Pontiac ATCT Fire Life Safety Upgrades

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
697DCK-22-R-00560
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Waterford, Michigan 48327, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks proposals to complete fire life safety upgrades at the Airport Traffic Control Tower and terminal buildings located at Oakland County International Airport in Waterford, Michigan. The Department of Transportation Federal Aviation Administration Southwestern Region requires installation of a new fire detection and alarm system, modification of existing fire suppression systems, and additional upgrades to fire protection components. Proposals are due November 4th, 2022 and the selected contractor must complete all work within 150 calendar days while minimizing disruptions to airport operations. Evaluation will be based on technical qualifications, past performance, and price.

The opportunity is set aside for total small business concerns. The primary NAICS code is 238210 and PSC code R499 covers the fire protection work. The incumbent is the airport authority. All work must be finished by December 31st, 2023 at the listed airport address. The contractor will install a new fire alarm system, modify sprinklers, replace fire barriers and doors, seal openings, apply fireproofing, install related hardware and train staff to complete the life safety upgrades valued around $500,000.

Notice text

7 versions

Update #7 · Latest ·

Amendment 06: POsted 10/31/2022

Amendment 05: Posted 10/28/2022

Amendment 04: Posted 10/27/2022

Amendment 03: Posted 10/25/2022

Amendment 02; Posted 10/21/2022

Amendment 01:Posted 10/13/2022

These specifications and accompanying drawings describe the life-safety upgrade for the existing
Airport Traffic Control Tower’s (ATCT’s) and terminal buildings at the OAKLAND COUNTY
INTERNATIONAL AIRPORT (PTK) and further include all work necessary to improve the
architectural, mechanical, electrical, and fire protection systems to comply with OSHA regulation
29 CFR 1960.20. The work as generally outlined below shall include, but not be limited to:
a. Installation and testing of new fire detection/alarm system and demolition of the existing
fire alarm system in the ATCT and the terminal building.
b. Modifications to and testing of existing fire suppression system in the ATCT and the base
building as shown on drawings.
c. Installation of new fire-rated access doors, partitions, barriers and systems, etc., as shown
on drawings.
d. Replacement or modification, repair, patching, painting, refinishing, resurfacing of existing
walls, partitions, and/or ceilings, as required.
e. Sealing off existing and/or newly made penetrations or openings through walls, floors,
soffit, etc. with fire-stop sealant(s), caulks, mortars, mineral/ceramic wool, gypsum
wallboard, and/or masonry.
f. Application of sprayed-on fireproofing materials or intumescent paint to protect steel
structures or hatches as shown on drawings.
g. Installation of new louvers, dampers, fire doors, and related hardware and electrical gear,
or modification/repair of existing doors, dampers, etc., as r as shown on drawings.
h. Training for personnel assigned by the FAA.
i. Preparation of documentation describing as-built configuration and operation and
maintenance of systems and equipment and warranty of the work.
2. The Contractor shall provide all materials, labor, equipment and services, (except those
specifically referenced as Government-furnished to perform the work included in the
Construction Documents. The Contractor shall complete the construction in 150 calendar days,
start to finish.
3. The construction site is located at Oakland County International Aiport (PTK) at 6510 Highland
Rd, Waterford, MI 48327. The tower is defined as “Golemon-Rolfe” type tower. This facility is
active and operational. The Contractor shall comply with all procedures, rules and regulations of
the airport and FAA and shall minimize interference with the function of the facility.

Update #6 ·

Amendment 05: Posted 10/28/2022

Amendment 04: Posted 10/27/2022

Amendment 03: Posted 10/25/2022

Amendment 02; Posted 10/21/2022

Amendment 01:Posted 10/13/2022

These specifications and accompanying drawings describe the life-safety upgrade for the existing
Airport Traffic Control Tower’s (ATCT’s) and terminal buildings at the OAKLAND COUNTY
INTERNATIONAL AIRPORT (PTK) and further include all work necessary to improve the
architectural, mechanical, electrical, and fire protection systems to comply with OSHA regulation
29 CFR 1960.20. The work as generally outlined below shall include, but not be limited to:
a. Installation and testing of new fire detection/alarm system and demolition of the existing
fire alarm system in the ATCT and the terminal building.
b. Modifications to and testing of existing fire suppression system in the ATCT and the base
building as shown on drawings.
c. Installation of new fire-rated access doors, partitions, barriers and systems, etc., as shown
on drawings.
d. Replacement or modification, repair, patching, painting, refinishing, resurfacing of existing
walls, partitions, and/or ceilings, as required.
e. Sealing off existing and/or newly made penetrations or openings through walls, floors,
soffit, etc. with fire-stop sealant(s), caulks, mortars, mineral/ceramic wool, gypsum
wallboard, and/or masonry.
f. Application of sprayed-on fireproofing materials or intumescent paint to protect steel
structures or hatches as shown on drawings.
g. Installation of new louvers, dampers, fire doors, and related hardware and electrical gear,
or modification/repair of existing doors, dampers, etc., as r as shown on drawings.
h. Training for personnel assigned by the FAA.
i. Preparation of documentation describing as-built configuration and operation and
maintenance of systems and equipment and warranty of the work.
2. The Contractor shall provide all materials, labor, equipment and services, (except those
specifically referenced as Government-furnished to perform the work included in the
Construction Documents. The Contractor shall complete the construction in 150 calendar days,
start to finish.
3. The construction site is located at Oakland County International Aiport (PTK) at 6510 Highland
Rd, Waterford, MI 48327. The tower is defined as “Golemon-Rolfe” type tower. This facility is
active and operational. The Contractor shall comply with all procedures, rules and regulations of
the airport and FAA and shall minimize interference with the function of the facility.

Update #5 ·

Amendment 04: Posted 10/27/2022

Amendment 03: Posted 10/25/2022

Amendment 02; Posted 10/21/2022

Amendment 01:Posted 10/13/2022

These specifications and accompanying drawings describe the life-safety upgrade for the existing
Airport Traffic Control Tower’s (ATCT’s) and terminal buildings at the OAKLAND COUNTY
INTERNATIONAL AIRPORT (PTK) and further include all work necessary to improve the
architectural, mechanical, electrical, and fire protection systems to comply with OSHA regulation
29 CFR 1960.20. The work as generally outlined below shall include, but not be limited to:
a. Installation and testing of new fire detection/alarm system and demolition of the existing
fire alarm system in the ATCT and the terminal building.
b. Modifications to and testing of existing fire suppression system in the ATCT and the base
building as shown on drawings.
c. Installation of new fire-rated access doors, partitions, barriers and systems, etc., as shown
on drawings.
d. Replacement or modification, repair, patching, painting, refinishing, resurfacing of existing
walls, partitions, and/or ceilings, as required.
e. Sealing off existing and/or newly made penetrations or openings through walls, floors,
soffit, etc. with fire-stop sealant(s), caulks, mortars, mineral/ceramic wool, gypsum
wallboard, and/or masonry.
f. Application of sprayed-on fireproofing materials or intumescent paint to protect steel
structures or hatches as shown on drawings.
g. Installation of new louvers, dampers, fire doors, and related hardware and electrical gear,
or modification/repair of existing doors, dampers, etc., as r as shown on drawings.
h. Training for personnel assigned by the FAA.
i. Preparation of documentation describing as-built configuration and operation and
maintenance of systems and equipment and warranty of the work.
2. The Contractor shall provide all materials, labor, equipment and services, (except those
specifically referenced as Government-furnished to perform the work included in the
Construction Documents. The Contractor shall complete the construction in 150 calendar days,
start to finish.
3. The construction site is located at Oakland County International Aiport (PTK) at 6510 Highland
Rd, Waterford, MI 48327. The tower is defined as “Golemon-Rolfe” type tower. This facility is
active and operational. The Contractor shall comply with all procedures, rules and regulations of
the airport and FAA and shall minimize interference with the function of the facility.

Update #4 ·

Amendment 03: Posted 10/25/2022

Amendment 02; Posted 10/21/2022

Amendment 01:Posted 10/13/2022

These specifications and accompanying drawings describe the life-safety upgrade for the existing
Airport Traffic Control Tower’s (ATCT’s) and terminal buildings at the OAKLAND COUNTY
INTERNATIONAL AIRPORT (PTK) and further include all work necessary to improve the
architectural, mechanical, electrical, and fire protection systems to comply with OSHA regulation
29 CFR 1960.20. The work as generally outlined below shall include, but not be limited to:
a. Installation and testing of new fire detection/alarm system and demolition of the existing
fire alarm system in the ATCT and the terminal building.
b. Modifications to and testing of existing fire suppression system in the ATCT and the base
building as shown on drawings.
c. Installation of new fire-rated access doors, partitions, barriers and systems, etc., as shown
on drawings.
d. Replacement or modification, repair, patching, painting, refinishing, resurfacing of existing
walls, partitions, and/or ceilings, as required.
e. Sealing off existing and/or newly made penetrations or openings through walls, floors,
soffit, etc. with fire-stop sealant(s), caulks, mortars, mineral/ceramic wool, gypsum
wallboard, and/or masonry.
f. Application of sprayed-on fireproofing materials or intumescent paint to protect steel
structures or hatches as shown on drawings.
g. Installation of new louvers, dampers, fire doors, and related hardware and electrical gear,
or modification/repair of existing doors, dampers, etc., as r as shown on drawings.
h. Training for personnel assigned by the FAA.
i. Preparation of documentation describing as-built configuration and operation and
maintenance of systems and equipment and warranty of the work.
2. The Contractor shall provide all materials, labor, equipment and services, (except those
specifically referenced as Government-furnished to perform the work included in the
Construction Documents. The Contractor shall complete the construction in 150 calendar days,
start to finish.
3. The construction site is located at Oakland County International Aiport (PTK) at 6510 Highland
Rd, Waterford, MI 48327. The tower is defined as “Golemon-Rolfe” type tower. This facility is
active and operational. The Contractor shall comply with all procedures, rules and regulations of
the airport and FAA and shall minimize interference with the function of the facility.

Update #3 ·

Amendment 02; Posted 10/21/2022

Amendment 01:Posted 10/13/2022

These specifications and accompanying drawings describe the life-safety upgrade for the existing
Airport Traffic Control Tower’s (ATCT’s) and terminal buildings at the OAKLAND COUNTY
INTERNATIONAL AIRPORT (PTK) and further include all work necessary to improve the
architectural, mechanical, electrical, and fire protection systems to comply with OSHA regulation
29 CFR 1960.20. The work as generally outlined below shall include, but not be limited to:
a. Installation and testing of new fire detection/alarm system and demolition of the existing
fire alarm system in the ATCT and the terminal building.
b. Modifications to and testing of existing fire suppression system in the ATCT and the base
building as shown on drawings.
c. Installation of new fire-rated access doors, partitions, barriers and systems, etc., as shown
on drawings.
d. Replacement or modification, repair, patching, painting, refinishing, resurfacing of existing
walls, partitions, and/or ceilings, as required.
e. Sealing off existing and/or newly made penetrations or openings through walls, floors,
soffit, etc. with fire-stop sealant(s), caulks, mortars, mineral/ceramic wool, gypsum
wallboard, and/or masonry.
f. Application of sprayed-on fireproofing materials or intumescent paint to protect steel
structures or hatches as shown on drawings.
g. Installation of new louvers, dampers, fire doors, and related hardware and electrical gear,
or modification/repair of existing doors, dampers, etc., as r as shown on drawings.
h. Training for personnel assigned by the FAA.
i. Preparation of documentation describing as-built configuration and operation and
maintenance of systems and equipment and warranty of the work.
2. The Contractor shall provide all materials, labor, equipment and services, (except those
specifically referenced as Government-furnished to perform the work included in the
Construction Documents. The Contractor shall complete the construction in 150 calendar days,
start to finish.
3. The construction site is located at Oakland County International Aiport (PTK) at 6510 Highland
Rd, Waterford, MI 48327. The tower is defined as “Golemon-Rolfe” type tower. This facility is
active and operational. The Contractor shall comply with all procedures, rules and regulations of
the airport and FAA and shall minimize interference with the function of the facility.

Update #2 ·

Amendment 01:Posted 10/13/2022

These specifications and accompanying drawings describe the life-safety upgrade for the existing
Airport Traffic Control Tower’s (ATCT’s) and terminal buildings at the OAKLAND COUNTY
INTERNATIONAL AIRPORT (PTK) and further include all work necessary to improve the
architectural, mechanical, electrical, and fire protection systems to comply with OSHA regulation
29 CFR 1960.20. The work as generally outlined below shall include, but not be limited to:
a. Installation and testing of new fire detection/alarm system and demolition of the existing
fire alarm system in the ATCT and the terminal building.
b. Modifications to and testing of existing fire suppression system in the ATCT and the base
building as shown on drawings.
c. Installation of new fire-rated access doors, partitions, barriers and systems, etc., as shown
on drawings.
d. Replacement or modification, repair, patching, painting, refinishing, resurfacing of existing
walls, partitions, and/or ceilings, as required.
e. Sealing off existing and/or newly made penetrations or openings through walls, floors,
soffit, etc. with fire-stop sealant(s), caulks, mortars, mineral/ceramic wool, gypsum
wallboard, and/or masonry.
f. Application of sprayed-on fireproofing materials or intumescent paint to protect steel
structures or hatches as shown on drawings.
g. Installation of new louvers, dampers, fire doors, and related hardware and electrical gear,
or modification/repair of existing doors, dampers, etc., as r as shown on drawings.
h. Training for personnel assigned by the FAA.
i. Preparation of documentation describing as-built configuration and operation and
maintenance of systems and equipment and warranty of the work.
2. The Contractor shall provide all materials, labor, equipment and services, (except those
specifically referenced as Government-furnished to perform the work included in the
Construction Documents. The Contractor shall complete the construction in 150 calendar days,
start to finish.
3. The construction site is located at Oakland County International Aiport (PTK) at 6510 Highland
Rd, Waterford, MI 48327. The tower is defined as “Golemon-Rolfe” type tower. This facility is
active and operational. The Contractor shall comply with all procedures, rules and regulations of
the airport and FAA and shall minimize interference with the function of the facility.

Update #1 ·

These specifications and accompanying drawings describe the life-safety upgrade for the existing
Airport Traffic Control Tower’s (ATCT’s) and terminal buildings at the OAKLAND COUNTY
INTERNATIONAL AIRPORT (PTK) and further include all work necessary to improve the
architectural, mechanical, electrical, and fire protection systems to comply with OSHA regulation
29 CFR 1960.20. The work as generally outlined below shall include, but not be limited to:
a. Installation and testing of new fire detection/alarm system and demolition of the existing
fire alarm system in the ATCT and the terminal building.
b. Modifications to and testing of existing fire suppression system in the ATCT and the base
building as shown on drawings.
c. Installation of new fire-rated access doors, partitions, barriers and systems, etc., as shown
on drawings.
d. Replacement or modification, repair, patching, painting, refinishing, resurfacing of existing
walls, partitions, and/or ceilings, as required.
e. Sealing off existing and/or newly made penetrations or openings through walls, floors,
soffit, etc. with fire-stop sealant(s), caulks, mortars, mineral/ceramic wool, gypsum
wallboard, and/or masonry.
f. Application of sprayed-on fireproofing materials or intumescent paint to protect steel
structures or hatches as shown on drawings.
g. Installation of new louvers, dampers, fire doors, and related hardware and electrical gear,
or modification/repair of existing doors, dampers, etc., as r as shown on drawings.
h. Training for personnel assigned by the FAA.
i. Preparation of documentation describing as-built configuration and operation and
maintenance of systems and equipment and warranty of the work.
2. The Contractor shall provide all materials, labor, equipment and services, (except those
specifically referenced as Government-furnished to perform the work included in the
Construction Documents. The Contractor shall complete the construction in 150 calendar days,
start to finish.
3. The construction site is located at Oakland County International Aiport (PTK) at 6510 Highland
Rd, Waterford, MI 48327. The tower is defined as “Golemon-Rolfe” type tower. This facility is
active and operational. The Contractor shall comply with all procedures, rules and regulations of
the airport and FAA and shall minimize interference with the function of the facility.

Files

File Type Posted
Amendment 06.pdf PDF
Amendment 05.pdf PDF
Amendment 04.pdf PDF
Amendment 03.pdf PDF
Amendment 02.pdf PDF
Amendment 1.pdf PDF
DB-F100199141.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE.pdf PDF
697DCK-22-R-00560 (4).pdf PDF
PTK ATCT FLS Upgrade 6-21-22Drawings.pdf PDF
PTK ATCT Fire Life Safety Upgrade Specs 6_21_2022.pdf PDF
Show all 11

Notice history

Notice Type Posted
Pontiac ATCT Fire Life Safety Upgrades Award Award Notice
This notice Latest solicitation Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity