F. Schedule of Material Submittals.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
Repair_Replace Liner, Wastewater Lagoon One Federal contract opportunity
Solicitation number
FA309923R0002
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 14-1022 PROJECT TITLE Repair/ Replace Wastewater Lagoon One SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALLAUGHLIN DIV 01 SPECIFICATIONSENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBSTATEMENT OF OBJECTIVESNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

NTP 1 - Design
1Proof of OPSEC Training2.42 Weeks prior to base accessTraining must be completed by all who have access to Controled Information.
235% Design Package3.2.11 (drawing only)NLT 30 Days after NTP 1
365% Design Package3.2.21 (drawing only)NLT 45 Days after Acceptance of 35% Design Submittal
495% Design Package3.2.31 (drawing only)NLT 35 Days after Acceptance of 65% Design Submittal
5Statement of Work3.2.9NLT 110 Days after NTP 1
6100% Design Package3.2.41NLT 25 Days after Acceptance of 95% Design Submittal
7Progress Schedule Form and Contract Progress Report6.1.17.1.1Biweekly
NTP 2 - Pre Construction
8AF Form 103, Work Clearance Request2.2NLT 1 week after NTP 2
9Contractor Safety Plan3.2.2NLT 2 weeks after NTP 2
10Certificate of Contractor Safety Compliance3.2.3NLT 7 days after NTP 2
11QC Manager Qualifications4.2.3NLT 7 days after NTP 2
12QC Plan4.2.4NLT 3 weeks after NTP 2
13Construction Site Plan12.1NLT 30 days after NTP 2
14Hazardous Material Approval (Safety Data Sheets)3.2.1NLT 30 days after NTP 2 (as required)
15Hazardous Waste Training Certificate3.2.2NLT 30 days after NTP 2 (as required)
16Laydown Area Request3.3.114 days prior to mobilization (as required)
17Public Water System Notification3.4.1NLT 30 days after NTP 2 (as required)
18Customer Service Inspection Certificate (TCEQ Form 20699)3.4.1NLT 3 weeks after NTP 2 (as required)
19TCEQ Public water system plan review submittal form (TCEQ Form 10233)3.4.1NLT 30 days after NTP 2 (as required)
20Clean Water Act TCEQ’s General Permit3.4.2NLT 30 days after NTP 2 (as required)
21Copy of notification to Department of State Health Services3.5.2.1NLT 10 days prior to construction start
22Worker/Area Protection Plan3.5.2.2NLT 3 weeks after NTP 2 (as required)
23Submittals per Contractor's Design / SOW10.4.4 through 10.4.113TBD
NTP 3 - Construction
24Non-Hazardous Waste Disposal Manifest and/or Waste Shipment Record5.1/6.2NLT 45 days from the date of signature of receiving facility
25Hazardous Waste Disposal Manifests5.2/6.2As required, prior to removal from Government property
26Hazmat Usage Log6.1End of each month during construction
27QC Daily Inspection Reports4.2.6Weekly
28Progress Schedule Form and Contract Progress Report6.1Biweekly
29Records of Existing Conditions7.1.1NLT 14 days after NTP 2
30Materials Testing7.1.3As required, within 7 days of test
31Submittals per Contractor's Design SOW10.4.4 through 10.4.112TBD
32Operation and Maintenance Data10.4.12NLT 2 weeks after Final Inspection
33As Built Drawings/CAD Files10.4.133.32 (D size)NLT 2 weeks after Final Inspection
34Completion Inspection (QC Manager Punchlist)13.46.7, 6.8NLT 3 days after Pre-Final Inspection
35Draft DD Form 135413.36.7Prior to Pre-Final Inspection
36Final DD Form 135413.36.8At Final Inspection
37Construction Warranty Management Plan13.2NLT 2 weeks after Final Inspection

Task Order # FA3099-16-D-0002-0002 SOW Atch 2

&"Times New Roman,Regular"&12Page &P of &N