The U.S. Army Corps of Engineers seeks to award a firm-fixed-price contract for the design-bid-build restoration and modernization of Buildings B551 and B561 at Red River Army Depot in Texarkana, Texas. The scope of work includes structural repairs, new roofs, code-compliant electrical and fire protection systems, and asbestos abatement. Proposals are due by September 10, 2020 with anticipated contract award by August 31, 2020 and project completion within 660 days of notice to proceed. The evaluation criteria will emphasize technical qualifications, past performance, and price.

This is a total small business set-aside solicitation. The primary NAICS code is 238210 and PSC code S206. The estimated value is between $25-100 million to be performed in Texarkana, Texas over a 660 calendar day period from notice to proceed. Key details include repairing and replacing failed building components for 91,000 square foot depot level rebuild facilities while increasing wall heights and upgrading building systems at Buildings B551 and B561.

Notice text

10 versions

Update #10 · Latest ·

**AMENDMENT 11 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF TUESDAY 08 SEPTEMBER 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #9 ·

**AMENDMENT 10 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF FRIDAY, 04 SEPTEMBER 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #8 ·

**AMENDMENT 09 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF FRIDAY, 04 SEPTEMBER 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #7 ·

**AMENDMENT 08 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF TUESDAY, 02 SEPTEMBER 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #6 ·

**AMENDMENT 07 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF TUESDAY, 01 SEPTEMBER 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #5 ·

**AMENDMENT 06 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF FRIDAY, 28 AUG 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #4 ·

**AMENDMENT 05 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF MONDAY., 24 AUG 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #3 ·

**AMENDMENT 04 FOR THIS SOLICITATION IS HEREBY POSTED AND ISSUED AS OF FRIDAY., 21 AUG 2020**

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #2 ·

PLEASE SEE ALL ATTACHMENTS AT THE BOTTOM OF THE SOLICITATION

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Update #1 ·

This request for proposal is for a Design-Bid-Build (DBB) contract.

the complete Restoration and Modernization of Buildings B551 and B561 at Red River Army Depot (RRAD), Texarkana, TX.

The Government intends to establish a Firm Fixed-Price (FFP) Contract for the repairs to buildings 551 and 561. The scope of work will include all work in accordance with the plans and specification to make necessary repairs to restore the failed and failing building components and correct regulatory code deficiencies.  Renovation will increased wall height but will not replace the building walls. Existing walls shall be reinforced to accommodate for the renovations. Buildings 551 and 561, each provide 91k SF of depot level rebuild operation space capable of supporting multiple depot programs, including MaxxPRO, Military All-Terrain Vehicle (MATV), Family of Medium Tactical Vehicles (FMTV), Cougar, High Mobility Multipurpose Wheeled Vehicle (HMMWV), and Trailers for Army, Navy, Marines, and Field Maintenance Squadron (FMS).

B551:

1. The following equipment items shall be removed and stored for reinstallation in the building: radiant heaters, HVLS fans, blue "turbo" fans, hose reels, and electrical cord reels.

2.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

3.  The existing air compressors (located on the west and south sides of the building) and associated equipment and canopy shall remain for reconnection to the building.

4. Portions of walls shall be selectively demolished for the installation of new roll-up doors.

5. Repair structural components in failing state and provide a standing seam metal roof.

6. Provide a code compliant electrical distribution system.

7. Provide a code compliant fire sprinkler system.

8. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

9. Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

10. Provide a compressed air distribution system and accessories in each building.

11. Provide overhead lifting in each building.

B561:

1.  The following items shall be removed and stored for reinstallation in the RM building: radiant heaters, HVLS fans, blue "turbo" fans, yellow "cool zone" fans, and LED light fixtures.

2.  The existing material handling equipment (3-ton floor-mounted bridge cranes and 1- and 3-ton floor mounted jib boom cranes) shall be removed and returned to the government for disposition.

3.  The existing fire alarm system components shall be removed and stored for reinstallation in the building.

4.  The existing air compressor (located on the south end of the building) and its associated equipment and canopy shall remain for reconnection to the building.

5.  The following existing facilities shall remain for reconnection to the building:

      a.  14'x44' restrooms, 2 each, one at the northwest corner and one at the southwest corner

      b.   26'x42' break room on the east side

      c.    12'x40' office on the east side

6.  Portions of walls shall be selectively demolished for the installation of new roll-up doors.

7. Repair structural components in failing state and provide a standing seam metal roof. The standing seam metal roof system will protect the integrity of the structural components in the existing structural system.

8.  Provide a code compliant electrical distribution system.

9.  Provide a code compliant fire sprinkler system.

10. Provide a code-compliant fire alarm/mass notification system for each building, utilizing the reclaimed components to the greatest extent practical.

11.  Provide exhaust fans, HVLS fans, and column/wall mounted fans in each building, utilizing the reclaimed fans to the greatest extent practical.

13.  Provide a compressed air distribution system and accessories in each building.

14.  Provide overhead lifting in each building.

Abatement of asbestos-containing materials shall be accomplished in both buildings, particularly in the renovated areas . B551 asbestos materials are roofing, caulking, foundation tar, fire doors, and the exterior wall coating (beneath paint). B561 asbestos materials are roofing, caulking, and fire doors.

FAR 36.204{f) Disclosure of the magnitude of construction project between $25,000,000 and $100,000,000.

The request for proposal is anticipated to be issued on or about 3 July 2020, and bids due on or about 3 August 2020. A firm-fixed price contract is anticipated to be awarded. Anticipated contract award date on or about 31 August 2020.

Anticipated project completion date is 660 days from Notice to proceed.

After solicitation issuance, contractors may view and/or download this solicitation and all amendments at the following internet address: htt ps:// www.beta.SAM.gov/.The use of the website requires prior registration at www.beta.SAM. gov/. Plans and specifications will not be made available in paper format or on compact disc. It is the Offerers responsibility to monitor the beta.SAM web site for amendments to the solicitation. You must be registered with the System Award for Management

{SAM), to receive a Government contract awa rd. You may register with SAM at https://www.sam.gov/. This contract is subject to the availability of funds per FAR clause 52.232-18.

The Government reserves the right to use only the Internet as notification of any amendments to this solicitation. It is the offerers responsibility to view the beta.SAM website daily for amendments to the solicitation. Accordingly, prospective contractors may view and/or download the solicitation and all amendments from the beta.SAM address after solicitation issuance at the following address: httP-s://www.beta.SAM.gm!L. Solicitation Number: W9126G20B0031.

Place of Performance:

Red River Army Depot Texarkana, Texas 75501

United States

Files

File Type Posted
Amendment_11.pdf PDF
B3_W9126G20B0031_am_10.pdf PDF
Amendment_09.pdf PDF
Amendment_8.pdf PDF
Amendment_07.pdf PDF
am_6.pdf PDF
B3_Amendment_05.pdf PDF
am_04.pdf PDF
B5_Second Site Visit_Completed sign in sheet 200819.pdf PDF
B5_Second_Site Visit 200819 photos.pdf PDF
B3_Amendment_03.pdf PDF
Amendment_02.pdf PDF
Amendment 01.pdf PDF
B551 and B561_Completed sign-in sheet.pdf PDF
B3_0-551-COMBINED-RTA.pdf PDF
B3_W9126G20B0031.pdf PDF
B3_0-561-COMBINED-RTA.pdf PDF
Show all 17

Notice history

Notice Type Posted
RRAD B551 and 561 Repairs Latest special notice Special Notice
RRAD B551 and 561 Repairs Special Notice
This notice Solicitation
RRAD B551 and 561 Repairs Pre-Solicitation
RRAD B551 and 561 Repairs Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Sources Sought- Sources Sought & Other Transaction Authority (OTA) Construction for Non-Destructive Testing Facility, Red River Army Depot, Texas Texas 75570, United States · NAICS 236220 ENDIST Fort Worth No set-aside
Sources Sought -Building 493 Generator and Backup Power Installation- Red River Army Depot Texarkana, Texas 75501, United States · NAICS 238210 ENDIST Fort Worth No set-aside
Design-Build Maintenance and Repair Army Reserve (MRAR) of Equipment Concentration Site (ECS), B-56767, at North Fort Hood, TX Bldg. 56767 Equipment Concentration Site (ECS) #6428th St. and Park Ave.North Fort Hood, TX Gatesville, Texas 76528, United States · NAICS 236220 ENDIST Louisville Total Small Business
Design/Build Maintenance and Repair Army Reserve (MRAR), Area Maintenance Support Activity (AMSA) 21, JBMDL, NJ Joint Base MDL, New Jersey, United States · NAICS 236220 ENDIST Louisville Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity