Pier (1) for COLNAV in Gorgona Island, Colombia

Award Notice Posted

Solicitation number
SAQMMA16R0507
Agency
Awarded
to Estudios Edificaciones E Interventorias En Ingenieria Eeii S A S
Set-aside
No set-aside

Opportunity facts

Contract number
SAQMMA17C0087 Federal contract award
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Place of performance
National Natural Park in Gorgona Island, Cauca, Colombia. Colombia

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

****Award Notice****

The award of the subject solicitation was made to the following company Estudios, Edificaciones e Interventorias en Ingenieria-EEII SAS in the amount of $1,866,980.65

***Amend 003, 2nd set of Q&As and other tech attachments are included****

***Amend 002, Proposal due date is extended from Oct 19 to October 31, 2016 at 10:00AM ET, see attachments for additional information***

***Amend 001, Proposals due date has been extended, see attachments for additional information***

*****Solicitation Notice****

This is a Solicitation Notice for the construction of one pier at the National Natural Park in Gorgona Island, Cauca, Colombia. The order of magnitude for this requirement is between $1,000,000 and $5,000,000. The estimated period of performance is 225 calendar days. This acquisition is under full and open procedures.

If you intend to submit a proposal, you should thoroughly examine all documents contained in this solicitation package. The USG has scheduled a site visit (see L.9, FAR 52.236-27) and a pre-proposal conference. All prospective offerors are invited to attend. The conference will be held in Gorgona Island, Colombia on September 14, 2016. Additional information is included in this solicitation package.

Update #5 ·

***Amend 003, 2nd set of Q&As and other tech attachments are included****

***Amend 002, Proposal due date is extended from Oct 19 to October 31, 2016 at 10:00AM ET, see attachments for additional information***

***Amend 001, Proposals due date has been extended, see attachments for additional information***

*****Solicitation Notice****

This is a Solicitation Notice for the construction of one pier at the National Natural Park in Gorgona Island, Cauca, Colombia. The order of magnitude for this requirement is between $1,000,000 and $5,000,000. The estimated period of performance is 225 calendar days. This acquisition is under full and open procedures.

If you intend to submit a proposal, you should thoroughly examine all documents contained in this solicitation package. The USG has scheduled a site visit (see L.9, FAR 52.236-27) and a pre-proposal conference. All prospective offerors are invited to attend. The conference will be held in Gorgona Island, Colombia on September 14, 2016. Additional information is included in this solicitation package.

Update #4 ·

***Amend 002, Proposal due date is extended from Oct 19 to October 31, 2016 at 10:00AM ET, see attachments for additional information***

***Amend 001, Proposals due date has been extended, see attachments for additional information***

*****Solicitation Notice****

This is a Solicitation Notice for the construction of one pier at the National Natural Park in Gorgona Island, Cauca, Colombia. The order of magnitude for this requirement is between $1,000,000 and $5,000,000. The estimated period of performance is 225 calendar days. This acquisition is under full and open procedures.

If you intend to submit a proposal, you should thoroughly examine all documents contained in this solicitation package. The USG has scheduled a site visit (see L.9, FAR 52.236-27) and a pre-proposal conference. All prospective offerors are invited to attend. The conference will be held in Gorgona Island, Colombia on September 14, 2016. Additional information is included in this solicitation package.

Update #3 ·

***Amend 001, Proposals due date has been extended, see attachments for additional information***

*****Solicitation Notice****

This is a Solicitation Notice for the construction of one pier at the National Natural Park in Gorgona Island, Cauca, Colombia. The order of magnitude for this requirement is between $1,000,000 and $5,000,000. The estimated period of performance is 225 calendar days. This acquisition is under full and open procedures.

If you intend to submit a proposal, you should thoroughly examine all documents contained in this solicitation package. The USG has scheduled a site visit (see L.9, FAR 52.236-27) and a pre-proposal conference. All prospective offerors are invited to attend. The conference will be held in Gorgona Island, Colombia on September 14, 2016. Additional information is included in this solicitation package.

Update #2 ·

*****Solicitation Notice****

This is a Solicitation Notice for the construction of one pier at the National Natural Park in Gorgona Island, Cauca, Colombia. The order of magnitude for this requirement is between $1,000,000 and $5,000,000. The estimated period of performance is 225 calendar days. This acquisition is under full and open procedures.

If you intend to submit a proposal, you should thoroughly examine all documents contained in this solicitation package. The USG has scheduled a site visit (see L.9, FAR 52.236-27) and a pre-proposal conference. All prospective offerors are invited to attend. The conference will be held in Gorgona Island, Colombia on September 14, 2016. Additional information is included in this solicitation package.

Update #1 ·

This is a Pre-solicitation Notice of the Government's intent to issue a solicitation for the construction of one pier at the National Natural Park in Gorgona Island, Cauca, Colombia. The order of magnitude for this requirement is between $1,000,000 and $5,000,000. The estimated period of performance is 225 calendar days. This acquisition will be issued under full and open procedures.

The pier will have a length of 163 m, and its foundation in metallic piles filled with cast-in-place reinforced concrete, metallic bracing, concrete beams and concrete deck. The project includes excavations, filling material, reinforced concrete structures, metallic structures and accessories as well as the grounding protection system. The pier shall comply with the current standards of the Colombian Seismic Resistance Code (NSR Standard, 10) and the construction process with Environment Plan (PMA).


The contractor shall be responsible for transportation, and provide or coordinate accommodations for meals and lodging of the construction team at the work site or the contractor shall make arrange for such accommodations with the National Natural Park (PNN) personnel. This coordination will be based on PNN's personnel availability during the execution of this project.


The solicitation is expected to be posted in August, 2016 and available for 30 days - reference SAQMMA-16-R-0507. Proposal response time and submittal will be specified at the time the solicitation is posted. A pre-proposal conference and/or site visit(s) will be schedule and included in the solicitation. Award of a Firm-fixed price construction type contract is anticipated within 60 days of proposal receipt.


Additional Information concerning the location:
The pier will be located in Gorgona Island which belongs to the town of Guapi (Cauca) at 479 Km from Bogota, southwest of Colombia in the pacific coast. Guapi can be accessed by commercial flight from Cali or boat from Buenaventura. The Gorgona Island has a length of 9 Km by 2.5 Km, with an approximate area of 26 Km2 of land or insular surface and 61,687 Ha of marine area. This is a very humid and rainy area and the pier shall be constructed on Southeast side of the Gorgona Island. The job site can be access by boat which is around 35 Km from Guapi or by helicopter, since there is no access road. The offeror shall take into account all the environmental considerations for a construction project because this project will be developed on National Natural Park Gorgona, a sensitive environmental preservation area where the poisonous snakes are plentiful and other animal species.

Files

File Type Posted
SF30_Amend_003_(26OCT16)_Approved.pdf PDF
2nd_set_QandAs-final_(26OCT16).pdf PDF
Updated-Environmental_Data_Sheets_(25OCT16).pdf PDF
A-3B.pdf PDF
Specs-Electrical_gerator_and_fuel_Tank.pdf PDF
16R0507_Q As_Pier_in_Gorgona-Final.pdf PDF
S-03A.pdf PDF
Amend_002_SF30_Approved_14OCT16.pdf PDF
Amend_002-LICENCIA_AMBIENTAL_GORGONA.pdf PDF
E-01.pdf PDF
A-3A.pdf PDF
S-06A.pdf PDF
Colombian_Tax_Exemption_Certificate.pdf PDF
SF30A001-Approved_(28SEP16).pdf PDF
Soil-Geo_Study.pdf PDF
Amend_001-Sched_B-M(28SE).pdf PDF
J-1-1_Mat_Prod_Substitution_Form.pdf PDF
J-1-4_Insurance.pdf PDF
J-2-3_Impact_Survey.pdf PDF
FinalSched_B-M_16R0507(1SEP16).pdf PDF
SF1442_(01SEP16).pdf PDF
J-1-5_IncidentsF.pdf PDF
J-1-2_PastP.pdf PDF
J-1-3FirmT.pdf PDF
J-2-1_Bidding_charts.pdf PDF
Final_SOW_(01SEP16).pdf PDF
J-2-2_Drawings_(25aug16).pdf PDF
Show all 27