Presolicitation Notice: ERCIP Lake City Army Ammunition Plant Microgrid and Combined Heat and Power
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912QR26RA041
- Agency
-
ENDIST Louisville
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- PSC
- Y1NZ Construction Of Other Utilities
- Place of performance
- Independence, Missouri, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers (USACE) Louisville District is soliciting proposals for the design, construction, and implementation of a microgrid system with combined heat and power (CHP) generation at Lake City Army Ammunition Plant through Request for Proposal W912QR26RA041. The project involves Design-Bid-Build construction services and is classified under Power and Communication Line and Related Structures Construction (NAICS 237130). Key requirements include the installation of two 7.5 MW CHP combustion turbines capable of operating on natural gas and propane fuel to produce 15 MW of combined power and heat, complete with heat recovery steam generators, supplemental exhaust duct firing, and a black start diesel generator. The microgrid control system must be state-of-the-art, capable of operating in parallel with existing utility infrastructure, island mode during grid outages, and black start mode, with seamless integration at four points of common coupling with existing substations. The pre-solicitation notice was posted on February 26, 2026, with a response deadline of March 13, 2026, providing interested parties with two weeks to submit questions or express interest prior to the formal RFP release.
This procurement carries no set-aside designation and is open to all qualified contractors. The project scope includes all necessary electrical distribution equipment, underground duct banks, piping infrastructure, and a new industrial-grade control room to be located in the central heating plant, with the microgrid operating in tandem with the installation's existing central heating plant. The solicitation does not identify any incumbent contractors or specific award value in the pre-solicitation notice. The contract will encompass comprehensive integration with the facility's existing natural gas, steam, condensate, and water infrastructure systems, along with environmental controls to ensure compliant operations. While specific budget or award information is not disclosed in this preliminary notice, the complexity and scope of the CHP and microgrid system installation suggests a substantial construction contract requiring significant technical expertise and capabilities in power generation and electrical infrastructure.
Notice text
****ATTENTION: This is an updated Presolicitation Notice which corrects the solicitation number and expected solicitation release date from the previous posting for the Lake City Army Ammuntion Plant Microgrid and Combined Heat and Power project.****
The U.S. Army Corps of Engineers (USACE) Louisville District intends to issue a Request for Proposal (RFP) W912QR26RA041 for the construction of the ERCIP Lake City Army Ammunition Plant Microgrid and Combined Heat and Power.
Description: The proposed project is a Design-Bid-Build construction of a microgrid system powered by two 7.5 MW combined heat and power (CHP) combustion turbines with dual-fuel capable natural gas and propane fuel systems that make a 15 MW CHP power/heat production plant. The CHP will include heat recovery steam generators (HRSGs) and supplemental exhaust duct firing along with a black start diesel generator. The project will include all electrical distribution equipment and underground duct bank needed to connect to the existing electrical infrastructure. Microgrid controls will be installed to manage various modes of operation to include parallel mode with existing utility, island mode, and black start mode. The microgrid control system will be state of the art and will be integrated with two existing substations at four points of common coupling for seamless operation and load shed capability with the ability to island during a utility grid outage and leverage load shedding to balance microgrid supply and demand during islanded operation, and resynchronization with the grid upon grid restoration.
The project will install all piping and equipment needed to connect the CHP to the installation’s existing natural gas, steam, condensate, and water infrastructure and operate in tandem with the installation’s existing central heating plant. The microgrid will have industrial grade controls with a new control room located in the central heating plant. Environmental controls will be through the use of low NOx turbines and duct burners. The project also includes backup propane fuel storage/supply system, site improvements, demolition, full air permitting, communications, cybersecurity, and full commissioning.
The Contract Duration is one thousand fourteen (1014) calendar days from Notice to Proceed.
TYPE OF CONTRACT AND NAICS: This RFP will be for one (1) Firm-Fixed-Price (FFP) contract. The North American Industrial Classification System Code (NAICS) for this effort is 237130.
TYPE OF SET-ASIDE: This is will be a Unrestricted Full and Open procurement with hubzone price evaluation preference.
SELECTION PROCESS: This is a single phase, Design/Bid/Build procurement. The proposals will be evaluated using a Best Value Trade Off source selection process. The technical information contained in the Offeror's proposal will be reviewed, evaluated, and rated by the Government. The proposal for this procurement, at a minimum, will consist of the following: Volume I - Factor I – Past Performance, Factor II – Technical Approach. Volume II – Factor I – Price and Pro Forma Information. All evaluation factors, other than price, when combined, are considered approximately equal to cost or price.
DISCUSSIONS: The Government intends to award without discussions but reserves the right to conduct discussions should it be deemed in the Government's best interest.
CONSTRUCTION MAGNITUDE: The magnitude of this construction project is anticipated to be between $25 million and $100 million in accordance with DFARS 236.204. The magnitude of this project is expected to be at the upper end of this range.
ANTICIPATED SOLICITATION RELEASE DATE: The Government anticipates releasing the solicitation on or about 13 March 2026. Additional details can be found in the solicitation when it is posted to SAM.gov
SOLICITATION WEBSITE: The official solicitation, when posted, will be available free of charge by electronic posting only and may be found at Federal Business Opportunities website, SAM.gov. Paper copies of the solicitation will not be issued. Telephone and Fax requests for this solicitation will not be honored. Project files are Portable Document Format (PDF) files and can be viewed, navigated, or printed using Adobe Acrobat Reader. To download the solicitation for this project, contractors are required to register at System for Award Management (SAM) website at SAM.gov. Amendments, if/when issued, will be posted to the above referenced website for electronic downloading. This will be the only method of distributing amendments prior to closing; therefore, it is the Offerors responsibility to check the website periodically for any amendments to the solicitation.
REGISTRATIONS: Offerors shall have and shall maintain an active registration in the following database: System for Award Management (SAM): Offerors shall have and shall maintain an active registration in the SAM database at http://www.sam.gov to be eligible for a Government contract award. If the Offeror is a Joint Venture (JV), the JV entity shall have valid SAM registration in the SAM database representing the JV as one business/firm/entity. If at the time of award an Offeror is not actively and successfully registered in the SAM database, the Government reserves the right to award to the next prospective Offeror.
Cybersecurity Maturity Module Certification (CMMC): The Offeror shall have a current CMMC status at the following CMMC level, or higher: Level 2 (Self) for all information systems used in performance of the contract that process, store, or transmit FCI or CUI. See DFARS 252.204-7021.
Offerors will need to be registered in the Procurement Integrated Enterprise Environment (PIEE) at: https://piee.eb.mil. Then Navigate to the Supplier Performance Risk System (SPRS) to register for CMMC.
POINT-OF-CONTACT: The point-of-contact for this procurement is Contract Specialist Alexa Dukes at alexa.l.dukes@usace.army.mil.
This announcement serves as the Advance Notice for this project. Responses to this synopsis are not required.
Notice history
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Sources Sought -Building 493 Generator and Backup Power Installation- Red River Army Depot | ENDIST Fort Worth | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities