2of2 W9128F20Q0066Penstock Joint Packing Replacement Ft Randall Specs.pdf
PDF 695 KB Posted
- Attached to
- Solicitation Notice_FR Penstock Joint Packing Replacement Federal contract opportunity
- Solicitation number
- W9128F20Q0066
About this file
This solicitation notice seeks proposals for two penstock joint packing replacement projects at Fort Randall Dam. Entire work is required to replace the double expansion joint packing and hardware in penstock #8, including all labor, materials, and equipment. Work must begin by February 15, 2021 and be completed by April 2, 2021. A single expansion joint packing replacement is also required for penstock #3, including all labor, materials, and equipment. For this project, work must begin by March 15, 2021 and be completed by April 30, 2021. The solicitation, specification and drawings provide additional details. The Department of the Army Corps of Engineers Engineering District Omaha issued this solicitation notice.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amd 01 W9128F20Q0066_Penstock Packing at Ft. Randall Dam.pdf | ||
| Site Visit Minutes and Q-A.pdf | ||
| _Pre-Bid MEETING Minutes 8-21-20 _FINAL VERSION.pdf | ||
| Penstock Packing Pre-Bid Sign In Sheet.pdf | ||
| 1of 2 W9128F20Q0066Penstock Packing at Ft Randall Dam SD.PDF | ||
| Drawings FRG9 PENSTOCK JOINT PACKING REPLACEMENT FT RANDALL ADVERTI.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
(For Commercial Service)
Solicitation Number W9128F20Q0066
Penstock Joint Packing Replacement
Fort Randall Dam, SD
August 2020
US Army Corps of Engineers Omaha District
This page was intentionally left blank for duplex printing.
Penstock Joint Packing Replacement Fort Randall Dam, SD
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 12 00 SERVICE OPERATIONS
01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
DIVISION 02 - EXISTING CONDITIONS
02 83 00 LEAD
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 14 PENSTOCK JOINT PACKING REPLACEMENT
-- End of Project Table of Contents --
Penstock Joint Packing Replacement - Fort Randall Dam FRG9
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 12 00
SERVICE OPERATIONS
04/07
PART 1 GENERAL
1.1 SCOPE
1.2 RIGHT-OF-WAY
1.3 PROTECTION OF EXISTING FACILITIES AND WORKS
1.4 Trash Receptacles and Dumpster
1.5 CARE OF WATER
1.6 COOPERATION WITH OTHER CONTRACTORS
1.7 SUBMITTALS
1.8 POWER AVAILABILITY
1.9 CONTRACTOR'S AREA LIGHTING
1.10 STAGING PLAN
1.11 TUNNEL AIR INTAKE
1.12 PORTABLE TOILETS
1.13 FEDERAL HOLIDAYS AND WORKING HOURS
PART 2 NOT USED
PART 3 NOT USED
-- End of Section Table of Contents --
SECTION 01 12 00 Page 1
SECTION 01 12 00
SERVICE OPERATIONS
04/07
PART 1 GENERAL
1.1 SCOPE
The work covered in this section is outlined as a performance work statement requirements common to all the work. Specific requirements for materials and installations are provided under the Technical Sections herewith. No claims for extras shall be made on account of items presumed to have been omitted from this section.
1.2 RIGHT-OF-WAY
The Contractor will be assigned working areas or working right-of-way limits for use in the prosecution of work under this contract.
1.3 PROTECTION OF EXISTING FACILITIES AND WORKS
The Contractor shall be responsible for the protection of the work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started. All work, storage of materials, and plant shall be kept within the limits of the areas assigned. Prior to performance on this contract, , the Contractor shall confer with the Contracting Officer's representative to determine the proximity of any possible under-ground obstructions, pipe or equipment which could be damaged as a result of operations. Existing utility lines that are shown on the drawings or the locations are otherwise made known to the Contractor shall be protected from damage, and if damaged, shall be repaired by the Contractor at no additional expense to the Government. In the event that the Contractor damages any existing utility lines that are not shown or the locations of which have not been made known to the Contractor, report thereof shall be made immediately to the Contracting Officer. The Contractor will be responsible for the protection of structures from any structural damage during the performance on this contract. Roads and surfaces shall be protected from damage by the work or if damaged shall be repaired with equal materials at no additional expense to the Government. At all times the plant and work areas shall be kept in a condition conducive to safety of workmen and the public and neat in appearance. Waste or surplus materials shall not be allowed to accumulate in the work areas.
1.4 Trash Receptacles and Dumpster
The Contractor is responsible for providing their own trash receptacles which should be located within the contractors work space or approved staging area. Work spaces and staging areas shall be kept clean in order to prevent waste from being blown into the river. Government dumpsters or other waste containers are not available for contractor use. Contractor shall be responsible for management and offsite disposal of waste materials generated by this project in accordance with applicable laws a regulations.
SECTION 01 12 00 Page 2
1.5 CARE OF WATER
Full responsibility for care of water shall be borne by the Contractor until completion of work under this contract. The Contractor shall provide the materials and equipment and perform all work necessary to facilitate the needed work and to protect the work from damage by water. The Contractor shall make his own investigations and determinations of conditions, both existing and anticipated concerning care of water. Plans for care of water are subject to approval by the Contracting Officer prior to starting work. Facilities shall be removed upon completion of the work.
1.6 COOPERATION WITH OTHER CONTRACTORS
The Contractor shall cooperate and coordinate his work with that of others working in the area during the life of this contract. The Contractor shall coordinate his work with others to avoid undue interference and shall conduct his operations, other than approved required access, within the limits of the assigned work area or work right-of-way limits. The Contractor shall cooperate with others as necessary in the interest of timely completion of all work and in the event of disagreement the decision of the Contracting Officer shall be final.
1.7 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Pre-performance Submittals
Staging Plan
SD-02 Shop Drawings
Care of Water; G-PO
1.8 POWER AVAILABILITY
Available temporary power will be 110V receptacles are located roughly every 50 feet along the penstock. No 480V receptacles are available.
Contractor would need to provide their own power for anything other than the existing 110V receptacles.
When pumping water across the joint on the inside of the penstock, 110V power receptacles are available in the inspection gallery (outside the access door to the penstock located in the lower level of the powerhouse) and can be used to power a pump as needed
1.9 CONTRACTOR'S AREA LIGHTING
The Contractor shall provide all additional lighting necessary to insure a quality performance and to provide a safe work environment.
SECTION 01 12 00 Page 3
1.10 STAGING PLAN
The Contractor shall submit a staging plan that identifies access methods and locations for placement of equipment and material. The staging plan shall identify the types and quantities of items to be staged , and shall provide approximate locations of where these items will be placed.
1.11 TUNNEL AIR INTAKE
The Contractor is advised not to park vehicles near the outside air intake to the tunnel terminal area. The exhaust from vehicles can cause poor air quality in the tunnel.
1.12 PORTABLE TOILETS
Toilet facilities will not be available for Contractor's use. The Contractor shall provide and maintain portable toilets for use by the Contractor's staff. Toilet(s) shall be placed within the staging area. To prevent overturning by high winds, all portable toilets shall be anchored down.
1.13 FEDERAL HOLIDAYS AND WORKING HOURS
Work hours: The Contractor can work Monday through Friday 0700 to 1730.
Working outside these work hours will need written permission from the COR.
The Contractor will not be allowed to work on Federal holidays.
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If the wage determination has a discrepancy with the above list of observed Federal holidays, then the wage determination take precedence.
PART 2 NOT USED
PART 3 NOT USED
-- End of Section --
SECTION 01 12 00 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
10/17
PART 1 GENERAL
1.1 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.2 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS
1.3 SECURITY REQUIREMENTS
1.3.1 Security Requirements
1.3.2 List Of Contractors
1.3.3 Personnel Risk Assessment
1.3.4 Authorized Unescorted Access Requirements
1.3.5 Special Qualifications
PART 2 NOT USED
PART 3 NOT USED
SECTION 01 30 00.24 Page 1
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
10/17
PART 1 GENERAL
1.1 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This clause specifies the procedure for the determination of time extensions for unusually severe weather. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
Jan 17 Feb 15 Mar 8 Apr 5 May 5 Jun 6 Jul 4 Aug 4 Sep 5 Oct 4 Nov 5 Dec 16
c. Upon contract award and continuing throughout the contract, the contractor will record the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the
SECTION 01 30 00.24 Page 2 number of days anticipated in paragraph b. above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification.
1.2 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS
In order to closely coordinate work under this contract, the Contractor shall prepare a written agenda/meeting minutes and attend a weekly coordination meeting with the Contracting Officer and Using Service at which time the Contractor shall submit for coordination, the proposed daily work schedule for the next two week period.
1.3 SECURITY REQUIREMENTS
1.3.1 Security Requirements
All Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
1.3.2 List Of Contractors
Submit a complete, updated and signed, list of all Contractor and subcontractor personnel, including their titles and intended working hours, who will be working on site prior to start of work. This listing shall be revised and resubmitted when personnel changes occur.
1.3.3 Personnel Risk Assessment
A minimum of seven days prior to engaging in work submit, to the CO or Project POC, a Personnel Risk Assessment (PRA) for each employee requiring authorized unescorted access to the Jobsite. The Contractor employee will only be allowed authorized unescorted physical access after the PRA is shown to and approved by the Government.
1.3.4 Authorized Unescorted Access Requirements
Perform a PRA on all Contractor personnel that require authorized unescorted access to the Jobsite. Costs associated with the execution of the PRA shall be at the expense of the Contractor. The content of the PRA is defined by the requirements as follows:
a. Criminal Check - Obtain a criminal background check, completed within the last seven years, on all Contractor personnel that require authorized unescorted access to the Jobsite. A minimum of a 7-year criminal background check with the state patrol office shall be performed from all states of
SECTION 01 30 00.24 Page 3 residence and employment, for the past seven years. The COR through the Contacting Officer will approve, disapprove, or revoke authorized unescorted access to the Jobsite as a result of the seven-year background check in accordance with Army Directive 2014-05 Enclosure 2.
b. Identity Verification - Contractor employees shall provide positive verification of individual identity prior to authorized unescorted access to the Jobsite. Acceptable forms of identity verification are documents issued by a federal Government agency that include: the individual's photograph, name, and date of birth, such as a passport or military identification (ID) card. Additionally, a state issued driver's license or ID card is acceptable for identity verification.
c. The Criminal Check and Identity Verification shall be updated at least every seven years for each employee requiring authorized unescorted access to the Jobsite.
d. Escort Requirements - Contractor personnel not cleared for authorized access to the Jobsite may be escorted by Government or Contractor personnel that have authorized unescorted access to the Jobsite. All costs related to the escorting of non-cleared personnel shall be at the expense of the Contractor. Additional burden shall not be placed upon the Government to provide these escorts. Prior to access, coordination with the Project Security Officer is required, including but not limited to:
(1) Verification of identity with photo identification
(2) Name of escorting individual and verification of unescorted status
(3) Time of entry into the Jobsite
(4) Time exiting the Jobsite.
1.3.5 Special Qualifications
All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: https://atlevel1.dtic.mil/at.
The Contractor and all associated sub-contractors shall brief all employees on the local iWATCH, Corps Watch, or See Something, Say Something program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after contract award.
http://www.myarmyonesource.com/cmsresources/Army%20OneSource/Media/Videos/ Family%20Programs%20and%20Services/iWatch_Program/iWATCH%2060_4streaming.wmv
All new Contractor employees will complete Level I OPSEC training within 30 calendar days of their reporting for duty. Additionally, all Contractor employees must complete annual OPSEC awareness training.
http://cdsetrain.dtic.mil/opsec/index.htm
SECTION 01 30 00.24 Page 4
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas. There are NO classified materials at this project location.
The Prime Contractor Company must have (or will have) a Facility Clearance (FCL) at the appropriate level (IAW the NISPOM DOD 5220.22-M and AR 380-49) prior to the start of the contract awarded period of performance.
Contractor personnel performing work under this contract must have the required security clearance, per AR 380-67, at the appropriate level at the start of the period of performance. Security Clearances and FCL requirements are required to be maintained for the life of the contract IAW the DD254 attached to the contract. If no FCL, the supporting Government Contracting Activity will sponsor the prime contract company in obtaining the FCL. This location does NOT require a Facility Clearance/FCL.
The Contractor must pre-screen Candidates using the E-verify Program (http://www.dhs.gov/E-Verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
PART 2 NOT USED
PART 3 NOT USED
SECTION 01 30 00.24 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, OMH 02/2019
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
1.1.2 Project Type
1.1.3 Submission of Submittals
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.3.1 Action Codes
1.3.1.1 Contractor Action Codes
1.3.1.2 Government Reviewer Designations
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
1.4.2 For Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Pre-Performance Submittals
1.5.2.2 Format for SD-02 Shop Drawings
1.5.2.2.1 Drawing Identification
1.5.2.3 Format of SD-03 Product Data
1.5.2.3.1 Product Information
1.5.2.3.2 Standards
1.5.2.3.3 Data Submission
1.5.2.4 Format of SD-04 Samples
1.5.2.4.1 Sample Characteristics
1.5.2.4.2 Sample Incorporation
1.5.2.4.3 Comparison Sample
1.5.2.5 Format of SD-05 Design Data
1.5.2.6 Format of SD-06 Test Reports
1.5.2.7 Format of SD-07 Certificates
1.5.2.8 Format of SD-08 Manufacturer's Instructions
1.5.2.8.1 Standards
1.5.2.9 Format of SD-09 Manufacturer's Field Reports
1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)
1.5.2.11 Format of SD-11 Closeout Submittals
1.5.3 Source Drawings for Shop Drawings
1.5.3.1 Source Drawings
1.5.3.2 Terms and Conditions
1.5.4 Electronic File Format
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of SD-04 Samples
1.7 INFORMATION ONLY SUBMITTALS
SECTION 01 33 00 Page 1
1.8 PROJECT SUBMITTAL REGISTER
1.8.1 Submittal Management
1.8.2 Pre-performance Use of Submittal Register
1.8.3 Contractor Use of Submittal Register
1.8.4 Approving Authority Use of Submittal Register
1.8.5 Action Codes
1.8.6 Delivery of Copies
1.9 VARIATIONS
1.9.1 Considering Variations
1.9.2 Proposing Variations
1.9.3 Warranting that Variations are Compatible
1.9.4 Review Schedule Extension
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
ENG Form 4025-R
Project Submittal Register
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, OMH 02/2019
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contractor is responsible for total management of their work including, but not limited to, approval, scheduling, control, certification of all submittals and compliance with all applicable Buy-American and Trade Agreement clauses. The submittal management system provided in these specifications is intended to be a complete system for the Contractor to use to control the quality of materials, equipment and workmanship provided by manufacturers, fabricators, suppliers and subcontractors. Review each submittal for contract compliance. Compliance with all applicable Buy American and Trade Agreement Clauses is to be included in this review. The Contractor must provide the country of origin on ENG Form 4025 for each item submitted. The Submittal Register (ENG Form 4288) will be utilized to log and monitor all submittal activities.
The Contracting Officer may request submittals, in addition to those specified, when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager is to check and approve all items before submittal and stamp, sign, and date indicating action taken. Clearly identify proposed deviations from the contract requirements. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves;
test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required items.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval, upon Contract Award. Provide ample lead time to ensure the submittal's processing by the Government and any lead time needed by the manufacturer upon ordering after approval. Dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
SECTION 01 33 00 Page 3
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Pre-Performance Submittals
Submittals that are required prior to or at the start of performance (work) or the next major phase of the performance on a multiphase contract.
Pre-Performance Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
The Government reserves the right to handle pre-performance submittals (listed below) as administrative submittals via a Serial Letter, as directed by the Project, Area or Resident Office. When directed by the Project, Area or Resident Office (as directed), submit administrative submittals for acceptance by the Government. Format for the Serial Letter will be as directed by the Project, Area or Resident Office.
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Project Schedule
Submittal Register
Accident Prevention Plan
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
SECTION 01 33 00 Page 4
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards ensuring work can be judged. Includes assemblies or portions of assemblies that are to be incorporated into the project and those that will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
SECTION 01 33 00 Page 5
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (SDS)concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data provided by the manufacturer, or the system provider, including manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.
Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
Data incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a performance contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of performance on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
SECTION 01 33 00 Page 6
1.2.3 Work
As used in this section, on-site and off-site performance required by contract documents, including labor necessary to produce submittals, performance, materials, products, equipment, and systems incorporated or to be incorporated in such performance. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having any designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Pre-Performance Submittals
Submittal Register; G-PO
1.3.1 Action Codes
1.3.1.1 Contractor Action Codes
DESIGN BID BUILD SUBMITTALS
Submittal Classifications shown in UFGS Sections
Submittal Classification
Corresponding Submittal Register
Code which is populated in the SI Submittal Register.
Software
Limitations: (The software shows one character delineation in the Submittal Register)
RMS – The following Submittal
Classifications are populated in RMS when the Submittal Data File is pulled into RMS)
G Submittal requires Government Approval
G GA
BLANK Submittal is For Information Only
(FIO)
BLANK FIO
1.3.1.2 Government Reviewer Designations
Following the Submittal Classification designation "G", the following reviewer designations may be included:
RO - Resident Office AO - Area Office DO - District Office AE - Architect Engineer
SECTION 01 33 00 Page 7
Additional information will be provided at the pre-design and/or pre-performance conference.
Corps of Engineers, Omaha District Office for "DO" reviewer designations, submittals will be coordinated through:
Michael Hebert U.S. Army Corps of Engineers Omaha District Attn: CENWO-CDS-T 1616 Capitol Ave Omaha, NE 68102-4901 E-mail: CENWO.ConstructionSubmittal@usace.army.mil
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.4.2 For Information Only
Submittals not requiring Government approval will be for information only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.5 PREPARATION
1.5.1 Transmittal Form
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. If there are multiple Item numbers listed on a particular ENG Form 4025-R submittal, combine all submitted items for review into a single Adobe file with bookmarks (for ease of review). Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Pre-Performance Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
SECTION 01 33 00 Page 8
1.5.2.2 Format for SD-02 Shop Drawings
Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.
Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Submit an electronic copy of drawings in PDF format.
1.5.2.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
1.5.2.3 Format of SD-03 Product Data
Present product data submittals for each section. Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.2.3.1 Product Information
Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.
Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.
1.5.2.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or
SECTION 01 33 00 Page 9 listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer.
State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.2.3.3 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the performance effort.
Submit the manufacturer's instructions before installation.
1.5.2.4 Format of SD-04 Samples
1.5.2.4.1 Sample Characteristics
Furnish samples in the following sizes, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:
a. Sample of Equipment or Device: Full size.
b. Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.
c. Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
e. Sample Volume of Nonsolid Materials: Pint. Examples of nonsolid materials are sand and paint.
f. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
g. Sample Panel: 4 by 4 feet.
h. Sample Installation: 100 square feet.
1.5.2.4.2 Sample Incorporation
Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at the time of use.
Recording of Sample Installation: Note and preserve the notation of any area constituting a sample installation, but remove the notation at the final clean-up of the project.
SECTION 01 33 00 Page 10
1.5.2.4.3 Comparison Sample
Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.
When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
1.5.2.5 Format of SD-05 Design Data
Provide design data and certificates on 8 1/2 by 11 inch page size.
1.5.2.6 Format of SD-06 Test Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.2.7 Format of SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inch page size.
1.5.2.8 Format of SD-08 Manufacturer's Instructions
Present manufacturer's instructions submittals for each section. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.
Submit the manufacturer's instructions before installation.
1.5.2.8.1 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer.
State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.2.9 Format of SD-09 Manufacturer's Field Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
SECTION 01 33 00 Page 11
1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.
1.5.2.11 Format of SD-11 Closeout Submittals
When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.3 Source Drawings for Shop Drawings
1.5.3.1 Source Drawings
The entire set of source drawing files (DWG or DGN) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.5.3.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of performance data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not performance documents.
Differences may exist between the source drawing files and the corresponding performance documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed performance documents prepared by the Government and the furnished source drawing files, the signed and sealed performance documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing performance data related to this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).
1.5.4 Electronic File Format
Provide submittals in electronic format, with the exception of material
SECTION 01 33 00 Page 12 samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. All documents must make use of optical character recognition (OCR) routines to make text searchable and selectable, so that the text can be copied. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature.
E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer, unless directed otherwise by COR. Provide electronic documents over 10 MB on an optical disc or through an electronic file sharing system, such as secure ftp site or Government web application located at the following website:
https://safe.arl.army.mil/. Use of the Government web application must be initiated by the Government, unless Contractor has a Government CAC card.
The Government may allow the AMRDEC SAFE Web Application located at the following website: https://safe.amrdec.army.mil/safe/. Both Government web applications restrict the number of days files are available to download.
1.6 QUANTITY OF SUBMITTALS
Submittals are to be transmitted electronically, unless directed otherwise.
1.6.1 Number of SD-04 Samples
a. Submit two samples, or two sets of samples showing the range of variation, of each required item. One approved sample or set of samples will be retained by the approving authority and one will be returned to the Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in the technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of nonsolid materials.
1.7 INFORMATION ONLY SUBMITTALS
Submittals without an action code must be certified by the QC manager and submitted to the Contracting Officer for information-only. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the
SECTION 01 33 00 Page 13
Government in those instances where the technical specifications so prescribe.
1.8 PROJECT SUBMITTAL REGISTER
A sample Project Submittal Register showing submittals required by the specifications is attached to this section as "Project Submittal Register."
1.8.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and (i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM). The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.8.2 Pre-performance Use of Submittal Register
Submit the submittal register as an electronic database, using the submittal management program furnished to Contractor, unless directed otherwise by COR. Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register database submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
SECTION 01 33 00 Page 14
1.8.3 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in the program used by the Contractor with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
Column (q) Date approval was received.
1.8.4 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
1.8.5 Action Codes
See paragraph Action Codes above.
1.8.6 Delivery of Copies
Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request, unless a paper copy is requested by the Contracting Officer. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.
1.9 VARIATIONS
1.9.1 Considering Variations
Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals.