This request for proposal solicits bids for a design-bid-build contract to perform restoration and modernization work at Buildings B551 and B561 at Red River Army Depot in Texarkana, Texas. The scope of work includes repairing structural components, installing a standing seam metal roof, upgrading electrical and mechanical systems to current codes, providing fire sprinklers and a fire alarm/mass notification system, and asbestos abatement. Bids are due by August 3, 2020 and award is anticipated by August 31, 2020 with a 660 day period of performance. The government intends to award a firm-fixed-price contract valued between $25-100 million. Work will include removing and reinstalling equipment, selective wall demolition, and adding roll-up doors. The document provides details on specific requirements and work items for each building.

View the file

Other files

File Type Posted
B3_W9126G20B0031_am_10.pdf PDF
Amendment_09.pdf PDF
Amendment_8.pdf PDF
Amendment_07.pdf PDF
am_6.pdf PDF
B3_Amendment_05.pdf PDF
am_04.pdf PDF
B5_Second_Site Visit 200819 photos.pdf PDF
B5_Second Site Visit_Completed sign in sheet 200819.pdf PDF
B3_Amendment_03.pdf PDF
Amendment_02.pdf PDF
Amendment 01.pdf PDF
B551 and B561_Completed sign-in sheet.pdf PDF
B3_0-551-COMBINED-RTA.pdf PDF
B3_0-561-COMBINED-RTA.pdf PDF
B3_W9126G20B0031.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04 EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The Solicitation for Repair B551 and B561 at Red River Army Depot (RRAD), Texas is amended as follows.

See SF30 Continuation Sheet(s)

NOTE: Bid Receipt is 17 September 2020; at 10:00 AM, CT

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer) (Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

W9126G20B0031

X 9B. DATED (SEE ITEM 11)

05-Aug-2020

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08 SEP 2020

CODE

US ARMY ENGINEER DISTRICT, FORT WORTH

ATTN: CESWF-CT

819 TAYLOR ST, ROOM 2A19

P.O. BOX 17300

FORT WORTH TX 76102-0300

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODE CODE

EMAIL: TEL:

W9126G20B0031

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

CHANGES TO SOLICITATION W9126G20B0031

1. Replacement Sections: Replace the following section with the accompanying new section of the same number and title bearing the notation W9126G20B0031 0011:

11 81 28 - FACILITY FALL PROTECTION (FOLD-AWAY SYSTEM)

41 22 13.14 - BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING

End of Summary of Changes

Repair B551 and B561 RR20B551

SECTION 11 81 28

FACILITY FALL PROTECTION (FOLD-AWAY SYSTEM)

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z359 (2019) Fall Protection & Fall Restraint

ASTM INTERNATIONAL (ASTM)

ASTM A36/A36M (2014) Standard Specification for Carbon Structural Steel

ASTM A572/A572M (2018) Standard Specification for High-Strength Low-Alloy Columbium-Vanadium Structural Steel

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1 (2020) Structural Welding Code

OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)

OSHA (1910) Specification 1910.66: Personal Fall Arrest System

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Structural Steel Framework and Assembly Drawings ; G

SD-03 Product Data

System Type, Configuration and Catalog Data ; G

Personnel Harness and Accessories ; G

Retraction System and Arresting Cables ; G

SD-05 Design Data

Capacities, Performance Loads and Applied Forces ; G

SECTION 11 81 28 Page 1

W9126G20B0031 0011

SD-07 Certificates

Welders Certificates of Compliance ; G

SD-08 Manufacturer's Instructions

Users Operational Instructions ; G

SD-09 Manufacturer's Field Reports

Manufacturer's Acceptance Inspection Report ; G

SD-10 Operation and Maintenance Data

Maintenance schedule and procedures ; G

1.3 MAINTENANCE MATERIAL SUBMITTALS

Provide 4 copies of the maintenance and operation manual. Maintain one permanent copy at the facility site.`Provide two fall harnesses and cable system at each bay location.

1.4 QUALITY CONTROL

1.4.1 Regulatory Requirements

After the system has been installed and after any modifications, an acceptance inspection must be performed using the After a Fall Event and Annual Anchor Track System Inspection Checklist included in the Assembly and Operation Instruction Manual before use. The manufacturer's representative shall perform the acceptance inspections. Submit a copy of the manufacturer's acceptance inspection report to the Contracting Officer.

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver all components to the site in sealed containers and protected from weather. Store at the site either indoors or sealed from weather conditions.

1.6 WARRANTY

Included a manufacturer's warranty on manufacturer’s standard form and outlines the manufacturer’s agreement to repair or replace assemblies and components that fail in materials and/or execution within warranty period from date of substantial completion.

Warranty shall include the engineered track equipment, wearable end truck wheels, anchors and trolley wheels and teeth to be free from defects in material and workmanship for a period of ten (10) years commencing on the date of manufacturer's approved acceptance report

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

Provide delegated design and engineered system, furnished and installed for the fold-away fall protection systems. the column-mounted fold-away system when in use shall provide a fixed path of rigid fall protection

SECTION 11 81 28 Page 2 with an enclosed track hung from two or more swing arms that fold away when not in use. Provide a single track system for two workers. Track is mounted to swing arms bolted to structural support columns. Provide a locking mechanism when system is in use. The system shall be configured as indicated on drawing and within alternate bays. Custom support spacing shall fit the building column spacing. Provide an arm reach distance of 14 feet. <am#0004> Motorization of the arms shall be provided . </am#0004> Provide a field assembly with bolt-together components. Minimize the need for welding.

2.1.1 Design Requirements

As a basis of design refer to the following manufacture:

Rigid Lifelines® Locations: Morgantown, PA and Las Vegas, NV;

Phone: 800-869-2080;

Website: RigidLifelines.com

The basis of design is not intended to limit other products and system provide they meet or exceed the performances, and other salient characteristics specified herein.

2.1.2 Performance Requirements

Design system for a single track and two independent workers per track in conformance with the following applicable standards ANSI Z359 , OSHA 1910.66, and AISC Manual of Steel Construction. The system shall be designed and sealed by a licensed engineer. Submit design calculations for the capacities, performance loads and applied forces . Submit structural steel framework and assembly drawings .

2.1.2.1 Coverage

System shall provide coverage area of size indicated on drawings and consist of:

a. Enclosed track bolted on swing arms mounted to existing structures or steel I-beams

b. Track pivot hanger assemblies

c. Swiveling connector anchor trolley

d. Personnel fall arresting harness, and restraining cable and devise <am#0011>

e. Provide electro mechanical retraction system of the restraint cable when not in use or required for crane movement.

</am#0011>

2.1.2.2 Design Strength

For each user, the system shall be designed based on a worst-case placement of the 900-pound (408 kg) maximum average arresting force with a safety factor of two and the weight of the anchor system.

2.1.2.3 Operating Temperature

5 to 200 degrees F (-15 to 93 C)

SECTION 11 81 28 Page 3

2.1.2.4 Structural Design

The system’s structural design is based on dynamic load capacity. System shall be designed to withstand:

1. System and dynamic load and impact factors.

2. Dynamic load capacity equal to rated capacity.

3. Inertia forces from system and dynamic load movement.

2.2 FABRICATION

2.2.1 Shop Fabrication

Fabricated using high strength steel or ASTM A36/A36M steel for structural components. Shop fabricate to the greatest extent possible. All welding shall be performed by AWS D1.1 structural certified welders. Submit copies of welders certificates of compliance .

2.3 MANUFACTURED UNITS

Column-Mounted Fold-Away system as manufactured as a custom-engineered system, fabricated using high strength steel or ASTM A36/A36M steel for structural components. Submit system type, configuration and catalog data of the proposed system.

Provide track, tubing, and welded track having minimum yield strength of 46,000 pounds per square inch. Steel I-beams and plate having minimum yield strength of 36,000 pounds per square inch. Steel Track shall be rolled from ASTM A572/A572M , A607, or A715 grade steel. Design track profile to ensures wheel protection, accurate alignment with minimum friction, and low-maintenance, self-cleaning profile. All track shall have full contact flange loading surfaces (flat) to decrease flange and wheel loads during a fall event.

Provide enclosed anchor tracks held by pivot hanger assemblies bolted to swing arms mounted to existing structures or mast weldments.

2.3.1 Swing Arms

Two bolt-together weldments that form an inverted-L. Includes wall brackets (two per swing arm) consisting of a formed channel, a fabricated steel tube bracket, two bronze bushings, and bolt to allow rotation.

2.3.2 Pivot Hanger Assemblies

Provide a rigid connection for suspending tracks and movement necessary to fold away. Assembly to consist of beam to track bolt assemblies and tube brackets.

2.3.3 Track

Enclosed cold-formed steel track and permits trolley(s) to ride on lower inside flanges. Fabricated lower running flanges with a flat surface for higher durability and wheel contact. Sloped flanges are not permitted.

SECTION 11 81 28 Page 4

2.3.4 Track Splice

Includes truss splice plates and channel-shaped track splice joints for joining track sections. Splice joints must be located within four feet of a support point.

2.3.5 Standard Track Cantilevers

A maximum of 18 inches of cantilever is allowed from a hanger location to the end of the track. Up to 12 inches of cantilever is allowed from a hanger location to the end of the plain track.

2.3.6 Swiveling Connector

Rigid-body trolley designed to ride inside enclosed track and to carry load. Provide anchor trollies are to be built with non-consumable parts and a fault indicator that appears if an internal spring breaks. When at least 80 pounds of force, including the weight of the self-retracting lanyard, are exerted on the swiveling connector, the brakes shall engage.

2.3.6.1 Construction

Steel body with two wheels on each side and positioning attachment point at center of trolley so load weight is evenly distributed to trolley wheels.

2.3.6.2 Braking System

If at least 80 pounds of force, including the weight of the self-retracting lanyard, are exerted on the swiveling connector, a series of eight hardened-alloy steel contact points create friction against the enclosed track. The friction generated by the contact points, in conjunction with the weight of the worker, shall causes the trolley to stop all movement on the track.

2.3.6.3 Wheels

Removable, self-centering wheels with sealed lifetime lubricated bearings.

Vertical wheels shall be flat to match track profile. Non-removable or tapered wheels are not acceptable. Provide polyamide wheel material.

2.3.6.4 Design

Designed for attachment of carabiner.

2.3.6.5 End Stops

Molded composite resilient bumper installed in track to prevent end trucks from rolling out of track. Bolt stops without energy absorbing bumper are not acceptable.

2.3.7 Personnel Harness

Provide two personnel retraction harnesses per swing arm including accessories. Submit personnel harness. Submit product data for personnel harness and accessories .

SECTION 11 81 28 Page 5

2.3.8 Retraction Systems and Arresting Cables

Provide two retraction systems and arresting cables per swing arm. Submit product data for retraction system and arresting cables .

2.4 SHOP FINISHING

2.4.1 Paint System

a. Paint all systems with one coat of safety yellow industrial enamel.

b. Adhere to the standards of the Society for Protective Coatings (SSPC) for all product surface preparation.

c. Debur and descale using power tools equipped with sanding discs and wire wheels prior to painting.

d. Wash all components with a high-pressure/high temperature biodegradable decreasing solution.

e. Paint all components with quick drying semi-gloss enamel applied to a minimum dry-film thickness of two to three mils.

f. Apply finishing coat with a hot, airless, electrostatic spray paint system. Painted components are cured at air temperature.

PART 3 EXECUTION

3.1 EXAMINATION

3.1.1 Project Conditions

Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer. Do not install products under environmental conditions outside manufacturer’s absolute limits.

3.2 PREPARATION

3.2.1 Protection

Do not start installation until support structures are properly prepared.

Verify all materials and ensure all parts are present prior to commencement of work.

3.3 INSTALLATION

Install in accordance with manufacturer's assembly and operation instructions manual. Do not modify system components without manufacturer's approval. Check electrical supply, conduit, wiring, disconnect switch, and other electrical components prior to starting work.

3.3.1 Swing Arm Installation Column-Mounted Fold-Away System

Bolt the boom weldments to the column weldments to form the inverted-L shaped swing arms. Verify adequate span and ceiling clearances before proceeding. Hold top wall bracket against supporting column in its proper location with a C-clamp or other supporting method. Establish the correct distance from the top wall bracket to the bottom wall bracket. Hold the

SECTION 11 81 28 Page 6 bottom wall bracket against the supporting column with a C-clamp or other supporting method. Check the alignment of the bottom bracket with the top bracket in two planes. The alignment shall be within 1/16-inches from top to bottom. Using the wall brackets as templates, mark the established hole locations. Drill the holes in the column for the wall brackets. Mount the wall brackets to the column with bolts supplied by the installer. Ensure all bolts are properly tightened. Lift the assembly with its bearings attached into place. Insert bolt through bracket. Ensure thrust plate is properly located at the bottom of each bearing. Torque the nut to manufacture's specifications.

3.3.2 Enclosed track installation

Raise the track and attach it to the swing arms with the appropriate fasteners. Torque bolts to specifications.

3.3.3 Swiveling Connector Anchor Trolley Installation

Install swiveling connector Anchor Trolley on track. Secure end stops bolts and rubber bumpers. After installation is complete, enclosed tracks should be leveled. Check tightness for all bolts and nuts. Torque locknuts, bolts, and flat washers to appropriate specifications. Install with an ANSI-rated self-retracting lanyard (SRL). Connect SRL and retrieval tagline in accordance with manufacturer's specifications.

3.4 FIELD QUALITY CONTROL

3.4.1 Inspection

3.4.1.1 Acceptance Inspection

After the system has been installed and after any modifications, an acceptance inspection must be performed using the After a Fall Event and Annual Anchor Track System Inspection Checklist included in the Assembly and Operation Instruction Manual before use. The manufacturer's approved installer shall perform the acceptance inspections. Submit a copy of the manufacture's acceptance inspection report to the contracting officer.

3.4.1.2 Inspection Procedure

a. Verify that the beam clamps are installed horizontal within + / - five degrees.

b. Verify that end stop bolts are present and have locknuts installed.

c. Using a torque wrench, check that all bolts are present and torqued to values shown on Assembly Drawing.

d. Check that splices are centered on track joints.

e. Verify that capacity labels are present, attached, and legible. See Label Placement Drawing. Verify that the number of trolleys matches the value on the capacity label.

f. Verify that the fall arrest system is not being used for material handling.

g. Check the track for levelness within + / - 1/4 inches per 20 feet of track.

SECTION 11 81 28 Page 7

h. Verify the track flanges. Track flanges cannot be bent downward more than five degrees.

i. Check all system welds for cracks.

j. Check system components for corrosion and bent or damaged areas.

k. Verify that all wheel studs, if supplied, are torqued to value shown on Assembly.

l. Verify trolley can traverse entire length of track without snags.

m. Check trolley for visibly bent swiveling connector, broken welds, or corrosion.

n. Test the operation of the trolley's swiveling connector and verify that it can rotate freely. Test the operation of the trolley and verify the wheels rotate freely.

o. Check system components for loose components or missing fasteners.

p. Check system support structure for stability. Verify that hanger assemblies are installed properly, and fasteners are torqued to proper values. Check system for unauthorized modifications. System modification are not authorized.

3.5 ADJUSTING AND CLEANING

Clean all surfaces of dirt dust, grease and oil residue. Touch up scratches and blemishes with matching paint from manufacturer.

3.6 CLOSEOUT ACTIVITIES

3.6.1 Training

Manufacturer's representative shall provide 4 hours of training to the government staff in the use and operation of the system. Include persons impressible for maintenance of the system. Submit 4 copies of users operational instructions . Submit 4 copies of maintenance schedule and procedures .

3.7 PROTECTION

Cover and protect system surfaces until building is turned over to the government.

-- End of Section --

SECTION 11 81 28 Page 8

SECTION 41 22 13.14

BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN GEAR MANUFACTURERS ASSOCIATION (AGMA)

AGMA 908 (1989B; R 1999) Information Sheet:

Geometry Factors for Determining the Pitting Resistance and Bending Strength of Spur, Helical and Herringbone Gear Teeth

ANSI/AGMA 2001 (2004D; R 2010) Fundamental Rating Factors and Calculation Methods for Involute Spur and Helical Gear Teeth

ANSI/AGMA 2015-1 (2001A; R 2014) Accuracy Classification System - Tangential Measurements for Cylindrical Gears

ANSI/AGMA 6013 (2006A; R 2016) Standard for Industrial Enclosed Gear Drives

ANSI/AGMA 6113 (2016B) Standard for Industrial Enclosed Gear Drives (Metric Edition)

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 360 (2016) Specification for Structural Steel Buildings

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B30.2 (2017) Overhead and Gantry Cranes (Top Running Bridge, Single or Multiple Girder, Top Running Trolley Hoist)

ASME B30.10 (2019) Hooks

ASME HST-4 (2016) Performance Standard for Overhead Electric Wire Rope Hoists

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M (2020) Structural Welding Code - Steel

AWS D14.1/D14.1M (2005; Amd 1 2017) Specification for Welding of Industrial and Mill Cranes and Other Material Handling Equipment

SECTION 41 22 13.14 Page 1

ASTM INTERNATIONAL (ASTM)

ASTM A275/A275M (2018) Standard Practice for Magnetic Particle Examination of Steel Forgings

ASTM A668/A668M (2020) Standard Specification for Steel Forgings, Carbon and Alloy, for General Industrial Use

ASTM A931 (2008; R 2013) Standard Test Method for Tension Testing of Wire Ropes and Strand

ASTM A1023/A1023M (2019) Standard Specification for Stranded Carbon Steel Wire Ropes for General Purposes

ASTM E125 (1963; R 2013) Photographs for Magnetic Particle Indications on Ferrous Castings

ASTM E543 (2015) Standard Practice for Agencies Performing Non-Destructive Testing

ASTM E1417/E1417M (2016) Standard Practice for Liquid Penetrant Testing

ASTM F3125/F3125M (2015a) Standard Specification for High Strength Structural Bolts, Steel and Alloy Steel, Heat Treated, 120 ksi (830 MPa) and 150 ksi (1040 MPa) Minimum Tensile Strength, Inch and Metric Dimensions

CRANE MANUFACTURERS ASSOCIATION OF AMERICA (CMAA)

CMAA 70 (2015) Specification for Top Running Bridge and Gantry Type Multiple Girder Electric Overhead Traveling Cranes

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA 250 (2018) Enclosures for Electrical Equipment (1000 Volts Maximum)

NEMA ICS 5 (2017) Industrial Control and Systems:

Control Circuit and Pilot Devices

NEMA ICS 6 (1993; R 2016) Industrial Control and Systems: Enclosures

NEMA ICS 8 (2011) Crane and Hoist Controllers

NEMA MG 1 (2018) Motors and Generators

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2019; TIA 19-1; TIA 19-2; TIA 19-3; TIA

19-4; ERTA 1 2019) National Electrical Code

SECTION 41 22 13.14 Page 2

RESEARCH COUNCIL ON STRUCTURAL CONNECTIONS (RCSC)

RCSC S348 (2014; Errata 2015) RCSC Specification for Structural Joints Using High-strength Bolts

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)

29 CFR 1910.179 Overhead and Gantry Cranes

29 CFR 1910.306 Specific Purpose Equipment and Installations

UNDERWRITERS LABORATORIES (UL)

UL 50 (2015) UL Standard for Safety Enclosures for Electrical Equipment, Non-Environmental Considerations

UL 489 (2016) UL Standard for Safety Molded-Case Circuit Breakers, Molded-Case Switches and Circuit-Breaker Enclosures

UL 943 (2016; Reprint Feb 2018) UL Standard for Safety Ground-Fault Circuit-Interrupters

UL 1004-1 (2012; Reprint Aug 2017) UL Standard for Safety Rotating Electrical Machines - General Requirements

UL 1449 (2014; Reprint Jul 2017) UL Standard for Safety Surge Protective Devices

1.2 DEFINITIONS

a. Bridge Crane: That part of an overhead crane system consisting of girder(s), end trucks, end ties, walkway, and drive mechanism which carries the trolley(s) and travels along the runway rails parallel to the runway.

b. Crane Runway: The track system along which the crane operates horizontally, including track hangar rods, track connection devices, and runway structural supports.

c. Dead Loads: The loads on a structure which remain in a fixed position relative to the structure.

d. Girder: The principal horizontal beam of the crane bridge. It is supported by the crane end trucks.

e. Lifted Load: The load consisting of the rated load and the weight of lifting devices attached to the crane such as the load block, bucket, or other supplemental devices.

f. Pendant: A control for a hoist and a crane. The pendant hangs from

SECTION 41 22 13.14 Page 3 the hoist or the crane by a cable at a height that is easy for the operator to reach.

g. Rated Load: The maximum working load suspended under the load hook.

h. Standard Commercial Cataloged Product: A product which is currently being sold, or previously has been sold, in substantial quantities to the general public, industry or Government in the course of normal business operations. Models, samples, prototypes or experimental units do not meet this definition. The term "cataloged" as specified in this section is defined as "appearing" on the manufacturer's published product data sheets. These data sheets must have been published or copyrighted prior to the issue date of this solicitation and have a document identification number or bulletin number.

i. Top Running Crane: An electric overhead traveling crane that runs on rails on top of support girders.

j. Trolley Load: Weight of the trolley and its associated equipment carried by the trolley wheels.

k. Operating Environments:

(1) General Purpose Service: This applies to most cranes and are, in large measure, the manufacturers' standard designs. Cranes should be classified as General Purpose Service if they are operating in routine environments.

1.3 SYSTEM DESCRIPTION

The requirements for the crane runway system and rail supporting structures are specified in Section 05 12 00 STRUCTURAL STEEL, and must conform to AISC 360 .

1.3.1 Crane Design Criteria

Cranes will operate in the given spaces and match the runway dimensions and rails indicated. Hook coverage, hook vertical travel, clear hook height, lifting capacity, and load test weight must not be less than that indicated.

1.3.1.1 General

The number of cranes, <am#0006> there their </am#0006> locations and <am#0006> there their </am#0006> spans are located on the drawings for each of the two buildings #551 and #561, with the capacity expressed in 20 tons <am#0006>pounds </am#0006> , for each overhead electric traveling (OET) crane. Also clearly locate and identify each multiple girder hoist and system components.

1.3.1.2 Classification

Provide top running overhead electric traveling (OET) multiple girder cranes conforming to CMAA 70 service class D for operation in an indoor environment, general purpose service, meeting the requirements of ASME B30.2 , with an ambient temperature range of <am#0004>Neg 10 <am#0011> to </am#0011> Pos 12020 </am#0004> <am#0011> to <am#0011> <am#0010> 120 </am#0010> degrees Fahrenheit . <am#0004> The crane span must be 34 feet 4 inch with a vertical lift of 20 feet and as specified herein The crane span

SECTION 41 22 13.14 Page 4 shall be equal in all framing bays and must be a minimum of 34 feet 4 inch with a vertical lift of 20 feet and as specified herein. Coordinate final crane span with steel framing system . <am#0007>

The crane must be pendant controlled and radio controlled and operate in the spaces and within the loading conditions indicated. The pendant controller must be mounted on a separate festooned cable system from the trolley power supply. The crane must operate on 460V-volts AC, 60 Hz, three phase power source. Maximum crane wheel loads (without impact) due to dead, trolley, and lifted loads, with the trolley in any position, must not cause a more severe loading condition in the runway support structure than that produced by the design wheel loads and spacing indicated.

1.3.1.3 Rated Capacity and Speeds

Provide crane with rated capacity of 20 tons <am#0006> pounds </am#0006> .

Lower load block or assembly of hook, swivel bearing sheaves, pins, and frame suspended by the hoisting ropes are not considered part of the rated capacity.

Rated (maximum) speeds plus or minus 10 percent (feet/min) for the main hoist, bridge, and trolley at the rated load are specified in the table below. The minimum speed must not exceed the values listed. Values in the table are for a fully loaded crane. <am#0006> Using overspeed, the hoist function must be capable when not loaded. </am#0006>

SECTION 41 22 13.14 Page 5

Rated Speeds feet/min

Description Minimum Maximum

Main Hoist VFD infinitely variable 0 12

Trolley VFD infinitely variable 0 65

Bridge VFD infinitely variable 0 120

1.4 VERIFICATION OF DIMENSIONS

The Contractor is responsible for the coordination and proper relation of their work to the building structure and to the work of all trades.

Verify all dimensions of the building that relate to fabrication of the crane and notify the Contracting Officer of any discrepancy before finalizing the crane order.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Overhead Electric Traveling Crane ; G

Complete Schematic Wiring Diagram ; G

SD-03 Product Data

Gear Reducers ; G

Hoist Brakes ; G

Travel Brakes ; G

Couplings ; G

Load Blocks and Hooks ; G

Wheels ; G

Hoists ; G

Sheaves ; G

Commercial Hoist and Trolley Units ; G

End Trucks ; G

Bridge Rails ; G

SECTION 41 22 13.14 Page 6

End Stops ; G

Bumpers ; G

Variable Frequency Drives ; G

Motors ; G

Runway Conductor System ; G

Bridge Conductor System ; G

Limit Switches ; G

Radio Control System ; G

Pendant Pushbutton Station ; G

Pendant Conductor System ; G

Controls ; G

Control Parameter Settings ; G

Runway Conductor System ; G

Bridge Conductor System ; G

Capacity Overload Protective Device ; G

Load Indicating Device ; G

Painting System ; G

SD-05 Design Data

Load and Sizing Calculations ; G

SD-06 Test Reports

Hook Proof Test ; G

Hook Non-destructive Test (NDT) ; G

Post-erection Inspection ; G

Operational Tests ; G

Hook Tram Measurement ; G

Load Tests ; G

SD-07 Certificates

Wire Ropes ; G

Crane Runway System ; G

SECTION 41 22 13.14 Page 7

Hazardous Material ; G

Loss of Power Test ; G

Coupling Alignment Verification Record ; G

Overload Test ; G

Brake Adjustment Record ; G

Compliance with Listed Standards ; G

SD-10 Operation and Maintenance Data

Operation and Maintenance Manuals ; G

1.6 QUALITY ASSURANCE

1.6.1 Manufacturer Qualification

Overhead Electric Traveling Crane must be designed and manufactured by a company with a minimum of 10 years of specialized experience in designing and manufacturing the type of overhead crane required to meet requirements of the Contract Documents. Crane design shall be accomplished by, or directly supervised by, a registered professional engineer (PE). PE licensing must be by a board or agency authorized to license and register professional engineers. The PE may be a Contractor's regular employee or a consultant. The PE's review and attestation of specification compliance and professional responsibility must be signified by his or her PE original seal and dated signature on the final drawings. The professional engineers must only undertake and perform work under this contract in the branch(s) of engineering in which they are licensed.

1.6.2 Pre-Delivery Inspections

Contractor is responsible for performance of quality control inspections, testing, and documentation. Submit all crane test data recorded on appropriate test record forms suitable for retention for the life of the crane.

1.6.2.1 Inspection of Steel Castings

Visually inspect and test load-carrying steel castings using the magnetic-particle inspection method or using ultrasonic testing.

Reference allowable degree of discontinuities to ASTM E125, and relationship to service loads and stresses, critical configuration, location and type. All load bearing components, couplings, shafts, and gears, in the hoist drive train must be rolled or forged steel, except brake drums which may be ductile iron. Methods of repairing the discontinuities is subject to review by the Contracting Officer.

1.6.2.2 Inspection of Hook Assembly

<am#0007>Inspect hook by a magnetic-particle type inspection and X-rayed and tested ultrasonically prior to delivery Inspect hook by a magnetic-particle type inspection prior to delivery </am#0007> . Furnish documentation of hook inspection to Contracting Officer prior to field operational testing. As part of the acceptance standard, linear indications are not allowed. Welding repairs of hook are not permitted. A hook showing

SECTION 41 22 13.14 Page 8 linear indications, damage or deformation is not acceptable and must be replaced immediately.

1.6.2.2.1 Hook Non-Destructive Test (NDT)

Magnetic-particle inspect the hook over the entire area in accordance with ASTM A275/A275M . Acceptance standard is no defects. A defect is defined as a linear indication that is greater than 1/16 inch long. For hooks of non-magnetic material, NDT will be liquid penetrant (PT) method in accordance with ASTM E1417/E1417M . For PT testing of hooks containing stainless steels, titanium, or nickel based alloys, total halogens and Sulphur used in the NDT process must be controlled as specified in

T9074-AS-GIB-010/271.

Inspect each hook and shank over the entire surface area by magnetic particle inspection.

a. Procedure: Conduct magnetic particle inspection in accordance with ASTM A275/A275M with the following restrictions: Do not use DC yokes (including switchable AC/DC yokes used in the DC mode) or permanent magnet yokes. Do not use automatic powder blowers or any other form of forced air other than from a hand-held bulb for the application or removal of dry magnetic particles. Remove arc strikes. Equipment ammeters must have an accuracy of plus or minus 5 percent of full scale (equipment ammeter accuracy other than that stated is acceptable provided the MT procedure states that a magnetic field indicator is used to establish and verify adequate field strength for all aspects of the inspection.)

b. Acceptance Criteria: Defects found on the hook will result in rejection of defective items for use on furnished hoist. For this inspection, a defect is defined as a linear indication for which the largest dimension is greater than 1/16 inch .

c. Test Report: Submit a test report of the magnetic particle inspection of each hook provided the Contracting Officer for approval prior to final acceptance of hoist installation. Certify test reports by the testing organization. The performing organization must provide a written statement of certification to ASTM E543, current within one year of the date the NDT was performed. The NDT procedures including technique sheets specific to the types, shapes, and size of the parts being examined must adequately describe the orientation of the hooks within the magnetizing equipment. The performing organization must have the NDT procedures and its technique sheet used for testing of the hook reviewed and approved by an independent Level III examiner.

Submit the (Level III examiner) approved procedures, technique sheet, and certification to the Contracting Officer with the test report.

1.6.2.3 Hook Proof Test

Proof test the load hook per ASME B30.10 . Perform the proof test prior to Hook NDT.

1.6.3 Certificates

All certifications must be dated and bear the original signature (above the printed name) of the authorized representative of the Contractor or the manufacturer of the items or equipment being certified. Each certification will clearly identify the crane, the drives, components, and

SECTION 41 22 13.14 Page 9 location (as applicable) to which it applies:

a. Submit a Wire Ropes Certification with the wire rope manufacturer's certification that the rope meets the published breaking strength or the actual breaking strength of a sample taken from the reel and tested. Certification is to be traceable to the hoist, crane, and reel.

b. Submit a Crane Runway System Certificate stating that the new crane will operate properly on the runway; if the crane(s) cannot operate without restriction, the Contractor must indicate crane limitations.

c. Submit a Hazardous Material Certificate that the crane does not contain hazardous material including asbestos, lead, cadmium, chromium, PCBs, or elemental mercury. Products required for the designing and manufacturing of cranes must not contain the prohibited materials.

d. Submit a Loss of Power Test Certificate stating that a test may be performed in which power is removed from the crane while the hoist, bridge, and trolley are in operation.

e. Submit a Certificate of the Coupling Alignment Verification Record .

f. Submit an Overload Test Certificate stating that the crane can be periodically load tested to 125 percent (plus 0 minus 5 percent) of rated load.

g. Submit an Overload Test Certificate stating that the crane can be periodically load tested to 125 percent (plus 0 minus 5 percent) of rated load.

h. Submit a Certificate of the Brake Adjustment Record . Provide a brake adjustment record and installation/maintenance manuals for each brake on the crane. Each brake measurement must have a tolerance traceable to the associated brake manual or documentation provided by the brake manufacturer, location of measurements, and the actual brake setting.

Changes made to settings of the brake, at any time, will void the record.

i. Submit a Certificate of Compliance with Listed Standards

1.6.4 Drawings: Overhead Electric Traveling Crane

a. Submit drawings showing the general arrangement of all components in plan, elevation, and end views. Show all major features of the crane including: hook approaches on all four sides, clearances and principal dimensions, assemblies of hoist, trolley and bridge drives, motor nameplate data, overcurrent protective device ratings, and electrical schematic drawings. Include weights and centers of gravity of major components. Provide maximum wheel loads (without impact) and spacing imparted to the crane runway system track beams. Indicate the crane speeds along the runway, the trolley speeds along the bridge girder, and the hoist lifting speeds; all speeds indicated are speeds with hoist loaded with rated crane capacity load.

b. Submit shop drawings of all fabricated components. Shop drawing quality must be equivalent to the contract drawings accompanying this solicitation. Drawings must be reviewed, signed, and sealed by a

SECTION 41 22 13.14 Page 10 registered professional engineer.

c. Provide integral schedule of crane components on each drawing. The schedule must provide a cross reference between manufacturer data and shop drawings. Components listed on the schedule of crane components must include total quantity, description, original manufacturer, and part number. Distributing agents will not be acceptable in lieu of the original manufacturer.

1.6.5 Design Data: Load and Sizing Calculations

Submit complete list of equipment and materials, including manufacturer’s descriptive data and technical literature, performance charts and curves, catalog cuts, and installation instructions. Submit calculations reviewed, signed, and sealed by a registered professional engineer verifying the load cases, sizing of the bridge girders, end trucks, travel drives, brake selections, and overcurrent protection for motors, controllers, and branch circuits. Provide a list of all codes and standards, design assumptions, equations, specified efficiencies, limits, factors of safety, component ratings, and sources of values used. Include free body diagrams or sketches of each load case.

1.6.6 Welding Qualifications and Procedures

Welding must be in accordance with qualified procedures using AWS D14.1/D14.1M as modified. Written welding procedures must specify the Contractor's standard dimensional tolerances for deviation from camber and sweep and not exceed those specified in AWS D14.1/D14.1M and CMAA 70.

Welders and welding operators must be qualified in accordance with AWS D1.1/D1.1M or AWS D14.1/D14.1M .

1.7 CRANE SAFETY

Comply with the mandatory and advisory safety requirements of ASME B30.10 , ASME B30.2 , ASME HST-4, CMAA 70, 29 CFR 1910.147 , 29 CFR 1910.179 , 29 CFR 1910.306 , and all applicable provisions of 29 CFR 1910 and NFPA 70 .

PART 2 PRODUCTS

2.1 ACCEPTABLE PRODUCTS

2.1.1 Acceptable Manufacturers

Bridge crane shall be provided by acceptable manufacturer or approved equal. The basis of design manufacturer is not intended to limit other manufactures provided they meet or exceed the performances and other salient characteristics specified herein.

1. Equipment Fabricators, Inc. (Basis of Design)

2. Ace Industries (Gaffey), Inc.

3. OMi Crane Systems, Inc.

2.2 MATERIALS

2.2.1 General

Provide materials and equipment which are standard products of manufacturers regularly engaged in the fabrication of complete and totally functional cranes including necessary ancillary equipment. Material will

SECTION 41 22 13.14 Page 11 be free from defects and imperfections that might affect the serviceability and appearance of the finished product. All material must be new and unused.

2.2.2 Nameplates

Secure nameplates to each major component of equipment with the manufacturer's name, address, type or style, model or catalog number, and serial number. Provide two bridge identification plates, one for each side of the bridge. Provide noncorrosive metal identification plates with letters which are easily read from the floor, showing a separate number such as BC-1, BC-2, for each bridge crane.

2.2.3 Capacity Marking

Mark the rated capacity in <am#0006> 20 ton pounds </am#0006> units on each side of the crane on the bridge girders. Capacity marks must be large enough to be clearly visible from the floor. The markings must be positioned to be visible at the operator's position after the crane has been installed.

2.2.4 Safety Warnings

Affix labels in a readable position to each lift block or control station in accordance with ASME B30.2 . Submit safety warnings, diagrams and other instructions suitably framed and protected for display as indicated by the Contracting Officer as follows:

Design and locate the word "WARNING" or other legend to bring the label to the attention of the operator. Provide durable type warning labels and display the following information concerning safe-operating procedures:

Cautionary language against lifting more than the rated load; operating the hoist when the hook is not centered under the hoist; operating hoist with twisted, kinked or damaged rope; operating damaged or malfunctioning hoist; operating a rope hoist with a rope that is not properly seated in its hoist drum groove; lifting people; lifting loads over people; and removing or obscuring the warning label.

2.3 STRUCTURAL REQUIREMENTS

Structural requirements must be in accordance with CMAA 70, Section 3.

Structural steel materials must conform to the standards permitted in CMAA 70 and AISC 360 .

2.3.1 Structural Connections

High-strength bolted structural connections must be designed and installed in accordance with RCSC S348. Bolts must be of ASTM F3125/F3125M Grade A325/A325M or Grade A490/A490M material. Galvanized bolts are not acceptable.

Welded connections must be performed in accordance with AWS D14.1/D14.1M .

Allowable stress values must comply with CMAA 70.

2.3.2 Bridge Girder or Girders

Provide wide flange beam, standard I-Beam, or section fabricated from rolled plates and shapes bridge girders. If the ends of bridge girders are notched to fit over the end trucks, the notches must be reinforced

SECTION 41 22 13.14 Page 12 with vertical diaphragms and horizontal stiffeners.

2.3.3 Bridge Rails

Provide bridge rails, crane girders and other sections that are straight and true. Make all rail joints flush and true without misalignment of running tread and design to minimize vibration. The gap between adjacent rail ends and the vertical misalignment of running treads shall not exceed 1/32 inch . Solid stock (e.g. square bar, roundstock) is not permitted as bridge rail. Center bridge rail on top flange or position bridge rail over girder web for torsion box girders. Fasten rail to girder with welded clips. Position rail clips in pairs and at not more than 36 inches on center. Bolt bridge rail joints using standard joint bars. Stagger and position rail joints directly over girder diaphragms. Provide a positive stop at bridge rail ends to prevent creep.

2.3.4 End Ties and Bridge Girder End Connections

If equalizing end trucks are used, provide rigid end ties between girders to form a frame that is rigid about the vertical and horizontal axes. If compensating end trucks are used, provide end ties which are rigid about the vertical axis but relatively flexible about the horizontal axis to permit partial rocking motion for wheel load compensation. Provide full depth diaphragms at girder connections and jacking points. Provide horizontal gusset plates at the elevation of top and bottom end tie flanges for connection to girder ends. Make end connections with high-strength bolts in accordance with the Structural Connections section of this specification. Use tapered alignment pins to maintain original shop alignment between bridge girders and end ties/trucks.

2.3.5 End Trucks

Provide rotating or fixed axle type end trucks fabricated from structural steel plate to provide a rigid box section structure. Center wheels between the webs of the box section. Configure bridge and trolley trucks with a feature that limits load movement to 1 inch in the event of wheel or shaft failure. Provide jacking pads for removal of wheel assemblies.

Wheel axle bearing seats must be designed such that wheel and axle bearing assembly can be removed with not more than 3 inches of jacking.

2.3.6 Trolley Frame

Provide trolley frame as a one-piece structural steel weldment. Provide pads for the use of jacks or wedges when changing truck wheels. Make all trolley yokes and load bars of drop forged, cast or rolled steel. Equip trolley with permanent lifting attachments.

2.3.7 End Stops and Bumpers

Fit bridge girders with structural steel end stops. Locate stops to permit maximum trolley travel. Fit bridge end trucks and trolley frames with shock-absorbing bumpers capable of decelerating and stopping the bridge and trolley within the limits stated by 29 CFR 1910 and CMAA 70.

Bumpers must fully engage end stops. Mount bumpers so that there is no direct shear on mounting bolts (if any) upon impact. Bumpers must provide adequate clearance between the crane and surrounding structure when compressed to preclude damaging equipment. Ensure bridge and trolley bumper retention in accordance with ASME B30.2 . When more than one crane is located and operated on the same runway, bumpers shall be provided on

SECTION 41 22 13.14 Page 13 their adjacent ends or on one end of one crane. Fit the other end of the end-truck with a structural steel stop to engage the bumpers of the adjacent crane. Ensure bridge bumpers are properly aligned with runway end stops. Metal to metal contact at the bumper to end stop connection is not permitted.

2.4 MECHANICAL REQUIREMENTS

a. Provide steel shafts, gears, keys, and couplings. Cast iron and aluminum used to support components of the hoist power transmission train must be ductile. Gray cast iron load bearing parts are prohibited.

b. All bearings, except those subject only to small rocker motion, must be anti-friction type. All connections subject only to small rocking motion are to be fitted with bushings or thrust washers in the pivot pin bore, as applicable. Bronze bushings must have provisions for grease lubrication.

c. All mechanical components must be accurately aligned and positively secured to maintain the alignment. Parts must not be forced into position to obtain apparent alignment.

2.4.1 Hoists

Provide hoist conforming to ASME B30.2 and CMAA 70 service class D or better, double reeved, except as modified and supplemented in this section. Standard commercial hoist and trolley units (packaged hoists), if used, must meet ASME HST-4 Duty Class H4 or better. For custom hoist shafts, the fatigue design factor must be a minimum of 1.5.

2.4.2 Drives

2.4.2.1 Bridge Drives

Provide A-4 bridge drive arrangement as specified in CMAA 70 consisting of a single electric motor mechanically connected through gear reduction and drive shafts to the drive wheels or separate drive motors at each end of bridge. Outdoor cranes must have half of the total wheels driven.

Acceleration and deceleration must meet the requirements specified in this section. Gears must conform to applicable AGMA standards. Provide oil tight fully enclosed gear reducers with pressure or splash type lubrication. Bridge travel limit switches are required.

2.4.2.2 Trolley Drives

Provide complete trolley drive arrangement with a minimum of two wheels driven by an integral electric motor. Drive mechanism must run in totally enclosed oil bath. Limit switches are required for drive mechanism.

Acceleration and deceleration controls must meet requirements specified in this section.

2.4.3 Load Blocks and Hooks

The load block must be constructed of steel <am#0004> non-sparking materials </am#0004> and designed to prevent steel-to-steel contact of moving parts. The block must be fully enclosed, concealing the sheaves and wire ropes, except for wire rope slots and drain holes. The block

SECTION 41 22 13.14 Page 14 must be clearly marked with the capacity in pounds on both sides. The load block sheaves must be constructed of <am#0004>non-sparking materials steel </am#0004> .

Provide an unpainted single barbed forged steel hook complying with ASTM A668/A668M . Provide an unpainted single barbed hook <am#0004> made of non-sparking material steel </am#0004> with a minimum material longitudinal elongation of 16 percent in 2 inches.