Pirnie upper envelope project – alexander pirnie federal building
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 47PC0220R0008
- Agency
-
Region 2
Public Buildings Service, General Services Administration
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Utica NY 13501 USA
Notice details come from SAM.gov. Updated .
About this opportunity
The General Services Administration, Region 2, Public Buildings Service intends to issue a Request for Proposal to replace approximately 28,500 square feet of existing roofing systems at the Alexander Pirnie Federal Building in Utica, New York. The project includes replacing slate, wood planking, insulation, gutters, drains and installing new roof membranes across multiple roof levels. Offerors must demonstrate experience on similar projects and key personnel qualifications. Evaluation will consider technical approach, past performance and price. Responses are due by March 10, 2020 with a pre-proposal site visit on February 11, 2020.
This requirement is designated as a 100% total small business set-aside. The NAICS code is 238310 and PSC code R499. The place of performance is Utica, New York 13501. The project involves replacement of roofing systems across three levels and optional installation of steam coils or replacement of direct expansion refrigeration systems at two air handling units. The selected contractor must complete all work within 360 days of award with a substantial completion date of 300 days. The General Services Administration Public Buildings Service Region 2 will administer the contract.
Notice text
6 versions
Update #6 · Latest ·
This Amendment No. 0004 is being issued to provide GSA response to a RFI received. Please see attached SF30 for details.
This amendment must be signed and returned with your offer.
This Amendment No. 0003 is being issued to provide GSA response to RFIs received (Please see attached Amendment 0003 - Q-A for details).
This amendment must be signed and returned with your offer.
Missing Attchment for Amendment No. 0002 for site visit sign-in sheet is added.
An amendment is issued to this solicitation. This Amendment No. 0002 is being issued to:
1. Extend the proposal due date to Tuesday, March 10, 2020, by 4:00 P.M. EST.; and accordingly the RFI due date is being revised to be COB, Friday February 28, 2020;
2. Provide GSA response to RFIs received (Please see attached Amendment 0002 for details).
This amendment must be signed and returned with your offer
An amendment is issued to this solicitation. This Amendment No. 0001 is being issued to provide a 2nd site visit date and GSA responses to the RFI questions received. Please see attached Amendment 0001 for details.
This amendment must be signed and returned with your offer.
THIS IS A SOLICITATION NOTICE. The General Services Administration, Region 2, Public Buildings Service, intends to issue a Request for Proposal (RFP) # 47PC0220R0008, to replace approximately 28,500 sf of existing roofing systems at the Alexander Pirnie Federal Building (161’ x 166’) will be replaced with new roofing systems at Alexander Pirnie Federal Building, 10 Broad Street, Utica, NY 13501. The existing 2” thick wood planking which is located beneath the mansard roofing system- will be replaced with new 2” thick wood planking which has field fabricated R-30 insulated panels installed on top of the new planking. The Yankee gutters will be replaced in their entirety with similar materials; and the existing roof drains and roof conductors located above the attic floor will be replaced in their entirety with new materials. The existing slate roofing materials which are installed on the sloped portion of the mansard roof will be replaced with synthetic slate materials and a new TPO roof membrane will be installed on the flat portion of the mansard roof. The ACM flashing materials which are installed at the six skylight structures at the Lower Roof will be abated and the six skylight structures will be demolished and the skylight openings which are located in the concrete slab beneath the Lower Roof will be closed. The existing roofing and wood support structures at the Lower Roof and Middle Roof will be removed and replaced with new TPO roof membranes and R-30 insulation that will be placed on the existing concrete slabs that support the wood framing. The existing roof membrane and associated insulation materials at the Upper Roof will be replaced with a new TPO roof membrane and R-30 insulation. Guardrails will be installed around the perimeter of the flat roofs; snow rails will be installed at the lower edge of the slate roofs. A roof tie-off system will be installed at the peak of the slate roofs; and a secondary roof drain system will be installed at the Lower Roof and the two drain conductors will be routed through the interior of the building and terminate at the north wall at two sheep’s mouth nozzles.
The project involves HVAC work and is described hereafter: a ventilation system will be installed in the attic space to regulate temperature and humidity. The existing rooftop equipment at the Middle Roof and Lower Roof will be removed and reinstalled on the lowered roofs. Existing electrical and mechanical systems which are hung from the mansard ceiling will be re-supported. At the conclusion of the project, the existing site will be restored to its original condition.
This project has three options as described hereafter:
Option One includes the following work: a steam coil with associated piping and controls will be installed at the basement AHU identified as PHCU-1 and will be installed at the second floor AHU identified as PHCU-2.
Option Two includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-2 provides 7,030 cfm of conditioned air to the Alexander Pirnie Federal Building.
Option Three includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-1 provides 20,850 cfm of conditioned air to the Alexander Pirnie Federal Building.
TYPE OF SET-ASIDE: This requirement will be solicited as a 100% Total Small Business set-aside.
Update #5 ·
This Amendment No. 0003 is being issued to provide GSA response to RFIs received (Please see attached Amendment 0003 - Q-A for details).
This amendment must be signed and returned with your offer.
Missing Attchment for Amendment No. 0002 for site visit sign-in sheet is added.
An amendment is issued to this solicitation. This Amendment No. 0002 is being issued to:
1. Extend the proposal due date to Tuesday, March 10, 2020, by 4:00 P.M. EST.; and accordingly the RFI due date is being revised to be COB, Friday February 28, 2020;
2. Provide GSA response to RFIs received (Please see attached Amendment 0002 for details).
This amendment must be signed and returned with your offer
An amendment is issued to this solicitation. This Amendment No. 0001 is being issued to provide a 2nd site visit date and GSA responses to the RFI questions received. Please see attached Amendment 0001 for details.
This amendment must be signed and returned with your offer.
THIS IS A SOLICITATION NOTICE. The General Services Administration, Region 2, Public Buildings Service, intends to issue a Request for Proposal (RFP) # 47PC0220R0008, to replace approximately 28,500 sf of existing roofing systems at the Alexander Pirnie Federal Building (161’ x 166’) will be replaced with new roofing systems at Alexander Pirnie Federal Building, 10 Broad Street, Utica, NY 13501. The existing 2” thick wood planking which is located beneath the mansard roofing system- will be replaced with new 2” thick wood planking which has field fabricated R-30 insulated panels installed on top of the new planking. The Yankee gutters will be replaced in their entirety with similar materials; and the existing roof drains and roof conductors located above the attic floor will be replaced in their entirety with new materials. The existing slate roofing materials which are installed on the sloped portion of the mansard roof will be replaced with synthetic slate materials and a new TPO roof membrane will be installed on the flat portion of the mansard roof. The ACM flashing materials which are installed at the six skylight structures at the Lower Roof will be abated and the six skylight structures will be demolished and the skylight openings which are located in the concrete slab beneath the Lower Roof will be closed. The existing roofing and wood support structures at the Lower Roof and Middle Roof will be removed and replaced with new TPO roof membranes and R-30 insulation that will be placed on the existing concrete slabs that support the wood framing. The existing roof membrane and associated insulation materials at the Upper Roof will be replaced with a new TPO roof membrane and R-30 insulation. Guardrails will be installed around the perimeter of the flat roofs; snow rails will be installed at the lower edge of the slate roofs. A roof tie-off system will be installed at the peak of the slate roofs; and a secondary roof drain system will be installed at the Lower Roof and the two drain conductors will be routed through the interior of the building and terminate at the north wall at two sheep’s mouth nozzles.
The project involves HVAC work and is described hereafter: a ventilation system will be installed in the attic space to regulate temperature and humidity. The existing rooftop equipment at the Middle Roof and Lower Roof will be removed and reinstalled on the lowered roofs. Existing electrical and mechanical systems which are hung from the mansard ceiling will be re-supported. At the conclusion of the project, the existing site will be restored to its original condition.
This project has three options as described hereafter:
Option One includes the following work: a steam coil with associated piping and controls will be installed at the basement AHU identified as PHCU-1 and will be installed at the second floor AHU identified as PHCU-2.
Option Two includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-2 provides 7,030 cfm of conditioned air to the Alexander Pirnie Federal Building.
Option Three includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-1 provides 20,850 cfm of conditioned air to the Alexander Pirnie Federal Building.
TYPE OF SET-ASIDE: This requirement will be solicited as a 100% Total Small Business set-aside.
Update #4 ·
Missing Attchment for Amendment No. 0002 for site visit sign-in sheet is added.
An amendment is issued to this solicitation. This Amendment No. 0002 is being issued to:
1. Extend the proposal due date to Tuesday, March 10, 2020, by 4:00 P.M. EST.; and accordingly the RFI due date is being revised to be COB, Friday February 28, 2020;
2. Provide GSA response to RFIs received (Please see attached Amendment 0002 for details).
This amendment must be signed and returned with your offer
An amendment is issued to this solicitation. This Amendment No. 0001 is being issued to provide a 2nd site visit date and GSA responses to the RFI questions received. Please see attached Amendment 0001 for details.
This amendment must be signed and returned with your offer.
THIS IS A SOLICITATION NOTICE. The General Services Administration, Region 2, Public Buildings Service, intends to issue a Request for Proposal (RFP) # 47PC0220R0008, to replace approximately 28,500 sf of existing roofing systems at the Alexander Pirnie Federal Building (161’ x 166’) will be replaced with new roofing systems at Alexander Pirnie Federal Building, 10 Broad Street, Utica, NY 13501. The existing 2” thick wood planking which is located beneath the mansard roofing system- will be replaced with new 2” thick wood planking which has field fabricated R-30 insulated panels installed on top of the new planking. The Yankee gutters will be replaced in their entirety with similar materials; and the existing roof drains and roof conductors located above the attic floor will be replaced in their entirety with new materials. The existing slate roofing materials which are installed on the sloped portion of the mansard roof will be replaced with synthetic slate materials and a new TPO roof membrane will be installed on the flat portion of the mansard roof. The ACM flashing materials which are installed at the six skylight structures at the Lower Roof will be abated and the six skylight structures will be demolished and the skylight openings which are located in the concrete slab beneath the Lower Roof will be closed. The existing roofing and wood support structures at the Lower Roof and Middle Roof will be removed and replaced with new TPO roof membranes and R-30 insulation that will be placed on the existing concrete slabs that support the wood framing. The existing roof membrane and associated insulation materials at the Upper Roof will be replaced with a new TPO roof membrane and R-30 insulation. Guardrails will be installed around the perimeter of the flat roofs; snow rails will be installed at the lower edge of the slate roofs. A roof tie-off system will be installed at the peak of the slate roofs; and a secondary roof drain system will be installed at the Lower Roof and the two drain conductors will be routed through the interior of the building and terminate at the north wall at two sheep’s mouth nozzles.
The project involves HVAC work and is described hereafter: a ventilation system will be installed in the attic space to regulate temperature and humidity. The existing rooftop equipment at the Middle Roof and Lower Roof will be removed and reinstalled on the lowered roofs. Existing electrical and mechanical systems which are hung from the mansard ceiling will be re-supported. At the conclusion of the project, the existing site will be restored to its original condition.
This project has three options as described hereafter:
Option One includes the following work: a steam coil with associated piping and controls will be installed at the basement AHU identified as PHCU-1 and will be installed at the second floor AHU identified as PHCU-2.
Option Two includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-2 provides 7,030 cfm of conditioned air to the Alexander Pirnie Federal Building.
Option Three includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-1 provides 20,850 cfm of conditioned air to the Alexander Pirnie Federal Building.
TYPE OF SET-ASIDE: This requirement will be solicited as a 100% Total Small Business set-aside.
Update #3 ·
An amendment is issued to this solicitation. This Amendment No. 0002 is being issued to:
1. Extend the proposal due date to Tuesday, March 10, 2020, by 4:00 P.M. EST.; and accordingly the RFI due date is being revised to be COB, Friday February 28, 2020;
2. Provide GSA response to RFIs received (Please see attached Amendment 0002 for details).
This amendment must be signed and returned with your offer
An amendment is issued to this solicitation. This Amendment No. 0001 is being issued to provide a 2nd site visit date and GSA responses to the RFI questions received. Please see attached Amendment 0001 for details.
This amendment must be signed and returned with your offer.
THIS IS A SOLICITATION NOTICE. The General Services Administration, Region 2, Public Buildings Service, intends to issue a Request for Proposal (RFP) # 47PC0220R0008, to replace approximately 28,500 sf of existing roofing systems at the Alexander Pirnie Federal Building (161’ x 166’) will be replaced with new roofing systems at Alexander Pirnie Federal Building, 10 Broad Street, Utica, NY 13501. The existing 2” thick wood planking which is located beneath the mansard roofing system- will be replaced with new 2” thick wood planking which has field fabricated R-30 insulated panels installed on top of the new planking. The Yankee gutters will be replaced in their entirety with similar materials; and the existing roof drains and roof conductors located above the attic floor will be replaced in their entirety with new materials. The existing slate roofing materials which are installed on the sloped portion of the mansard roof will be replaced with synthetic slate materials and a new TPO roof membrane will be installed on the flat portion of the mansard roof. The ACM flashing materials which are installed at the six skylight structures at the Lower Roof will be abated and the six skylight structures will be demolished and the skylight openings which are located in the concrete slab beneath the Lower Roof will be closed. The existing roofing and wood support structures at the Lower Roof and Middle Roof will be removed and replaced with new TPO roof membranes and R-30 insulation that will be placed on the existing concrete slabs that support the wood framing. The existing roof membrane and associated insulation materials at the Upper Roof will be replaced with a new TPO roof membrane and R-30 insulation. Guardrails will be installed around the perimeter of the flat roofs; snow rails will be installed at the lower edge of the slate roofs. A roof tie-off system will be installed at the peak of the slate roofs; and a secondary roof drain system will be installed at the Lower Roof and the two drain conductors will be routed through the interior of the building and terminate at the north wall at two sheep’s mouth nozzles.
The project involves HVAC work and is described hereafter: a ventilation system will be installed in the attic space to regulate temperature and humidity. The existing rooftop equipment at the Middle Roof and Lower Roof will be removed and reinstalled on the lowered roofs. Existing electrical and mechanical systems which are hung from the mansard ceiling will be re-supported. At the conclusion of the project, the existing site will be restored to its original condition.
This project has three options as described hereafter:
Option One includes the following work: a steam coil with associated piping and controls will be installed at the basement AHU identified as PHCU-1 and will be installed at the second floor AHU identified as PHCU-2.
Option Two includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-2 provides 7,030 cfm of conditioned air to the Alexander Pirnie Federal Building.
Option Three includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-1 provides 20,850 cfm of conditioned air to the Alexander Pirnie Federal Building.
TYPE OF SET-ASIDE: This requirement will be solicited as a 100% Total Small Business set-aside.
Update #2 ·
An amendment is issued to this solicitation. This Amendment No. 0001 is being issued to provide a 2nd site visit date and GSA responses to the RFI questions received. Please see attached Amendment 0001 for details.
This amendment must be signed and returned with your offer.
THIS IS A SOLICITATION NOTICE. The General Services Administration, Region 2, Public Buildings Service, intends to issue a Request for Proposal (RFP) # 47PC0220R0008, to replace approximately 28,500 sf of existing roofing systems at the Alexander Pirnie Federal Building (161’ x 166’) will be replaced with new roofing systems at Alexander Pirnie Federal Building, 10 Broad Street, Utica, NY 13501. The existing 2” thick wood planking which is located beneath the mansard roofing system- will be replaced with new 2” thick wood planking which has field fabricated R-30 insulated panels installed on top of the new planking. The Yankee gutters will be replaced in their entirety with similar materials; and the existing roof drains and roof conductors located above the attic floor will be replaced in their entirety with new materials. The existing slate roofing materials which are installed on the sloped portion of the mansard roof will be replaced with synthetic slate materials and a new TPO roof membrane will be installed on the flat portion of the mansard roof. The ACM flashing materials which are installed at the six skylight structures at the Lower Roof will be abated and the six skylight structures will be demolished and the skylight openings which are located in the concrete slab beneath the Lower Roof will be closed. The existing roofing and wood support structures at the Lower Roof and Middle Roof will be removed and replaced with new TPO roof membranes and R-30 insulation that will be placed on the existing concrete slabs that support the wood framing. The existing roof membrane and associated insulation materials at the Upper Roof will be replaced with a new TPO roof membrane and R-30 insulation. Guardrails will be installed around the perimeter of the flat roofs; snow rails will be installed at the lower edge of the slate roofs. A roof tie-off system will be installed at the peak of the slate roofs; and a secondary roof drain system will be installed at the Lower Roof and the two drain conductors will be routed through the interior of the building and terminate at the north wall at two sheep’s mouth nozzles.
The project involves HVAC work and is described hereafter: a ventilation system will be installed in the attic space to regulate temperature and humidity. The existing rooftop equipment at the Middle Roof and Lower Roof will be removed and reinstalled on the lowered roofs. Existing electrical and mechanical systems which are hung from the mansard ceiling will be re-supported. At the conclusion of the project, the existing site will be restored to its original condition.
This project has three options as described hereafter:
Option One includes the following work: a steam coil with associated piping and controls will be installed at the basement AHU identified as PHCU-1 and will be installed at the second floor AHU identified as PHCU-2.
Option Two includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-2 provides 7,030 cfm of conditioned air to the Alexander Pirnie Federal Building.
Option Three includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-1 provides 20,850 cfm of conditioned air to the Alexander Pirnie Federal Building.
TYPE OF SET-ASIDE: This requirement will be solicited as a 100% Total Small Business set-aside.
Update #1 ·
THIS IS A SOLICITATION NOTICE. The General Services Administration, Region 2, Public Buildings Service, intends to issue a Request for Proposal (RFP) # 47PC0220R0008, to replace approximately 28,500 sf of existing roofing systems at the Alexander Pirnie Federal Building (161’ x 166’) will be replaced with new roofing systems at Alexander Pirnie Federal Building, 10 Broad Street, Utica, NY 13501. The existing 2” thick wood planking which is located beneath the mansard roofing system- will be replaced with new 2” thick wood planking which has field fabricated R-30 insulated panels installed on top of the new planking. The Yankee gutters will be replaced in their entirety with similar materials; and the existing roof drains and roof conductors located above the attic floor will be replaced in their entirety with new materials. The existing slate roofing materials which are installed on the sloped portion of the mansard roof will be replaced with synthetic slate materials and a new TPO roof membrane will be installed on the flat portion of the mansard roof. The ACM flashing materials which are installed at the six skylight structures at the Lower Roof will be abated and the six skylight structures will be demolished and the skylight openings which are located in the concrete slab beneath the Lower Roof will be closed. The existing roofing and wood support structures at the Lower Roof and Middle Roof will be removed and replaced with new TPO roof membranes and R-30 insulation that will be placed on the existing concrete slabs that support the wood framing. The existing roof membrane and associated insulation materials at the Upper Roof will be replaced with a new TPO roof membrane and R-30 insulation. Guardrails will be installed around the perimeter of the flat roofs; snow rails will be installed at the lower edge of the slate roofs. A roof tie-off system will be installed at the peak of the slate roofs; and a secondary roof drain system will be installed at the Lower Roof and the two drain conductors will be routed through the interior of the building and terminate at the north wall at two sheep’s mouth nozzles.
The project involves HVAC work and is described hereafter: a ventilation system will be installed in the attic space to regulate temperature and humidity. The existing rooftop equipment at the Middle Roof and Lower Roof will be removed and reinstalled on the lowered roofs. Existing electrical and mechanical systems which are hung from the mansard ceiling will be re-supported. At the conclusion of the project, the existing site will be restored to its original condition.
This project has three options as described hereafter:
Option One includes the following work: a steam coil with associated piping and controls will be installed at the basement AHU identified as PHCU-1 and will be installed at the second floor AHU identified as PHCU-2.
Option Two includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-2 provides 7,030 cfm of conditioned air to the Alexander Pirnie Federal Building.
Option Three includes the following work: the R-22 direct expansion refrigeration system (DX cooling coil, compressor unit, refrigeration piping, and air-cooled condensing unit) which provides cooling at the basement AHU identified as PHCU-1 will be replaced in its entirety. PHCU-1 provides 20,850 cfm of conditioned air to the Alexander Pirnie Federal Building.
TYPE OF SET-ASIDE: This requirement will be solicited as a 100% Total Small Business set-aside.
Files
Show all 27
Notice history
| Notice | Type | Posted |
|---|---|---|
| Pirnie upper envelope project – alexander pirnie federal building | Award Notice | |
| This notice | Solicitation | |
| Pirnie upper envelope project – alexander pirnie federal building | Pre-Solicitation | |
| Pirnie upper envelope project – alexander pirnie federal building | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| GAOA Remove and Replace Roofing on Island Park Admin Site Housing Units | Forest Service | Total Small Business | |
| SOLICITATION NOTICE- Rochester, NY Courthouse Construction | — | Service-Disabled Veteran-Owned Small Business | |
| SOLICITATION NOTICE- Massena NY Virtual Law Enforcement Training Facility- Construction | — | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity