Between Sherman County, Oregon, And Klickitat County, Washington. Rufus, Oregon 97050, United States · NAICS 237990 ENDIST Portland No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors