Site Visit - GAOA Lolo Recreation Site Water System Replacements

Closed Special Notice Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
1240LU24B0002
Agency
Forest Service Department of Agriculture
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Z1AZ Maintenance Of Other Administrative Facilities And Service Buildings
Place of performance
Missoula, Montana, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Forest Service published a Special Notice to invite contractors to conduct site visits for water system replacement projects planned at four recreation sites on the Lolo National Forest in Montana. The projects aim to replace aging water distribution infrastructure at Bend Guard Station, Lee Creek Campground, Grizzly Campground, and Seeley Lake Campground.

Interested contractors must inspect each project site on their own before November 30, 2023 to evaluate existing conditions and project scope prior to submitting bids. The solicitation documents with full construction details will be posted in mid-December. Bids for the waterline replacement work are due February 22, 2024. Eligible contractors should have experience developing water systems for recreation areas. The projects range from $250,000 to $500,000 and are scheduled to be completed between May 2024 and October 2025. Site visits are an opportunity for contractors to assess each project and develop informed bids for the planned water infrastructure upgrades across the four Lolo National Forest sites.

Notice text

2 versions

Update #2 · Latest ·

Z- GAOA Lolo Recreation Site Water System Replacements on the Lolo National Forest  - SITE VISIT NOTICE ONLY, Interested vendors must inspect the site on their own before 02/15/2024, prior to bidding!

Project Locations.  The project is located at various recreation sites throughout the Lolo National Forest shown on the vicintity Map and listed below:Bend Guard Station – Plains/Thompson Falls Ranger District, Sanders County, Lee Creek Campground – Missoula Ranger District, Missoula County, Grizzly Campground – Missoula Ranger District, Missoula County & Seeley Lake Campground – Seeley Lake Ranger District, Missoula County.

The contractor shall furnish all labor, transportation, equipment, material, supervision, and expertise necessary to accomplish the work at each site.  The scope of work at each site is slightly different in nature, details of the work at each site are described below:

Bend Guard Station – This project includes installation of new waterline from existing well to cookhouse, connection to existing well and connection to existing water service piping within cookhouse, installation of lateral line over to stock tank with non-potable water hydrant, installation lateral line to flushing hydrant controlled with ball valve, and replacement of piping and appurtenances within the cookhouse building.  Additional valves, pressure switches, and junctions will also be required. 

Lee Creek Campground – This project includes the replacement of all water system lines and four water spigots within the Lee Creek Campground. A new pumphouse and new inner workings such as pressure tanks are also included as optional bid items. 

Grizzly Campground – This project includes coordinating with power utility company to bring power into the campground, a new pumphouse/control room, remove existing hand pump and installing new pump, new waterline between pump and pumphouse/control room, and one hydrant with concrete splash pad.  The contract will also include an option item to install an additional water line to second hydrant. 

Seeley Lake Campground – This project will include the replacement of a segment of waterline and the associated hydrants and pipe junctions that have been damaged at the Seeley Lake Campground.  

Construction Magnitude is between $250,000 and $500,000

Period of Performance: 05/01/2024 to 10/01/2025

ALL Solicitation documents will be posted in late january under this solicitation number.

     

Update #1 ·

Z- GAOA Lolo Recreation Site Water System Replacements on the Lolo National Forest  - SITE VISIT NOTICE ONLY, Interested vendors must inspect the site on their own before 11/30/2023, prior to bidding!

Project Locations.  The project is located at various recreation sites throughout the Lolo National Forest shown on the vicintity Map and listed below:Bend Guard Station – Plains/Thompson Falls Ranger District, Sanders County, Lee Creek Campground – Missoula Ranger District, Missoula County, Grizzly Campground – Missoula Ranger District, Missoula County & Seeley Lake Campground – Seeley Lake Ranger District, Missoula County.

The contractor shall furnish all labor, transportation, equipment, material, supervision, and expertise necessary to accomplish the work at each site.  The scope of work at each site is slightly different in nature, details of the work at each site are described below:

Bend Guard Station – This project includes installation of new waterline from existing well to cookhouse, connection to existing well and connection to existing water service piping within cookhouse, installation of lateral line over to stock tank with non-potable water hydrant, installation lateral line to flushing hydrant controlled with ball valve, and replacement of piping and appurtenances within the cookhouse building.  Additional valves, pressure switches, and junctions will also be required. 

Lee Creek Campground – This project includes the replacement of all water system lines and four water spigots within the Lee Creek Campground. A new pumphouse and new inner workings such as pressure tanks are also included as optional bid items. 

Grizzly Campground – This project includes coordinating with power utility company to bring power into the campground, a new pumphouse/control room, remove existing hand pump and installing new pump, new waterline between pump and pumphouse/control room, and one hydrant with concrete splash pad.  The contract will also include an option item to install an additional water line to second hydrant. 

Seeley Lake Campground – This project will include the replacement of a segment of waterline and the associated hydrants and pipe junctions that have been damaged at the Seeley Lake Campground.  

Construction Magnitude is between $250,000 and $500,000

Period of Performance: 05/01/2024 to 10/01/2025

ALL Solicitation documents will be posted in Mid-December under this solicitation number.

     

Attachments

Files attached to this notice, newest first
File Type Posted
LeeCreekCampground_Plans.pdf PDF
Grizzly Campground Water System Plans.pdf PDF
Bend Guard Station Water System Improvements - Plans.pdf PDF
Seeley Campground Plans.pdf PDF

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
GAOA Lolo Recreation Site Water System Replacements Award Award Notice
GAOA Lolo Recreation Site Water System Replacements Latest solicitation Solicitation
GAOA Lolo Recreation Site Water System Replacements Pre-Solicitation
Site Visit - GAOA Lolo Recreation Site Water System Replacements This notice · Original Special Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity