PEVI - 201919A - Repointing of the Memorial Column

Award Notice Posted

Solicitation number
P16PS00702
Agency
Awarded
to Coon Caulking & Sealants, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
INP16PC00479 Federal contract award
NAICS code
238140 Masonry Contractors
PSC
Not on record
Place of performance
Perry's Victory & International Peace Memorial South Bass Island Ottawa County Put-In-Bay, Ohio 43456, United States

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

PEVI - P16PS00702
SOLICITATION AMENDMENT 000005


The hour and date specified for receipt of offers remains July 29, 2016 at 5:00 PM ET.


*******SPECIAL NOTE FOR CLARIFICATION********
> The attachment for Amendment No. 000002 is indicated in FedBizOpps as Amendment No. 000001.
> The attachments for Amendment No. 000003 are indicated in FedBizOpps as Amendment No. 000002.
> The attachment for Amendment No. 000004, is indicated in FedBizOpps as Amendment No. 000003.
> The attachments for this Amendment No. 000005, which are the Standard Form 30 and the pre-proposal conf/site visit minutes, are indicated in FedBizOpps as Amendment No. 000004.


The purpose of this Amendment No. 000005 is the following:


1. Provide minutes from the pre-proposal conference/site visit held on July 13, 2016.


See summary of changes below for complete amendment details.


Summary of Changes


The minutes from the pre-proposal conference/site visit held on July 13, 2016 are incorporated, and are attached.
End of amendment

Update #5 ·

PEVI - P16PS00702
SOLICITATION AMENDMENT 000004


The hour and date specified for receipt of offers remains July 29, 2016 at 5:00 PM ET.


*******SPECIAL NOTE FOR CLARIFICATION********
> The attachment for Amendment No. 000002 is indicated in FedBizOpps as Amendment No. 000001.
> The attachments for Amendment No. 000003 are indicated in FedBizOpps as Amendment No. 000002.
> The attachment for this Amendment No. 000004, which is the Standard Form 30, is indicated in FedBizOpps as Amendment No. 000003.


The purpose of this Amendment No. 000004 is the following:


1. Answer questions from potential offerors.


See summary of changes below for complete amendment details.


Summary of Changes


A. Questions from potential offerors, and the official Government responses to those questions are listed below, and are incorporated.


Q1. Will we be leaving the mock up areas alone and consider them finished?
A1. Yes, except for any portion of a mock-up area of the study which had undesirable results.


Q2. Is the inside dimension of the davit points indicated on the drawing accurate.
A2. The I.D. of the davit socket on top of the observation deck wall measured 5 3/16 (which is contrary to the drawing dimension of 4 7/8 I.D.) (NOTE: Not the davit on observation deck floor).


Q3. What elevator service company does the park use for their annual testing.
A3. Schindler Elevator Company 1-800-225-3123.


Q4. Can NPS provide name and contact information of company currently servicing elevator for the column as well as current certificate?
A4. Schindler Elevator Company 1-800-225-3123. The elevator is inspected annually and the current certificate is available from Park staff, not inside the elevator for public view.


Q5. What is weight capacity of the elevator?
A5. 2,500 lbs


Q6. Can information be provided on the age and make of the elevator along with inspection/ maintenance history?
A6. Original 1936 Otis Elevator Cab & Motor.


Gearless elevator machine hoist (motor) was rebuilt in April of 2009.


Entire elevator was given a total safety inspection and subsequently updated and brought up to current safety standards right after the motor was re-built.


Annual Safety Test Completed in May 2015.


5-year Load Test - August 2015.


May contact Schindler Elevator Company for additional information.


Q7. Power Supply for Swingstage motors
What is available capacity for electric service to supply project with power? Number of available circuits and size(s)? What are locations of available connections? Is the below power requirements available: Preferred: 4 separate draws of single phase 20 amp/204V; Secondary: 4 separate draws of single phase 20 amp/104V.
A7. Assume that there is adequate electrical capacity available for bidding purposes.


Q8. Section 040140 - Efflorescence Removal - paragraph 2.1.A.1 specifies that clean potable water with iron content of less than parts per million be used for cleaning purposes. The following two paragraphs state to notify C.O. if local water provided to the park is not suitable for cleaning uses on this project. It states that testing is the responsibility of the contractor. Who is responsible for costs to treat water to achieve acceptable levels (test results) if water provided from local source(s) on the island is not suitable per the specifications for use in cleaning operations on this project? Is NPS responsible for this cost? Or is the contractor responsible for this cost? Has any testing of water been conducted to know if this is a potential problem?
A8. It is not our intent to have the Contractor treat the water in any fashion if it exceeds that iron content. Therefore, only provide the C.O. the test result and that information will be forwarded to the Park for their information. No need to take any other action by the Contractor.


Search in Specs:


Q9. What is weight capacity of upper plaza? Is a specific weight limit known?
A9. 50 PSF maximum.


Q10. Section 01500, paragraph 3.3.D requires a project sign. Please verify size, correct material from which sign should be fabricated and how it should mounted and/or displayed?
A10. Provide a 4-foot by 4-foot painted exterior grade 1/2-inch MDO or plywood panel backer. Place sign at 3-feet above grade to the bottom of the sign (so total of 7-feet high). Secure using 4-inch by 4-inch wood posts set in concrete for stability. Provide a digital print on adhesive vinyl of the graphics as a submittal for NPS review showing font sizes, colors, etc.


Q11. Contractor's Environmental Manager is required in section 013100. Can this person also serve as project superintendent or another significant duty on the project? Or does this role need to be a standalone position on the project?
A11. That person can be assigned to other duties, so it is NOT a stand alone position.


Q12. Can project SSHO (site safety health officer) and superintendent be the same person? Or does each role need to be a standalone position on the project?
A12. The only reference found for a "Project Site Safety Manager" was in the technical capability description of Sub-Factor F - Safety. That person can be assigned to other duties, so it is NOT a stand alone position. Jobsite safety duties may be assigned to go along with other duties or roles on the project as well.


Q13. Proposals are due at 5:00pm; can you please clarify what time zone? The solicitation documents state Eastern Time, but with the proposals being due to NPS in Lakewood CO I would assume that means 5:00pm Mountain Time.
A13. Offers are due at 5:00 PM ET. This translates to 3:00 PM MT.


Q14. I see in section L.3 that proposals shall consist of one attachment per Part; therefore Part I, Part II and Part III will each be separate files. Does NPS have a limit of 5MB attachments per email like other government agencies do? If so, can the 3 separate Parts be sent in 3 separate emails?
A14. File size limitation is 10MB. If necessary, the files can be sent in separate emails. Ensure that all emails/files arrive no later than the hour and date specified for receipt of offers, and are clearly marked/labeled in the subject line of the email.


Q15. Can portable chain link fencing be used for the construction fence around the work area as long as it meets the requirements in spec section 01500 temporary facilities and controls?
A15. Yes, if the construction fencing meets the requirements in Section 015000 (reference Part 3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION - E,F and G).
End of Amendment

Update #4 ·

PEVI - P16PS00702
SOLICITATION AMENDMENT 000003

The purpose of this Amendment No. 000003 is the following:
1. Clarify the solicitation type.
2. Clarify Amendment No.'s 000001 & 00002, as there is conflicting information on FedBizOpps.
3. Provide pre-proposal conference/site visit information.
4. Extend the hour and date specified for receipt of offers.
5. Answer questions from potential offerors.

*******SPECIAL NOTE FOR CLARIFICATION: The attachment for Amendment No. 000002 is indicated as Amendment No. 000001. The attachments for this Amendment No. 000003 are indicated as Amendment No. 000002.**********


See summary of changes below for complete amendment details.


Summary of Changes


A. The original solicitation posted to FedBizOpps on June 27, 2016 indicates a Notice Type of "Combined Synopsis/Solicitation." This is incorrect. The correct Notice Type is "Solicitation."


B. Amendment No. 00001 changed Solicitation Provision 52.236-27 "Site Visit (Construction) to incorporate an organized site visit. The Standard Form 30 incorporating that change is attached to this amendment.


C. Amendment No. 00002 provided a two (2) page follow-up to the Spring 2016 repointing and cleaning trials performed at Perry's Victory & International Peace Memorial on the monument. The Standard Form 30 incorporating this document, as well as the document itself, is attached to this amendment.


D. The pre-proposal conference/site visit agenda and sign-in sheet are incorporated, and are attached to this amendment. Any minutes, and any questions and answers, will be incorporated via a future amendment.


E. The hour and date specified for receipt of offers is extended to July 29, 2016 at 5:00 PM ET.


F. Questions from potential offerors, and the official Government responses to those questions are listed below, and are incorporated. Any questions not answered in this amendment, will be answered via a future amendment.


Q1. PPQ requirements stated in Section L are not clear on how many Past Performance Questionnaires should be submitted to NPS. Please verify?
a. Should PPQ's be submitted for same projects identified in Sub-Factor A?
b. When are PPQ's due to NPS?
A1. There is no specific number of Past Performance Questionnaire's (PPQ's) required. PPQ's must be submitted for the same projects identified in Sub-factor A. PPQ's are due by the hour and date specified for receipt of offers.


Q2. We have located two price schedule forms, one which matches spec section 01 27 00, and one that varies on line item #1. Could you clarify which one we should use.
A2. The correct contract price schedule to use for submission of proposals, is the one labeled "Not used" in CLIN 1. General Conditions are not a separate CLIN. General Condition costs are to be spread across all other CLIN's.
End of Amendment


 

Update #3 ·

PEVI - P16PS00702
SOLICITATION AMENDMENT 000002

The purpose of this amendment is to provide a two (2) page follow-up to the Spring 2016 repointing and cleaning trials performed at Perry's Victory & International Peace Memorial on the monument.  Observations were conducted on 16 June 2016 and the attachment is a follow-up to the previous observations.

As a result of this amendment the solicitation remains unchanged.

Update #2 ·

P16PS00702 - PEVI - 201919A

Solicitation Amendment 000001


The subject solicitation is amended as follows:


1. FAR Provision 52.236-27 - Site Visit is here by amended to the following and is incorporated herein by full text to provide an organized pre-proposal site visit to Perry's Victory & International Peace Memorial, Put-In-Bay, OH.


52.236-27 -- Site Visit (Construction) (Feb 1995) Alternate I (Feb 1995)


(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.


(b) An organized site visit has been scheduled for --


10:00 a.m. to 12:00 p.m., Eastern Time, Wednesday, 13 July 2016


(c) Participants will meet at --


Perry's Victory & International Peace Memorial
93 Delaware Avenue
South Bass Island in Put-in-Bay Township, Ottawa County, OH 43456-0549
The Monument's Lower Flat Stairs


Offerors are invited to attend the pre-proposal site visit, non-mandatory, at their own expense as listed in the above FAR Provision.


Please see the following website for Directions and Transportation information.


https://www.nps.gov/pevi/planyourvisit/directions.htm


 

Update #1 ·

The Department of Interior (DOI), National Park Service (NPS), Denver Service Center (DSC), is soliciting proposals on a 100% Small Business Set-Aside basis to all small business firms having the capability to perform the work described in the solicitation.


Solicitation documents are attached to this notice. Paper copies of the solicitation and associated documents will not be made available. Instructions for proposal submission are included in Section L of the solicitation. The NPS intends to award a Firm-Fixed-Price type contract as a result of the solicitation. If awarded, award will be made to the Offeror whose proposal represents the best value to the Government.


Prospective Offerors must be registered with the System for Award Management website and complete representations and certifications at https://www.sam.gov. Offers received from Other Than Small Business concerns shall not be considered or evaluated.


Solicitation number is P16PS00702 and is issued as a Request for Proposal (RFP)


Title: PEVI - 201919A - Repointing of the Memorial Column at Perry's Victory & International Peace Memorial


North American Industrial Classification System (NAICS) code: 238140 - Masonry Contractors


Size Standard: $15M


Estimated Magnitude of Construction: $1,000,000 to $5,000,000


Estimated Period of Performance: April 2017 through November 2017


All correspondence and submissions shall be in writing only emailed directly to the Contract Specialist with a courtesy copy to the Contracting Officer cited in this notice. Phone inquiries, other than those for scheduling site visits, will not be responded to.


Offerors are highly encouraged to conduct a pre-proposal site visit. Pre-proposal site visits may be arranged during normal duty hours by contacting:


Rodney Karr
93 Delaware Avenue
P.O. Box 549
Put-In-Bay, OH 43456-0549
419-285-2184
Rodney_Karr@nps.gov


Offerors interested in submitting a proposal, please read the entire attached Request for Proposal and all associated documents. Questions are due not later than 5:00 p.m., ET, 13 July 2016 to allow sufficient time for response prior to proposal submission.


Contractors are encouraged to offer their most advantageous/best proposal not later than 5:00 p.m., ET, 27 July 2016. Offers not received by the suspense date/time will not be considered for evaluation or award.


 

Files

Show all 21

Notice history

Notice Type Posted
PEVI - 201919 - Repointing the Memorial Column Latest Award Notice
This notice Award Notice
PEVI - 201919 - Memorial Repointing Project Original Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors