Pre-Proposal Conference: Repointing of the Memorial Column at Perry’s Victory & International Peace Memorial
P16PS00702
July 13, 2016
Meeting Notes
Ms. Barbara Fearon, General Superintendent, NPS, Perry’s Victory & International Peace Memorial
Mr. Rick Rampi, Project Manager, NPS, Denver Service Center
Ms. Monica Divelbess, Contract Specialist, NPS, Denver Service Center
Mr. Rodney Karr, Acting Facility Manager, NPS, Perry’s Victory & International Peace Memorial
Mr. Rampi: introduction and Monument history and repair history
• Past repairs, contract reviews, what to expect when working, what to look for when working
• NPS no longer awards contracts based on lowest bid, but based on technical quality and price
Ms. Fearon: Remember NPS heritage resources, visitors, and safety will influence work environment
Mr. Karr: Review of island, U.S. Canada border, Battle of Lake Erie, Memorial
• Importance of this project
• Limit questions made to park staff, they cannot answer project related questions
Ms. Divelbess: (See slides), Solicitation is best value
• Closing Date may change based on questions
• “best value” award based on technical quality and price
• Discussions may be opened
• Submit a minimum of 3 and no more than 8 relevant projects
• Section K contractors need to submit using SAM System o What is SAM, there is time to register with the system before the bid o Proposed equals=name brands, need to let NPS know substitute brands
• Questions due July 20th, will be released in amendment o NPS will extend deadline if needed based on questions
• Seasonal climate will affect work, for example do paperwork in winter, contractors must exercise time management
• NPS will only accept electronic submissions, submission NEED TO BE ON TIME, allow time for technical difficulties that might occur during file uploading
• File size limit 25mb, multiple submissions allowed
• Contractor will receive a neutral rating if no past performance is submitted
Mr. Rampi: Contractors need to relate experience and past performance to this project
• Please provide contact information for material suppliers from past performances
• NPS likes to partner with contractors, here to work together
• Contactors face seasonal challenge, complete project in one season!
Question: Monument access, will the column be closed?
• Yes, but NPS staff can enter, contractors need to keep public out, and provide safety
Mr. Karr: For security and safety, NPS will coordinate with the responsible party
Ms. Fearon: Park will be open, but Monument structure will be closed
• Expect hundreds of visitors on park grounds daily
• Monument is very important to island businesses/community
• NPS maintenance will need access during project
Question: will construction inspection officer be present during project?
• Yes, quality control, joints need to hold in order to hold the mortar
Mr. Rampi: Any problems receiving specs? No
• Presentation, history of project
• Column’s physical specs
• Plaza, upper plaza load restrictions, concrete in bad condition
• Column has numbered blocks and joints
• Past joint repair: original mortar was used o Then silicon was used which traps water (1982)
• Height challenge, unable to easily maintain or inspect column
• 2011 Phase 1 project was swing stage access
• 2014-2015 studies/investigation: best material for repair o 3 mockups areas and others to test, included winter test on how temperature change affected materials o Original mortar and mixture before project had the best results
• Quality control: A/E experienced with high rise structures and mortar will supervise project
• Contractors will conduct an on-site test mockup and meet those expectations throughout the project
• Contractors need to be aware of joint shrinkage and of the cracks/micro-cracks in 2014-15 mockups
• Contractors need to transport mortar and be aware of time need to do so
• Attention to detail, if contractor only has brick experience the bid will not receive as high as a rating
• Preferred if QC inspectors and supervisors are contractor’s employees
• Swing stage safety: plan needed
• NPS and mason will work together
• QC: an A/E hire will be a conflict of interest because A/E is already working with NPS, use independent, a testing agency that works with mortar will score high
• No issue with bonding: mortar is best material
• Limit on grinding (historical structure), contractor will need to remove silicon
Question: use/inspection of elevator, certificate name?
• Mr. Rampi: contract specifies that elevator is used for personnel not materials, supplies need to be hoisted to upper plaza
• Ms. Fearon: Historic original elevator car, need to protect elevator car
• Mr. Karr: training on elevator operation will be provided, information for service contact will be provided
Mr. Rampi: cleaning system, if training needed it can be done in-house
• Water and power access available
• Restroom access, contractor will clean restrooms or provide portable restrooms
• Basement can be used for project office
• Island has ash plant for sand
• Lodging booked in summer, high rates to stay on island, save on ferry fees
• Mainland cheaper rates
• Rent houses
• hard to find hotel with per diem
Ms. Fearon: extended ferry schedule in summer vs winter’s limited schedule, hard to transport vehicles in summer
Meeting end – participants then toured project site with NPS